Diketahui:
Stb = 16
Q25 = 75.16 m3/dt
B = 25.16 m
Io = 0.0016
H = 5 m
w = 0.5

#. Diminta = Rencanakan check Dam.


#. Penyelesain:
-. Tinggi air di atas peluap:

B= 25.16 m

75.16 = 0.71 h + 1.77 25.16 h3/2


75.16 = 74.76
h = 1.392 (dengan cara coba - coba)

H= 5 m

-. Tampungan Sedimen:
Kemiringan dasar semula sungai (Io) = 0.0016 (dari soal)
Kemiringan dasar seimbang (Is) = 1/2 x Io = 0.0008
Kemiringan dasar seimbang dinamis(Id) = 2/3 x Io = 0.00107
H 5
L1 = = = 6250 ≈ 6250 m
Io - Is 0.0016 - 0.0008
H 5
L2 = = = 9375 ≈ 9375 m
Io - Id 0.0016 - 0.0010667

= 1/2 5 25.16 6250


= 393125 m3
= 1/2 5 25.16 9375
= 589687.500 m3

= 5 25.16 6250
= 786250.000 m 3

393125 + 589687.5 + 786250.0


= 1769062.500 m3

-. Perencanaan Sub Dam dan Lantai:


Letak dan tinggi Sub Dam (L) =
Perhitungan:

= 2 9.81 7 + 1.5
= 12.91 m/dt

75.16
25.16
= 2.987 m3/dt/m

2.987
12.91
= 0.231 m

12.91
= 8.573
9.81 0.231

0.231 2
1 + 8 8.573 - 1
2
= 2.691 m
5 2.691
= 13.456 ≈ 13.5 m
2.987
1.5
= 1.992 m/dt

-. Tebal Lantai:

t = 0.2 0.6 7 + 3 1.5 - 1


= 1.54 ≈ 2.0 m
#. Diketahui:
Stb = 16
Q25 = 75.16 m3/dt
B = 25.16 m
Io = 0.018
H = 5 m
w = 0.5

#. Diminta = Rencanakan check Dam.


#. Penyelesain:
-. Tinggi air di atas peluap:

B= 25.16 m

75.16 = 0.71 h + 1.77 25.16 h3/2


75.16 = 74.79
h = 1.392 (dengan cara coba - coba)

H= 5 m

-. Tampungan Sedimen:
Kemiringan dasar semula sungai (Io) = 0.018 (dari soal)
Kemiringan dasar seimbang (Is) = 1/2 x Io = 0.009
Kemiringan dasar seimbang dinamis(Id) = 2/3 x Io = 0.012
H 5
L1 = = = 555.556 ≈ 556 m
Io - Is 0.018 - 0.009
H 5
L2 = = = 833.333 ≈ 834 m
Io - Id 0.018 - 0.012

= 1/2 5 25.16 556


= 34972.4 m3
= 1/2 5 25.16 834
= 52458.600 m3

= 5 25.16 556
= 69944.800 m 3

34972.4 + 52458.6 + 69944.8


= 157375.800 m3

-. Perencanaan Sub Dam dan Lantai:


Letak dan tinggi Sub Dam (L) =

0.0175439

2850
Perhitungan:

= 2 9.81 7 + 1.5
= 12.91 m/dt

75.16
25.16
= 2.987 m3/dt/m

2.987
12.91
= 0.231 m

12.91
= 8.573
9.81 0.231

0.231 2
1 + 8 8.573 - 1
2
= 2.691 m
5 2.691
= 13.456 ≈ 13.5 m
2.987
1.5
= 1.992 m/dt

-. Tebal Lantai:

t = 0.2 0.6 5 + 3 1.5 - 1


= 1.3 ≈ 2.0 m