Back Up Data ( Perhitungan Volume )

Pekerjaan : PEMBANGUNAN PUSK. SAITI


BANGUNAN BARU
Lokasi : SAITI
Tahun Anggaran : 2016

I. PEKERJAAN PENDAHULUAN

1 Volume, Pas. Batu Bata 1/2 Batu Camp. 1 : 5

UNTUK PENAMBAHAN PASANGAN BATU DI ATAS RINGBALOK


HORIZONTAL
Segmen 1
C.3 - G.1 = 3.85 m x 1.00 = 3.85 M2
C.3 - D = 0.35 m x 3.50 = 1.23 M2
G - G.1 = 0.35 m x 3.50 = 1.23 M2
Segmen 3
B-I = 14.25 m x 0.5 = 7.13 M2
Segmen 5
B-I = 14.25 m x 0.5 = 7.13 M2
Segmen 6
B-I = 14.25 m x 0.5 = 7.13 M2
Segmen 7
B-I = 12.40 m x 0.5 = 6.20 M2
Segmen 8
A-B = 0.85 m x 0.5 = 0.43 M2
H-I = 0.85 m x 0.5 = 0.43 M2
56.85
VERTIKAL
Segmen B
3-5 = 3.70 m x 0.5 = 1.85 M2
6-7 = 2.85 m x 0.5 = 1.43 M2
Segmen B.1
5-6 = 1.85 m x 0.5 = 0.93 M2
Segmen C
3-5 = 3.70 m x 0.5 = 1.85 M2
6-7 = 2.85 m x 0.5 = 1.43 M2
Segmen C.1
7-9 = 1.85 m x 0.5 = 0.93 M2
Segmen C.3
1-2 = 1.35 m x 1.0 = 1.35 M2
Segmen D
3-5 = 3.70 m x 0.5 = 1.85 M2
Segmen G
3-5 = 3.70 m x 0.5 = 1.85 M2
Segmen G.1
1-2 = 1.35 m x 1.0 = 1.35 M2
7-9 = 2.40 m x 0.5 = 1.20 M2
Segmen H
3-5 = 3.70 m x 0.5 = 1.85 M2
Segmen H.1
6-7 = 2.85 m x 0.5 = 1.43 M2
Segmen H.2
5-6 = 1.85 m x 0.5 = 0.93 M2
Segmen I
3-5 = 3.70 m x 0.5 = 1.85 M2
6-7 = 2.85 m x 0.5 = 1.43 M2
44.25 58.20 M2

UNTUK PENAMBAHAN PASANGAN BATU PERUBAHAN DENAH

HORIZONTAL

Segmen 3
B-C = 2.85 m x 2.6 = 7.41 M2
H-I = 2.35 m x 2.6 = 6.11 M2
Segmen 4
B-C = 2.70 m x 3.5 = 9.45 M2
Segmen 6
B - G.2 = 9.50 m x 2.6 = 24.70 M2
Segmen 7
B - G.2 = 6.50 m x 2.6 = 16.90 M2
VERTIKAL

Segmen B.2
4-5 = 1.35 m x 3.5 = 4.73 M2
Segmen E
6-7 = 2.85 m x 3.5 = 9.98 M2
Segmen F
6-7 = 2.85 m x 3.5 = 9.98 M2
30.95 89.245
Jumlah = ### M2
PENGURANGAN

Diketahui :
Pasangan Kusen
P2 = 1.22 x 2.67 x 2.000 = 6.515 m2
P1 0.9 x 2.22 x 1.000 = 1.998 m2
P3 = 0.8 x 2.22 x 1.000 = 1.776 m2
PV = 0.9 x 2.52 x 2.000 = 4.536 m2
1.64 x 0.50 x 2.000 = 1.640 m2
PJ1 = 1 x 2.50 x 1.000 = 2.500 m2
1.64 x 1.75 x 1.000 = 2.870 m2
J2 = 2.59 x 1.75 x 3.000 = 13.598 m2
J1 = 2.59 x 1.75 x 1.000 = 4.533 m2
V1 = 1.05 x 0.50 x 2.000 = 1.050 m2
V2 = 0.55 x 0.50 x 2.000 = 0.550 m2
V3 = 2.51 x 0.50 x 1.000 = 1.255 m2
42.820 m2

Jumlah = 42.820 M2

Pasangan Batu Bata 1/2 Batu = 104.63 M2

5 Volume, Pas.Plesteran Dinding 1 : 5

a). Pas, Plesteran Dinding


Diketahui :
* Luas Bersih Dinding Pas. Bata 1 : 5 = 104.625
* Luas Pas. Keramik Dinding Km = 9.200 m
Penyelesaian :
Jadi Volume Pas. Plesteran 1 : 5 = 95.425 m
= 95.425 x 2 Sisi
M Total = 190.850 +

Volume, Pas.Plesteran Dinding 1 : 5 = 190.85 M


PEK. PLESTERAN BETON
Kolom Teras (25 x 35) = 1.200 x 2.900 x 6.000 = 20.880 M2
= 1.200 x 3.500 x 4.000 = 16.800 M2

Balok Topi Teras (10 x 30 = 0.100 + 0.600 x 20.000 = 1.200 M2


Jumlah = 38.880 M2
6 Volume, Acian Dinding, Kolom, Dan Pondasi

Diketahui :
* Acian Beton = 38.880 m

* Volume, Acian Dinding = 190.85 m

Penyelesaian :
** Jadi Volume, Acian Dinding, Kolom, Dan Pondasi
M = 38.880 + 190.85
M Total = 229.73 m

Volume, Acian Dinding, Kolom, Dan Pondasi 1 : 7 = 229.73 M

8 Volume. Pas.Lantai Keramik 60 x 60 Cm

Diketahui :
1 * Rg. Loket = 6.698 m
2 * Rg. Poli KIA = 10.973 m
3 * Rg. Poli Umum 1 = 10.973 m
4 * Rg. Poli Umum 2 = 10.973 m
5 * Rg. Apotek = 10.973 m
6 * Rg. Koridor 1 = 25.623 m
= 1.823 m
= 5.550 m Segmen 6 - 7 (E - F)
7 * Rg. Staff 1 = 8.123 m
8 * Rg. Staff 2 = 9.548 m Segmen 6 - 7 (C - E)
9 * Rg. Staff 3 = 12.398 m Segmen 6 - 7 (F - H.1)
10 * Rg. Obat = 5.273 m
11 * Rg. Teras Keliling = 33.750 m
= 6.563 m
= 24.550 m
= 13.400 m
Luas Total = 197.185 m

Volume. Pas.Lantai Grani 40 x 40 Cm = 27.495 M

9 Volume. Pas.Lantai Keramik Wafel 20 x 20 Cm ( Km/Wc )

Penyelesaian :
Volume. Pas. Keramik 20 x20 Lantai Km / Wc.
* Wc/Km Type B (1,5 x 1,5) 1 Unit = 1.823 m

Luas Total = 1.823 m

Volume. Pas.Lantai Keramik Wafel 20 x 20 Cm ( Km/Wc ) = 1.823 M

10 Volume. Pas.Dinding Keramik Km / Wc 20 x 40 Cm, Tinggi = 2,0 m

Diketahui :

* Wc/Km Type B (1,5 x 1,5) 1 Unit = 4.600 m

4.600 m
Penyelesaian :
** Jadi Volume. Pas. Keramik 20 x 20 Dinding Km / Wc. Tinggi = 2 m
M Total = 9.200 m 9.200

Volume. Pas.Dinding Keramik Km / Wc 20 x 25 Cm, T = 2,00 m = 9.200 M

IV. PEKERJAAN BETON.

1 Volume, Pek. Sloof 15/20 K. 175

Diketahui :
Horizontal
Segmen 2.a
A-B 0.85
I-J 0.85
Segmen 2.a
B-C 2.85
Segmen 8
A-B 0.85
I-J 0.85
Vertikal
Segmen E
6-7 2.85
Segmen F
6-7 2.85

Panjang Total = 11.950 m


* Lebar Sloof = 0.15 m
* Tinggi Sloof = 0.20 m

Penyelesaian :
** Jadi Volume, Pek. Sloof 12/20 K. 175
M = 11.950 x 0.15 x 0.20
M Total = 0.359 m

Volume, Pek. Sloof 15/20 K. 175 = 0.359 M3


11.95 m
2 Volume, Pek. Kolom Praktis K. 175

Diketahui :
* Luas kolom Prkatis 12 x 12 cm K. 175 = 0.014 m
* Tinggi kolom Praktis = 0.50 m
* Jumlah Kolom = 33 Bh
Jumlah = 16.50 m

* Luas kolom Prkatis 12 x 12 cm K. 175 = 0.014 m


* Tinggi kolom Praktis = 3.50 m
* Jumlah Kolom = 14 Bh
Jumlah = 49.00 m

Total Panjang = 65.50 m

Penyelesaian :
** Jadi Volume pek.Kolom Praktis K. 175
M = 0.014 x 65.50
M Total = 0.943 m

Volume, Pek. Kolom Praktis K. 175 = 0.943 M3


65.50 M

3 Volume, Pek. Kolom Praktis 15/25 K. 175

Diketahui :
* Luas Penampang kolom 15/25 = 0.038 m
* Tinggi kolom Praktis/ Buah = 1.650 m
* Jumlah kolom = 6 Bh
0.371
* Tinggi kolom Praktis/ Buah = 0.500 m
* Jumlah kolom = 2 Bh
0.038
* Tinggi kolom Praktis/ Buah = 3.500 m
* Jumlah kolom = 2 Bh
0.263

Volume, Pek. Kolom Praktis 12/40 K. 175 = 0.671 M3


17.90 m

7 Volume, Pek. Ring Balk 12/25 K. 175, Elv. + 3

Diketahui : Panjang Ring Balok Adalah :

* Panjang Ring Balk 12/25 Horisontal = 28.95 m Segmen 1 s/d 8 (3,85+2,6x4+1x2x4+3,35*2)


* Panjang Ring Balk 12/25 Vertikal = 34.50 m Segmen B s/d I (13,5x2+2x2+1,75x2)
Panjang Total = 63.45 m
* Luas Penampang Ring Balk 12/25 = 0.030 m

Penyelesaian :
** Jadi Volume pek. Ring Balk 12/25 K. 175
M = 63.45 x 0.030
M Total = 1.904 m

Volume, Pek. Ring Balk 12/30 K. 175 = 1.904 M3


63.45 m

Volume, Pek. Ring Balk 12/15 K. 175, Elv. + 3.65


* Luas Penampang Ring Balk 12/15 = 0.018 m
Segmen 1 (C.3 - G.1) = 3.85
Segmen 2 (B - C.3) = 5.35
(G.1 - I) = 5.35
Segmen 3 (B - I) = 14.25
Segmen 4 (B - C) = 2.73
Segmen 5 (B - I) = 14.25
Segmen 6 (B - E) = 6.11
(F - I) = 6.11
Segmen 7 (B - I) = 14.25
Segmen B (2 - 5) = 6.50
('6 - 7) = 3.00
Segmen B.1 (5 - 6) = 2.00
Segmen B.2 (4 - 5) = 1.50
Segmen C (3 - 5) = 4.00
('6 - 7) = 3.00
Segmen C.3 (1 - 3) = 4.00
Segmen D (3 - 5) = 4.00
Segmen E (6 - 7) = 3.00
Segmen F (6 - 7) = 3.00
Segmen G (3 - 5) = 4.00
Segmen G.1 (1 - 3) = 4.00
Segmen H (3 - 5) = 4.00
Segmen H.1 (6 - 7) = 3.00
Segmen H.2 (5 - 6) = 2.00
Segmen I (3 - 5) = 6.50
('6 - 7) = 3.00
132.75 - 55.95 = 76.80 M1
Penyelesaian :
** Jadi Volume pek. Ring Balk 12/20 K. 175
M = 132.75 x 0.018
M Total = 2.390 m

Volume, Pek. Ring Balk 12/30 K. 175 = 2.390 M3


132.75 m

11 Volume, Pek. Plat Atap, T = 10 Cm


Lebar 1 Meter = 10.90 x 2.00 = 21.80 m
= 21.80 x 1.00 x 0.10 = 2.18 M3
Lebar 2 Meter = 3.35 x 2.00 = 6.70 m
= 6.70 x 2.00 x 0.10 = 1.34 M3
Lebar 0,3 Meter = 21.15 x 0.30 = 6.35 m
= 6.35 x 0.30 x 0.10 = 0.19 M3
Jumlah Total Volume Plat Beton = 3.71 M3
37.10 m

Kuda - Kuda Kayu Kls II


Kuda - Kuda K.1 = 3.000 Bh
Balok 8/12 = 14.660 + 7.200 + 12.40 = 34.260 M1
= 34.260 x 0.010 x 3 = 0.987 M
Balok 8/12 = 11.580 + 3.460 = 3.460 M1
= 3.460 x 0.010 x 3 = 0.100 M
1/2 Kuda - Kuda
Balok 8/12 = 17.940 + 7.330 + 7.34 = 32.610 M1
= 32.610 x 0.010 x 2 = 0.626 M

Balok Nok
Balok 6/10 = 3.500 0.006 = 0.021 M

Balok Skor 5/7


Balok 5/7 = 2.00 x 4 x 0.004 = 0.028 M
Jumlah 1.761 M

Gording Kuda - Kuda Kayu Kls II


Kuda - Kuda K.
Belakang Balok 5/7 = 8 x 2.31 x 2= 36.960 M1
4.6 + 3.50 = 8= 45.070 M1
45.070 x 0.050 x 0.070 = 0.158 M
T. Samping = 5.00 x 12.68 x 2= 126.800 M1
126.800 x 0.050 x 0.070 = 0.444 M
T. Depan = 9.83 x 10.00 - 13 = 85.275 M1
85.275 x 0.050 x 0.070 = 0.298 M

Jumlah = 0.900 M

1 Volume. Pek. Rangka Atap Baja Ringan

I. Luas Rangka Atap Baja Ringan Tampak Depan


Diketahui :
a). Atap Bagian Tengah Bawah ( Teras)
* Panjang Ambang Bawah = 5.19 m
* Panjang Ambang Atas = 0.00 m
* Tinggi = 3.00 m
Volume = 5.19 + 0.00 x 3.00 = 7.79 m
2
b). Atap Bagian Tengah Atas
* Panjang Ambang Bawah = 9.27 m
* Panjang Ambang Atas = 3.50 m
* Tinggi = 3.33 m
Volume = 9.27 + 3.50 x 3.33 = 21.26 m
2
c). Atap Tampak Samping (kanan)
* Panjang Ambang Bawah = 4.36 m
* Panjang Ambang Atas = 4.36 m
* Tinggi = 4.00 m

Volume = 4.36 + 4.36 x 4.00 = 17.44 m


2
Segitiga 1.390 x 1.000 x 0.500 = 0.70 m
18.135
d). Atap Tampak Depan (kiri)
* Panjang Ambang Bawah = 4.36 m
* Panjang Ambang Atas = 4.36 m
* Tinggi = 4.00 m

Volume = 4.36 + 4.36 x 4.00 = 17.44 m


2
Segitiga 1.390 x 1.000 x 0.500 = 0.70 m
18.135
Jumlah = 65.317 M2
II. Luas Rangka Atap Baja Ringan Tampak Samping Kiri
Diketahui :
a). Atap Bagian Kiri ( Teras)
* Panjang Ambang Bawah = 2.42 m
* Panjang Ambang Atas = 2.42 m
* Tinggi = 3.00 m
Volume = 2.42 + 2.42 x 3.00 = 7.26 m
2
b). Atap Bagian Kanan Bangunan Lama
* Panjang Ambang Bawah = 12.69 m
* Panjang Ambang Atas = 0.00 m
* Tinggi = 7.33 m
Volume = 12.69 + 0.00 x 7.33 = 46.51 m
2
Jumlah = 53.769 M2
III. Luas Rangka Atap Baja Ringan Tampak Samping Kanan
Diketahui :
a). Atap Bagian Kanan ( Teras)
* Panjang Ambang Bawah = 2.42 m
* Panjang Ambang Atas = 2.42 m
* Tinggi = 3.00 m
Volume = 2.42 + 2.42 x 3.00 = 7.26 m
2
b). Atap Bagian Kanan Bangunan Lama
* Panjang Ambang Bawah = 12.69 m
* Panjang Ambang Atas = 0.00 m
* Tinggi = 7.33 m
Volume = 12.69 + 0.00 x 7.33 = 46.51 m
2
Jumlah = 53.769 M2
IV. Luas Rangka Atap Baja Ringan Tampak Belakang (Bangunan Lama)
Diketahui :
a). Atap Bagian Tengah Atas
* Panjang Ambang Bawah = 4.61 m
* Panjang Ambang Atas = 3.50 m
* Tinggi = 0.64 m
Volume = 4.61 + 3.50 x 0.64 = 2.60 m
2
b). Atap Tampak Samping (kanan)
* Panjang Ambang Bawah = 2.31 m
* Panjang Ambang Atas = 2.31 m
* Tinggi = 6.68 m

Volume = 2.31 + 2.31 x 6.68 = 15.43 m


2
Segitiga 1.390 x 1.000 x 0.500 = 0.70 m
16.126
c). Atap Tampak Depan (kiri)
* Panjang Ambang Bawah = 2.31 m
* Panjang Ambang Atas = 2.31 m
* Tinggi = 6.68 m

Volume = 2.31 + 2.31 x 6.68 = 15.43 m


2
Segitiga 1.390 x 1.000 x 0.500 = 0.70 m
16.126
Jumlah = 34.847 M2
*** Luas total pas. Rangka Atap = 65.317 + 53.77 + 53.77 + 34.85

M Total = 207.702 m

Volume.Pek. Pas. Rangka Atap = ### M

2 Volume. Pek. Pas. Atap

Volume.Pek. Pas. Atap = ### M

3 Volume. Pek. Bumbungan Atap

Diketahui :
* Panjang Bumbungan = 5.93 m
* Panjang Talang Jurai = 43.22 m
* Panjang Talang Jurai Dalam = 7.34 m

4 Volume. Pas. Rangka + Penutup Plafon Gypsum

Diketahui : Plafond Elv. + 3.40


* Segmen 7 - 9 (C.1 - G.2)
Datar Atas = 0.750 X 7.85 = 5.888 M
= 0.750 X 3.75 x 2.000 = 5.625 M
Datar Bawah = 0.650 X 6.65 x 1.000 = 4.323 M
Naikan dari Bawah = 0.100 X 6.65 x 1.000 = 0.665 M
(Luar) 0.100 X 3.00 x 2.000 = 0.600 M
Naikan Atas = 0.200 X 6.35 x 1.000 = 1.270 M
(Dalam) 0.200 X 3.00 x 2.000 = 1.200 M
* Segmen 6 - 7 (B - C)
= 2.850 X 2.85 = 8.123 M
* Segmen 6 - 7 (C - D)
= 3.350 X 2.85 = 9.548 M
* Segmen 6 - 7 (E - F)
Datar Atas = 0.750 X 3.75 x 2.000 = 5.625 M
Datar Bawah = 0.650 X 4.65 x 1.000 = 3.023 M
Naikan dari Bawah = 0.100 X 4.65 x 2.000 = 0.930 M
(Luar)
Naikan Atas = 0.200 X 4.35 x 2.000 = 1.740 M
(Dalam)
* Segmen 6 - 7 (F - H.1)
= 4.350 X 2.85 = 12.398 M
* Segmen 6 - 7 (H.1 - I)
= 1.870 X 2.85 = 5.330 M

* Segmen 5 - 6 (B.1 - H.2)


Datar Atas = 0.750 X 13.85 x 1.000 = 10.388 M
= 0.750 X 6.00 x 2.000 = 9.000 M
Datar Bawah = 0.650 X 12.65 x 1.000 = 8.223 M
Naikan dari Bawah = 0.100 X 12.35 x 2.000 = 2.470 M
(Luar)
Naikan Atas = 0.200 X 12.65 x 2.000 = 5.060 M
(Dalam)
* Segmen 4 - 5 (B - B.2)
= 1.350 X 1.35 = 1.823 M
* Segmen 4 - 5 (B.2 - C)
= 1.350 X 1.35 = 1.823 M
* Segmen 3 - 4 (B - C)
= 2.850 X 2.35 = 6.698 M
* Segmen 3 - 5 (B - C)
= 2.850 X 3.85 = 10.973 M
(D - G) = 2.850 X 3.85 = 10.973 M
(G - H) = 2.850 X 3.85 = 10.973 M
(H - I) = 2.850 X 3.85 = 10.973 M
* Segmen 1 - 3 (B - I)
Datar Atas = 1.500 X 14.05 x 1.000 = 21.075 M
= 1.500 X 3.05 x 1.000 = 4.575 M
Datar Bawah = 0.600 X 14.85 x 1.000 = 8.910 M
= 0.600 X 5.50 x 2.000 = 6.600 M
= 0.600 X 1.10 x 2.000 = 1.320 M
= 0.600 X 2.20 x 2.000 = 2.640 M
= 0.600 X 2.65 x 1.000 = 1.590 M
Naikan dari Bawah = 0.100 X 13.65 x 1.000 = 1.365 M
(Luar) 0.100 X 5.50 x 2.000 = 1.100 M
0.100 X 2.65 x 1.000 = 0.265 M
0.100 X 1.10 x 2.000 = 0.220 M
Naikan Atas = 0.200 X 14.05 x 1.000 = 2.810 M
(Dalam) 0.200 X 5.50 x 2.000 = 2.200 M
0.200 X 1.50 x 2.000 = 0.600 M
0.200 X 3.05 x 1.000 = 0.610 M

Volume.Pas. Rangka + Penutup Plafon = ### M

6 Volume. Pas. List Profil Gipsum

Diketahui :
1 * Segmen 7 - 9 (C.1 - G.2) = 13.850 + 3.700 = 17.550 m
2 * Segmen 6 - 7 (B - C) = 5.700 + 5.700 = 11.400 m
3 * Segmen 6 - 7 (C - D) = 6.700 + 5.700 = 12.400 m
4 * Segmen 6 - 7 (E - F) = 3.150 + 3.150 = 6.300 m
5 * Segmen 6 - 7 (F - H.1) = 5.700 + 8.700 = 14.400 m
6 * Segmen 6 - 7 (H.1 - I) = 3.700 + 5.700 = 9.400 m
7 * Segmen 5 - 6 (B.1 - H.2) = 3.700 + 27.700 = 31.400 m
8 * Segmen 4 - 5 (B - B.2) = 2.700 + 2.700 = 5.400 m
9 * Segmen 4 - 5 (B.2 - C) = 2.700 + 2.700 = 5.400 m
10 * Segmen 3 - 4 (B - C) = 5.700 + 4.700 = 10.400 m
11 * Segmen 3 - 5 (B - C) = 5.700 + 7.700 = 13.400 m
12 * Segmen 3 - 5 (D - G) = 5.700 + 7.700 = 13.400 m
13 * Segmen 3 - 5 (G - H) = 5.700 + 7.700 = 13.400 m
14 * Segmen 3 - 5 (H - I) = 5.700 + 7.700 = 13.400 m
15 * Segmen 1 - 3 (B - I) = 29.700 + 7.800 = 37.500 m

Volume. Pas. List Profil Gipsum = ### m

7 Volume. Pas. Lisplank Klasi Boar L = 30 Cm

Diketahui :
A. Lisplank Tampak Belakang
* Panjang Bangunan Kiri = 3.590 m
* Panjang Bangunan Samp. Kanan = 3.590 m
Jumlah = 7.180 m

B. Lisplank Tampak Samp. Kanan


* Panjang = 12.690 m
= 1.550 m
Jumlah = 14.240 m
C. Lisplank Tampak Samp. Kiri
* Panjang = 12.690 m
= 1.550 m
Jumlah = 14.240 m
D. Lisplank Tampak Depan
* Panjang = 12.180 m
= 5.190 m
Jumlah = 17.370 m

** Jadi Volume. Pas. Lisplank 30 Cm


Volume. Pas. Lisplank Klasi Boart 30 Cm = 53.030 M
Cat 18.561 M2

VII. PEKERJAAN PENGECATAN

1 Volume, Pengecatan Dinding,Dan Kolom,

Diketahui :
Pengecetan Dinding Bangunan Lama = 76.80 x 2.500
= 192.000 M2
* Volume, Pengecetan Beton

Pasangan Kusen
P2 = 1.22 x 2.67 x 2.000 = 6.515 m2
P1 0.9 x 2.22 x 3.000 = 5.994 m2
PV = 0.9 x 2.52 x 3.000 = 6.804 m2
1.64 x 0.50 x 3.000 = 2.460 m2
PJ1 = 1 x 2.50 x 3.000 = 7.500 m2
1.64 x 1.75 x 3.000 = 8.610 m2
J3 = 1.77 x 1.75 x 1.000 = 3.098 m2
40.980 m2

Jumlah = 151.020
Pengecetan Dinding Lama = 151.020 x 2.00 = ### M2

* Volume, Pengecetan Dinding Dan Beton = 229.730 m

2 Volume.Pek. Pengecatan Plafon

Volume.Pek. Pengecatan Plafon = ### M

3 Volume. Pek. Pengecatan Lisplank

Volume. Pek. Pengecatan Lisplank = 18.561 M

4 Volume. Pek. Water Profing 37.10 x 1.00 = 37.10

Volume. Pek. Pengecatan Atap = 37.104 M


5 Volume. Pek. Pengecatan Kayu

Volume. Pek. Pengecatan Kayu = 31.298 M

VIII. PEKERJAAN SANITASI

1 Type/ Volume/
Jenis Pekerjaan
No. satuan

1 Pas. Closet Duduk 1.00 Bh


2 Pas. Wastafel 0.00 Bh
3 Pas. Kran Air Stainless 2.00 Bh
4 Pas. Floor Drain 1.00 Bh
5 Kichen Zink 1 Lobang 1.00 Bh
6 Pas. Pipa 4 inc Instalasi Air Kotor Dari Wc Ke Septictank 2.00 m
7 Hanger + Support Pipa PVC 4" (Sambungan Pipa) 1.00 set
8 Pas. Pipa 2,5" inc Instalasi Air Kotor Dari Wc Ke Saluran Pembuangan 2.00 m
9 Hanger + Support Pipa PVC 2,5" (Sambungan Pipa) 1.00 set
10 GIP 1/2" (Jaringan Di dalam Bangunan ) 21.00 m
11 Hanger + Support Pipa GIP 1/2" (Sambungan Pipa) 1.00 set
X. PEKERJAAN INSTALASI LISTRIK

Type/ Volume/
Jenis Pekerjaan
No. Jumlah

1 Pas. Instalasi Titik Mata Lampu 9.00 Ttk


2 Pas. Instalasi Saklar 11.00 Ttk
3 Pas. Lampu Down Light 20 Watt 0.00 Bh
4 Pas. Lampu Down Light 18 Watt 9.00 Bh
5 Pas. Saklar Ganda 3.00 Bh
6 Pas. Saklar Tunggal 3.00 Bh
7 Pas. Stop Kontak 1 Pase 5.00 Bh
8 Pas. Stop Kontak 2 Pase 0.00 Bh
9 Pas. Sekring Box ( MCB ) 1.00 Bh

PAS. BATU ANDESIT

Pada Dinding 1.33 x 3.74 x 2 = 9.948 M2

Pada Kolom 0.30 + 0.80 )x 3.25 = 3.575 M2

0.30 + 0.40 )x 2.86 x 2 = 4.004 M2


0.15 x 2 x 2.86 = 0.858 M2

Total = 18.385 M2
1. KG BESI SLOOF 15 x 20 cm (SL-1)

Luas Penampang Panjang Dalam Total


Jenis Balok L T (m2) (m1)
a b
Sloof 0.15 0.2 0.03 11.95
15 x 20 (SL-1)
Tulangan Lebar Balok Tinggi Balok
Beugel (Kurangi Selimut Beton) (Kurangi Selimut Beton)
(m1) (m1)
a b
0.1 0.15
Satuan Pjg Tul. Beugel Panjang Total Tululangan
(m1) (m1)
f=c+d+e g
0.65 11.95
Bakesting Lebar Panjang
m1 m1
0.40 11.95

3. KG BESI KOLOM PRAKTIS 15 x 25 cm (K-2)

Luas Penampang Panjang Dalam Total


Jenis Balok L T (m2) (m1)
a b
Kolom 0.12 0.22 0.0264 17.90
15 x 40 (K -3)
Tulangan Lebar Balok Tinggi Balok
Beugel (Kurangi Selimut Beton) (Kurangi Selimut Beton)
(m1) (m1)
a b
0.07 0.17
Satuan Pjg Tul. Beugel Panjang Total Tululangan
(m1) (m1)
f=c+d+e g
0.63 17.90
Bakesting Lebar Panjang
m1 m1
0.44 17.90

5. KG BESI RING BALOK PRAKTIS 12 x 15 cm (RB-1) Elv. + 4.00

Luas Penampang Panjang Dalam Total


Jenis Balok L T (m2) (m1)
a b
Balok 0.12 0.15 0.018 132.75
12 x 12 (RB -2)
Tulangan Lebar Balok Tinggi Balok
Beugel (Kurangi Selimut Beton) (Kurangi Selimut Beton)
(m1) (m1)
a b
0.07 0.1
Satuan Pjg Tul. Beugel Panjang Total Tululangan
(m1) (m1)
f=c+d+e g
0.49 132.75
Bakesting Lebar Panjang
m1 m1
0.30 132.75

5. KG BESI RING BALOK PRAKTIS 12 x 25 cm (RB-2) Elv. +3,1

Luas Penampang Panjang Dalam Total


Jenis Balok L T (m2) (m1)
a b
Balok 0.12 0.25 0.03 63.45
12 x 12 (RB -2)
Tulangan Lebar Balok Tinggi Balok
Beugel (Kurangi Selimut Beton) (Kurangi Selimut Beton)
(m1) (m1)
a b
0.07 0.2
Satuan Pjg Tul. Beugel Panjang Total Tululangan
(m1) (m1)
f=c+d+e g
0.69 63.45
Bakesting Lebar Panjang
m1 m1
0.40 63.45

9. KG BESI PLAT ATAP

Luas Penampang Panjang Dalam Total


Jenis Balok L T (m2) (m1)
a b
Plat 1 0.1 0.1 37.10

Tulangan Lebar Plat Tebal Plat


Pembagi (Kurangi Selimut Beton) (Kurangi Selimut Beton)
(m1) (m1)
a b
0.95 0
Satuan Pjg Tul. Pembagi Panjang Total Tululangan
(m1) (m1)
f=c+d+e g
0.95 37.10
Bakesting Lebar Panjang
m1 m1
1.10 37.10
Jml. Tulangan Besi Panjang Besi
Koefisien Besi
(Bh) (m1)
c d e=bxc f
4 12 47.80 0.006165

Panjang Lipatan
Tulangan Tulangan
(m1) (m1)
c d e
0.20 0.30 0.15
Jarak Beugel Besi Jml. Beugel Jumlah Panjang Besi
Koefisien Besi
(m1) Bh Pembulatan (m1)
h i j=g/h k l=fxk m
0.15 8 80.67 80 52.00 0.006165
Luasan Vol. Sat.Balok
m2 m3
4.78 0.00
Jumlah 4.78 m2

Jml. Tulangan Besi Panjang Besi


Koefisien Besi
(Bh) (m1)
c d e=bxc f
6 12 107.40 0.006165

Panjang Lipatan
Tulangan Tulangan
(m1) (m1)
c d e
0.14 0.34 0.15
Jarak Beugel Besi Jml. Beugel Jumlah Panjang Besi
Koefisien Besi
(m1) Bh Pembulatan (m1)
h i j=g/h k l=fxk m
0.15 8 120.33 120 75.60 0.006165
Luasan Vol. Sat.Balok
m2 m3
7.88 0.00
Jumlah 7.88 m2

Jml. Tulangan Besi Panjang Besi


Koefisien Besi
(Bh) (m1)
c d e=bxc f
4 12 531.00 0.006165
Panjang Lipatan
Tulangan Tulangan
(m1) (m1)
c d e
0.14 0.20 0.15
Jarak Beugel Besi Jml. Beugel Jumlah Panjang Besi
Koefisien Besi
(m1) Bh Pembulatan (m1)
h i j=g/h k l=fxk m
0.15 8 886.00 886 434.14 0.006165
Luasan Vol. Sat.Balok
m2 m3
39.83 0.00
Jumlah 39.83 m2

Jml. Tulangan Besi Panjang Besi


Koefisien Besi
(Bh) (m1)
c d e=bxc f
4 12 253.80 0.006165

Panjang Lipatan
Tulangan Tulangan
(m1) (m1)
c d e
0.14 0.40 0.15
Jarak Beugel Besi Jml. Beugel Jumlah Panjang Besi
Koefisien Besi
(m1) Bh Pembulatan (m1)
h i j=g/h k l=fxk m
0.15 8 424.00 424 292.56 0.006165
Luasan Vol. Sat.Balok
m2 m3
25.38 0.00
Jumlah 25.38 m2

Jml. Tulangan Besi Panjang Besi


Koefisien Besi
(Bh) (m1)
c d e=bxc f
13 10 482.35 0.006165
13.3333333
Panjang Lipatan
Tulangan Tulangan
(m1) (m1)
c d e
0.95 0.00 0.00
Jarak Tulangan Besi Jml. Besi Jumlah Panjang Besi
Koefisien Besi
Koefisien Besi
(m1) Bh Pembulatan (m1)
h i j=g/h k l=fxk m
0.15 10 496.71 496 471.20 0.006165
Luasan Vol. Sat.Balok
m2 m3
40.81 0.00
Jumlah 40.81 m2
Besi
(Kg) Penggunaan
Tulangan
g=dxdxexf
42.435 Tul. Utama

Besi
(Kg)
n=ixixlxm 62.952 kg
20.517

Besi
(Kg) Penggunaan
Tulangan
g=dxdxexf
95.345 Tul. Utama

Besi
(Kg)
n = i x i x l x m 125.174 kg
29.829

Besi
(Kg) Penggunaan
Tulangan
g=dxdxexf
471.401 Tul. Utama
Besi
(Kg)
n = i x i x l x m 642.695 kg
171.294

Besi
(Kg) Penggunaan
Tulangan
g=dxdxexf
225.313 Tul. Utama

Besi
(Kg)
n = i x i x l x m 340.746 kg
115.432

Besi
(Kg) Penggunaan
Tulangan
g=dxdxexf
297.366 Tul. Utama

Besi
(Kg)
n = i x i x l x m 587.861 kg
290.495
PERHITUNGAN VOLUME PEKERJAAN

1. Kusen Kayu Type-P1 ( 1 Unit ) Kusen Baru 1 Unit, Pintu 4 Unit

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 0.9 2.15 5.200 1 5.2 0.0075
0 2.15
0

Ukuran (m) Volume


No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Ventilasi 0.000

3 Bingkai Pintu Panel 0.8 2.15 4.000 6.880


Jumlah 6.880

7 Engsel Pintu 3 4 12.000 Bh

8 Engsel Ventilasi 0.000 Bh

9 Kait Angin Ventilasi 0.000 Bh

10 Grendel Pintu 1 0 0.000 Bh

11 Grendel Ventilasi 0.000 Bh

12 Handle Pintu, T = 80 cm 0.000 Pasang

4 Kunci Pintu Gagang 1 4 4.000 Bh


5 Cat Kusen Kayu 0.25

2. Kusen Kayu Type-P2 ( 2 Unit ) , Pintu 4 Unit

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Penampang
Panjang (m)
Horisontal Vertikal Kusen (m2)
1 Kusen 0 0 0.000 1 0 0.0075
0 0
0

Ukuran (m) Volume


No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Ventilasi 1.08 0.4 4.000 1.728

3 Bingkai Pintu Panil 0.56 2.15 4.000 4.816

4 Kaca Ventilasi 1.02 0.3 4.000 1.224

5 Engsel Pintu 3 4 12.000 Bh


6 Engsel Ventilasi 2 2 4.000 Bh

7 Kait Angin Ventilasi 2 2 4.000 Bh

8 Grendel Pintu 1 4 4.000 Bh

9 Grendel Ventilasi 1 2 2.000 Bh

10 Handle Pintu, T = 40 cm 1 4 4.000 Pasang

11 Kunci Pintu Gagang 1 2 2.000 Bh


12 Cat Kusen Kayu 0.25

3. Kusen Kayu Type-P3 ( 1 Unit )

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 0.8 2 4.800 1 4.8 0.0075
0 2

Ukuran (m) Volume


No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Pintu Teakwood 0.75 1.95 1.000 1.463

Jumlah 1.463

3 Kulit Jeruk 0.75 1.95 1.000 1.463

4 Engsel Pintu 2 1 2.000 Bh

5 Kunci Pintu Gagang 1 1 1.000 Bh


6 Cat Kusen Kayu 0.25

4. Kusen Kayu Type-P.V1 ( 2 Unit ) Kusen Baru 2 Unit, Pintu 5 Unit

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 2.54 2.47 10.820 2 21.64 0.0075
2.54 2.47
0.4
0.4
Ukuran (m) Volume
No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Ventilasi 0.4 0.77 10.000 3.080 2.478


0.4 0.8 5.000 1.600
4.680
3 Bingkai Pintu Panil 0.8 2.02 5.000 8.080
Jumlah 8.080

4 Kaca Ventilasi 0.4 0.77 10.000 3.080


0.4 0.8 5.000 1.600
4.680

5 Engsel Pintu 3 5 15.000 Bh

6 Engsel Ventilasi 2 15 30.000 Bh

7 Kait Angin Ventilasi 2 15 30.000 Bh

8 Grendel Pintu 2 0.000 Bh

9 Grendel Ventilasi 1 15 15.000 Bh

10 Kunci Pintu Gagang 1 5 5.000 Bh


11 Cat Kusen Kayu 0.25

5. Kusen Kayu Type-PJ1 ( 1 Unit ) Ganti Kusen 1 Unit, Ganti Pintu Dan Jendela 3 Unit

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 2.64 2.45 15.120 1 15.12 0.0075
2.64 2.45
1.64 1.65
1.65
Ukuran (m) Volume
No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Ventilasi 0.4 0.77 8.000 2.464 2.4136


0.4 0.9 4.000 1.440
Bingkai Jendela
1.2 0.77 4.000 3.696 1.1032
7.600
3 Bingkai Pintu Panil 0.9 2.00 4.000 7.200
Jumlah 7.200

4 Kaca Ventilasi 0.28 0.65 8.000 1.456


0.28 0.78 4.000 0.874
Kaca Jendela 1.08 0.65 4.000 2.808
Kaca Jendela Kaca Mati 1.22 0.79 4.000 3.855
8.993

5 Engsel Pintu 3 4 12.000 Bh

6 Engsel Jendela 2 4 8.000 Bh

7 Engsel Ventilasi 2 12 24.000 Bh

8 Kait Angin Jendela 2 4 8.000 Bh

9 Kait Angin Ventilasi 2 12 24.000 Bh

10 Grendel Jendela 1 4 4.000 Bh

11 Grendel Ventilasi 1 12 12.000 Bh

12 Kunci Pintu Gagang 1 4 4.000 Bh


13 Cat Kusen Kayu 0.25

6. Kusen Kayu Type-J1 ( 1 Unit )

Ukuran (m)
Luas
Volume
No. Uraian Panjang (m) Jumlah (bh) Penampang
Panjang (m)
Kusen (m2)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 2.59 1.65 15.220 1 15.22 0.0075
2.59 1.65
2.59 1.65
0.85 1.65
Ukuran (m) Volume
No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Jendela 0.65 1.2 2.000 1.560 0.518


Bingkai Ventilasi 0.85 0.28 1.000 0.238 0.1582
0.77 0.28 2.000 0.431 0.294
2.229 0.9702
3 Kaca Jendela 0.67 1.08 2.000 1.447
Kaca Ventilasai 0.65 0.28 2.000 0.364
0.73 0.28 1.000 0.204
2.016
4 Engsel Jendela 2 2.000 4.000 Bh

5 Kait Angin Jendela 2 2.000 4.000 Bh

6 Grendel Jendela 1 2.000 2.000 Bh

7 Engsel ventilasi 2 3.000 6.000 Bh

8 Kait Angin Ventilasi 2 3.000 6.000 Bh

9 Grendel Ventilasi 1 3.000 3.000 Bh

10 Cat Kusen Kayu 0.25

7. Kusen Kayu Type-J2 ( 3 Unit )

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 2.95 1.65 15.450 3 46.35 0.0075
2.95 1.65
2.95 1.65
1.65
Ukuran (m) Volume
No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Jendela 0.6 1.2 6.000 4.320 1.512


Bingkai Ventilasi 0.6 0.4 6.000 1.440 0.84
5.760 2.352
3 Kaca Jendela 0.48 1.08 6.000 3.110
Kaca Ventilasai 0.48 0.28 6.000 0.806
Kaca Mati 0.85 0.4 3.000 1.020
0.85 1.2 3.000 3.060
7.997
4 Engsel Jendela 2 6.000 12.000 Bh

5 Kait Angin Jendela 2 6.000 12.000 Bh

6 Grendel Jendela 1 6.000 6.000 Bh

7 Engsel ventilasi 2 6.000 12.000 Bh

8 Kait Angin Ventilasi 2 6.000 12.000 Bh

9 Grendel Ventilasi 1 6.000 6.000 Bh


10 Cat Kusen Kayu 0.25

8. Kusen Kayu Type-J3 ( 1 Unit )

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Panjang (m) Penampang
Horisontal Vertikal Kusen (m2)
1 Kusen 1.77 1.65 10.260 1 10.26 0.0075
1.77 1.65
1.77 1.65

Ukuran (m) Volume


No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Jendela 0.81 1.2 2.000 1.944 0.5628


Bingkai Ventilasi 0.81 0.4 2.000 0.648 0.3388
2.592 0.9016
3 Kaca Jendela 0.69 1.08 2.000 1.490
Kaca Ventilasai 0.69 0.28 2.000 0.386
1.877
4 Engsel Jendela 2 2.000 4.000 Bh

5 Kait Angin Jendela 2 2.000 4.000 Bh

6 Grendel Jendela 1 2.000 2.000 Bh

7 Engsel ventilasi 2 2.000 4.000 Bh

8 Kait Angin Ventilasi 2 2.000 4.000 Bh

9 Grendel Ventilasi 1 2.000 2.000 Bh

10 Cat Kusen Kayu 0.25

5. Kusen Kayu Type-V1 ( 1 Unit )

Ukuran (m)
Luas
Volume
No. Uraian Panjang Panjang Panjang (m) Jumlah (bh) Penampang
Panjang (m)
Horisontal Vertikal Kusen (m2)
1 Kusen 1.05 0.4 3.300 2 6.6 0.0075
1.05 0.4
0.4

Ukuran (m) Volume


No. Uraian Jumlah (bh)
Lebar Tinggi (m2)

2 Bingkai Jendela 0 0 4.000 0.000 0

3 Kaca Ventilasi 0.46 0.28 4.000 0.515

4 Engsel Jendela 0 1 0.000 Bh

5 Kait Angin Jendela 0 1 0.000 Bh

6 Grendel Jendela 0 1 0.000 Bh

7 Cat Kusen Kayu 0.25


Jumlah Cat Kusen 31.298

Jumlah Cat Pintu Panil Dan Jendela Bingkai 17.959

Vernis Teakwood 1.463


Volume
Kusen
(m3)
0.039

Volume
(m2)
1.300

Volume
Kusen
(m3)
0.000
Volume
(m2)
0.000

Volume
Kusen
(m3)
0.036

Volume
(m2)
1.200

Volume
Kusen
(m3)
0.162
Volume
(m2)
5.410

Volume
Kusen
(m3)
0.113

Volume
(m2)
3.780

Volume
Kusen
(m3)
Volume
Kusen
(m3)
0.114

Volume
(m2)
3.805

Volume
Kusen
(m3)
0.348
Volume
(m2)
11.588

Volume
Kusen
(m3)
0.077

Volume
(m2)
2.565

Volume
Kusen
(m3)
0.050

Volume
(m2)
1.650