NO JENIS / GAMBAR PEKERJAANN

I PEKERJAAN KUSEN
1 PEKERJAAN KUSEN
1. KUSEN PINTU

2. PASANGAN BATA TASRAM


3. PASANGAN BATA

4. PLESTERAN DAN ACI

5. SPONENGAN DAN TALI AIR


6. PASANGAN KERAMIK

7. PASANGAN BATU ALAM

8. FINISHING PELAT LUIVEL


KELOMPOK 2:

PERHITUNGAN VOLUME

VOL = LUAS PENAMPANG x PANJANG PONDASI


1. LUAS PENAMPANG
= 0,5 x (A + B) x C
= 0,5 x (0,60 + 0,25) x 0,8
= 0,5 x 0,85 x 0,8
= 0,34 m3
2. PANJANG PONDASI
0,3m³
PANJANG HORIZONTAL
= 8m + 5,25 m + 2,75 m + 2,25 m + 3 m + 2,75 m + 3 m
+ 3m + 2m + 3m + 2,5m
= 37,5 m
PANJANG VERTICAL
= 14 m + 3,25 m + 4 m + 1,5 m + 3 m + 2,75 m + 1 m
+ 1,2 m + 1,25 m + 14 m
= 46m 3,75m
PANJANG KESELURUHAN
= 37,5 m + 46 m
= 83,5 m

46m

83,5m

VOL = TINGGI TASRAM x PANJANG TASRAM


1. TINGGI TASRAM (PADA UMUMNYA)
= 0,3 m
2. PANJANG TASRAM 0,3m
= JUMLAH PANJANG DINDING - PANJANG LUBANG
PINTU
= 76,2 m - 7,1 m
= 69,1 m
3. PANJANG LUBANG - LUBANG PINTU 69,1m
P1 = 0,92 x 2 = 1,84 m
P2 = 0,92 x 2 = 1,84 m
P3 = 0,92 x 2 = 1,84 m
P4 = 0,82 x 2 = 1,64 m
TOTAL = 1,8 + 1,8 + 1,8 + 1,64 m
= 7,04 m
4. PASANGAN BATA TASRAM
VOL = TINGGI TASRAM x PANJANG TASRAM
= 0,3 m x 69,1 m 7,04m
= 20,73 m²
P4 = 0,82 x 2 = 1,64 m
TOTAL = 1,8 + 1,8 + 1,8 + 1,64 m
= 7,04 m
4. PASANGAN BATA TASRAM
VOL = TINGGI TASRAM x PANJANG TASRAM
= 0,3 m x 69,1 m 7,04m
= 20,73 m²

20,73 m²
PASANGAN BATA
VOL = (TINGGI PASANGAN BATA x PANJANG
PASANGAN
BATA) - LUAS BUKAAN.
1. TINGGI PASANG BATA
= 3,5 m 3,5m
2. PANJANG PASANG BATA
= 59 m
3. LUAS BUKAAN = 59m
P1 = 0,75 x 1,83 x 1 unit
= 1,4 m2
P2 = 0,75 x 2,16 x 1 unit
= 1,62 m2
P3 = 0,75 x 2,16 x 3 unit
= 4,86 m2
P4 = 0,75 x 2,16 x 1 unit
= 1,62 m2
J1 = 0,75 x 1,83 x 1 unit
= 1,4 m2
J2 = 0,75 x 1,83 x 1 unit
= 1,4 m2
J3 = 0,75 x 1,83 x 1 unit
= 1,4 m2
J4 = o,75 x 1,83 x 2 unit
= 2,7 m2
J5 = 0,75 x 0,98 x 1 unit
= 0,73 m2
TOTAL BUKAAN = 1,4 + 1,62 + 1,4 + 1,4 + 0,73 + 4,86 +
1,62 + 1,4 + 2,7 = 13,13 m2.
4. PASANGAN BATU BATA
VOL = (TINGGI PASANG BATA x PANJANG PASANG
BATA) - LUAS BUKAAN
= ( 3,5 m x 59 m ) - 17,13 m
= 206,5 - 17,13 m
= 109,37 m2.
13,13m²

109,37m²
VOL = (2 x LUAS PASANGAN BATA) - LUAS KERAMIK
DINDING DAN BATU ALAM

= (2 x 109,37) m² - (11,7 + 2,47 + 5) m


= 218,74 m² - 19,17 m
= 199,34 m² 199,34 m²
VOL = PANJANG TRASRAM - LUBANG PINTU x 0,02
1. PANJANG TRASRAM
= JUMLAH PANJANG DINDING - PANJANG LUBANG
PINTU
= 76,2 m - 7,1 m
= 69,1 m 69,1 m
2. PANJANG LUBANG - LUBANG PINTU
P1 = 0,75 x 1,83 x 1 unit
= 1,4 m2
P2 = 0,75 x 2,16 x 1 unit
VOL = PANJANG TRASRAM - LUBANG PINTU x 0,02
1. PANJANG TRASRAM
= JUMLAH PANJANG DINDING - PANJANG LUBANG
PINTU
= 76,2 m - 7,1 m
= 69,1 m 69,1 m
2. PANJANG LUBANG - LUBANG PINTU
P1 = 0,75 x 1,83 x 1 unit
= 1,4 m2
P2 = 0,75 x 2,16 x 1 unit
= 1,62 m2
P3 = 0,75 x 2,16 x 3 unit
= 4,86 m2
P4 = 0,75 x 2,16 x 1 unit
= 1,62 m2
TOTAL = 1,4 + 1,62 + 4,86 + 1,62
= 9,47 m
3. SPONENGAN DAN TALI AIR
VOL = PANJANG TRASRAM - LUBANG PINTU x 0,02
= 69,1 - 9,47 x 0,02 9,47 m
= 59,63 x 0,02
= 1,1926 m1

1,1926 m1

VOL = LUAS KERAMIK YANG DIPASANG


= (7,75m x 3,00m) + ( 5,00 x 6,75)
57 M2
= 23,25m + 33,75m
= 57 M2

VOL = LUAS BIDANG YANG DIPASANG BATU ALAM


= (3,15 m x 0,5 m) + (3,15 m x 0,5 m) + (1,2 m x 3,5 m)
7,35 m²
= 1,575 m + 1,575 m + 4,2 m
= 7,35 m2

VOL = LUAS BIDANG PELAR LUIVEL


= ( 4,39 m x 0,65 m ) + ( 0,49 m x 0,65 m )
3,172 m²
= 2,8535 + 0,3185
= 3,172 m²
VOL = LUAS BIDANG PELAR LUIVEL
= ( 4,39 m x 0,65 m ) + ( 0,49 m x 0,65 m )
3,172 m²
= 2,8535 + 0,3185
= 3,172 m²