FACSIMILE TRANSMISSION

PIDC House, Dr. Ziauddin Ahmed Road, P. O. Box 3942,


Karachi-75530,Pakistan
Telephones PABX : 92-21-111-568-568 (UAN)
: 92-21-35651480-89 (10 Lines)
Fax : 92-21-35680005 and 92-21-35682125
PAKISTAN PETROLEUM LIMITED E-Mail : info@ppl.com.pk
Website : www.ppl.com.pk

Message Ref. No: JO 17.7/ No.of Pages : 01 21 September, 2023


FOR: GHPL ATTN: MR. IFTIKHAR ABBASI iftikhar.abbasi@ghpl.com.pk
AROL ATTN: MR. MATEEN AHMED Mateen.Ahmed@uep.com.pk
COPY: DGPC ATTN: MR. KASHIF ALI 051 9213245

FROM: MD,PPL

GAMBAT SOUTH PRODUCTION REPORT FOR DATE : 20-9-2023

SALES / PRODUCTION DATA GPF- I GPF- II GPF-III GPF-IV

S.N PARAMETERS UNIT SALES


1 GAS SALES MMSCFD - - - 38.56
2 PROCESSED GAS CALORIFIC VALUE BTU/SCF - - - 951.7
3 WOBBE INDEX BTU/SCF - - - 1129
4 TRANSMISSION LINE INJECTION PRESSURE PSIG - - - - - - 796 805
5 AVERAGE CO2 CONTENT MOL % - - - 1.698
6 AVERAGE H2S CONTENT PPM - - - -
7 HCDP DEG F - - - 23.00
8 AVERAGE WATER CONTENTS LB/MMSCF - - - 3.810
9 AVERAGE SALE GAS TEMPERATURE DEG F - - - 108.59
10 LPG SALE M.TONS - - - -
NRL BARRELS - - - 654.1
11 CONDENSATE SALE PARCO BARRELS - - - -
EPRF BARRELS - - - -
TRAFIGURA BARRELS - - - -

GAS PRODUCED, SALES AND OTHER FIGURES ARE BASED ON INSTRUEMENTS INSTALLED AT THE PLANT

S.N PARAMETERS UNIT AVERAGE AVERAGE AVERAGE AVERAGE


1 GAS FEED FROM WELL MMSCFD 7.25 - - 46.51
MIXING FROM GPF-II TO GPF-IV MMSCFD - - - -
2 GAS CONSUMED MMSCFD 0.408 0.000 - 2.650
3 GAS SHRINKAGE MMSCFD 0.660 - - 11.87
4 GAS FLARED / PURGED MMSCFD 0.010 0.000 - 0.050
5 LPG PRODUCED M.TONS - - - -
6 LPG STOCK M.TONS - 23.12 - -
7 CONDENSATE PRODUCED BARRELS 65.7 - - 500.7
8 CONDENSATE STOCK BARRELS 663.0 337 - 2172
9 WATER PRODUCED BARRELS 825.00 - - 295.0
10 PLANT OPERATIONAL TIME HOURS 24.00 - - 24.00

WELL & FEEDERLINE DATA


SHAHDADPUR SHAHDADPUR ZAFIR KABIR
SHAHDADPUR FIELD HADAF FIELD
S.N PARAMETERS UNIT WEST FIELD EAST FIELD FIELD FIELD

SHAHDAD X-1 SHARF X-1 SHARF-2 SHARF-3 WAFIQ X-1 NASR X-1 KINZA X-1 HADAF X-1 ZAFIR X-1 KABIR X-1

1 GAS PRODUCED MMSCFD 7.25 0.00 0.00 11.41 - 25.087 0.000 9.205 - 0.800
2 GAS SALES MMSCFD 6.172 0.00 0.00 6.87 - 16.407 0.000 8.328 - 0.784
3 GAS CONSUMED MMSCFD 0.408 0.000 0.000 1.771 - 0.652 0.000 0.226 - 0.000
4 GAS SHRINKAGE MMSCFD 0.660 0.00 0.00 3.19 - 8.028 0.000 0.640 - 0.016
5 GAS FLARED / PURGED MMSCFD 0.010 0.000 0.000 0.040 - 0.000 0.000 0.010 - 0.000
6 LPG PRODUCED M.TONS - - - - - - - - - 0.000
7 CONDENSATE PRODUCED BARRELS 65.7 - - 158.6 - 189.49 - 64.44 - 88.21
8 WATER PRODUCED BARRELS 825.00 0.00 0.00 138.09 - 122.64 - 32.68 - 1.586
9 CHOKE SIZE INCH 47 /64" 0 /64" 0 /64" 48 /64" - 60 /64" 0 /64" 78 /64" - 25 /64"
10 WELL FLOWING TIME HOURS 24.00 - - 24.00 - 24.00 - 24.00 - 24.00
11 WELL HEAD PRESSURE PSIG 2190 1910 2010 1880 - 2400 480 1240 - 1280
12 FEEDER LINE FLOWING PRESSURE PSIG 650 - - 1220 - 1135 100 1195 - 1205
13 FEEDER LINE TEMPERATURE DEG F 190 104 102 200 - 160 120 175 - 115

REMARKS WELL FLOWING STATUS

GPF-I sale gas : 6.172 MMscfd Shahdad X-I ------ GPF-I


Kinza X-I----GPF-II
GPF-I average Gas Heating Value : 1088.800 BTU/SCF
Total Sale Gas Volume from Field is 38.56 MMscfd Sharf-2 ---- GPF-IV
Sharf-3, Kabir X-I & Nasr X-I ---- GPF-IV
Increamentel Sale Volume is 31.93 MMscfd Hadaf X-I----GPF-IV (0.2 MMscfd is utilized at GPF-III genset as fuel gas)
Mixing sale gas from GPF-II at GPF-IV metering is 6.63 MMscfd Sale gas flow is being delivered thru single metering from GPF-IV.
GPF-II Facility shutdown for ATA

This is a system generated report