Dimensi Tanggul pada CP.AG.

Hitungan trial h dengan ketelitian 0.05 m


biaya pembebasan tanah = Rp. 100,000,000.00 per ha atau = 10,000.00 per m2
biaya pembuatan tanggul = Rp. 194,740.87 per m3
debit rencana - Qdesain = 129.55 m3/det
ns = 0.035 S= 0.00126 B= 26 m
nb = 0.065 d= 1.330 m

per 1 m' arah memanjang


h hs Qs Qb qb W Pembebasan Tanah Pembuatan Tanggul Biaya Total
(m) (m) m3/det m3/det m3/det/m (m) Luas (m2) Biaya(Rp.) Volume(m3) Biaya(Rp.) (Rp. 106)
0.585 1.92 77.870 51.680 0.223 231.27 261.951 2,619,512.17 29.899 5,822,537.94 8.44
0.635 1.97 81.288 48.262 0.256 188.38 219.463 2,194,626.69 31.043 6,045,321.51 8.24
0.685 2.02 84.765 44.785 0.291 154.07 185.548 1,855,476.38 32.207 6,271,999.88 8.13
0.735 2.07 88.299 41.251 0.327 126.19 158.067 1,580,667.28 33.391 6,502,573.08 8.08
0.785 2.12 91.891 37.659 0.365 103.23 135.511 1,355,110.44 34.595 6,737,041.09 8.09
0.835 2.17 95.540 34.010 0.404 84.11 116.791 1,167,908.63 35.819 6,975,403.92 8.14
0.885 2.22 99.246 30.304 0.445 68.02 101.103 1,011,027.92 37.063 7,217,661.57 8.23
0.935 2.27 103.008 26.542 0.488 54.36 87.844 878,437.22 38.327 7,463,814.04 8.34
0.985 2.32 106.826 22.724 0.533 42.67 76.554 765,535.78 39.611 7,713,861.32 8.48
1.035 2.37 110.699 18.851 0.578 32.60 66.876 668,763.53 40.915 7,967,803.42 8.64
min = 8.08

dipilih harga yang optimum, dengan parameter sebagai berikut:


W= 126.19 m m= 2
h= 0.735 m fb = 1.5 m
B= 26.00 m b= 4 m 4 4
165.13 m
maka jarak tanggul L = W + B + 2m(h + fb) + b
1.5 m
L = 165.13 m
jika W1 = W2 = W/2 = 63.095 m 2.30 h= 0.735 m 1 2.30
2

tinggi tanggul = 2.235 m


dibulatkan = 2.30 m 1.33

6.94 63.095 26 63.095 6.94


5m 5m

176.07
Qs =1/ns (h+d)5/3 (S)1/2.B
qb =1/nb (h)5/3 (S)1/2
pekerja org 17,854.00 0.192 3,427.97
mandor org 25,789.00 0.019 489.99
operator alat berat org 33,063.00 0.1 3,306.30
sopir truk org 27,111.00 0.1 2,711.10
kenek truk org 19,838.00 0.1 1,983.80
tanah urug m3 16,500.00 1.35 22,275.00
exavator backhoe 5jam/hr hari 525,000.00 0.15 78,750.00
dump truck 3-4 m hari 184,000.00 0.05 9,200.00
buldozer 100-150 HP hari 542,000.00 0.054 29,268.00
tandem roller 6-8 ton hari 205,000.00 0.125 25,625.00
177,037.16
keuntungan 10% 17,703.72
Biaya Total 194,740.87

hs = h + d
Qs =1/ns (h+d)5/3 (S)1/2.B

Qb = qb. W
qb =1/nb (h)5/3 (S)1/2
8.70
f(x) = 8.4288175522x^2 - 13.0500568885x + 1
8.60 R² = 0.976831293
0.59 8.44 8.50
biaya (Rp.)

0.64 8.24
0.69 8.13 8.70 8.40
0.74 8.08 8.60
f(x) = - 12.1562661225x^3 + 37.9685442299x^2 - 36.5320122507x + 19.247770299 8.30
0.79 8.09 8.50
R² = 0.9993156727
0.84 8.14 8.40 8.20
0.89 8.23 8.30
8.10
0.94 8.34 8.20
0.99 8.48 8.10 8.00
1.04 8.64 8.00
7.90
7.90
7.80 7.80
0.50 0.60 0.70 0.80 0.90 1.00 1.10 0.50 0.60 0.70 0.80 0.90
h (m)
dy/dx = 0
16.856 13.05
h = 0.77421 m ekonomis/efektif
cost = 8.108 Rp. 106
522x^2 - 13.0500568885x + 13.1480629044
3

0.80 0.90 1.00 1.10

ekonomis/efektif
Dimensi Tanggul pada CP.AG.7

Hitungan trial h dengan ketelitian 0.05 m


biaya pembebasan tanah = Rp. 100,000,000.00 per ha atau = 10,000.00 per m2
biaya pembuatan tanggul = Rp. 194,740.87 per m3
debit rencana - Qdesain = 129.55 m3/det
ns = 0.035 S= 0.00126 B= 26 m
nb = 0.065 d= 1.330 m

per 1 m' arah memanjang


h hs Qs Qb qb W Pembebasan Tanah Pembuatan Tanggul Biaya Total
(m) (m) m3/det m3/det m3/det/m (m) Luas (m2) Biaya(Rp.) Volume(m3) Biaya(Rp.) (Rp. 106)
0.585 1.92 77.870 51.680 0.223 231.27 261.954 2,619,541.20 29.899 5,822,537.94 8.44 6.36345 1,239,223.82
0.635 1.97 81.288 48.262 0.256 188.39 219.465 2,194,652.00 31.043 6,045,321.51 8.24 6.75545 1,315,562.24
0.685 2.02 84.765 44.786 0.291 154.07 185.550 1,855,498.69 32.207 6,271,999.88 8.13 7.15745 1,393,848.08
0.735 2.07 88.299 41.251 0.327 126.19 158.069 1,580,687.12 33.391 6,502,573.08 8.08 7.56945 1,474,081.32
0.785 2.12 91.891 37.659 0.365 103.23 135.513 1,355,128.22 34.595 6,737,041.09 8.09 7.99145 1,556,261.96
0.835 2.17 95.540 34.010 0.404 84.11 116.792 1,167,924.67 35.819 6,975,403.92 8.14 8.42345 1,640,390.02
0.885 2.22 99.246 30.305 0.445 68.02 101.104 1,011,042.48 37.063 7,217,661.57 8.23 8.86545 1,726,465.49
0.935 2.27 103.008 26.543 0.488 54.37 87.845 878,450.50 38.327 7,463,814.04 8.34 9.31745 1,814,488.36
0.985 2.32 106.826 22.725 0.533 42.67 76.555 765,547.96 39.611 7,713,861.32 8.48 9.77945 1,904,458.65
1.035 2.37 110.699 18.852 0.578 32.60 66.877 668,774.75 40.915 7,967,803.42 8.64 10.25145 1,996,376.34
min = 8.08
0.774 2.10 91.111 38.440 0.356 107.83 140.026 1,400,256.89 34.333 6,686,089.92 8.09
dipilih harga yang optimum, dengan parameter sebagai berikut:
W= 107.83 m m= 2
h= 0.774 m fb = 0.6 m
B= 26.00 m b= 3 m 3 3
142.33 m
maka jarak tanggul L = W + B + 2m(h + fb) + b
1.5 m
L = 142.3289 m
jika W1 = W2 = W/2 = 53.92 m 1.40 h = 0.774 m 1 1.40
2

tinggi tanggul = 1.37 m


dibulatkan = 1.40 m 1.33

12.10 53.92 26 53.92 12.10


5m 5m

168.03
Qs =1/ns (h+d)5/3 (S)1/2.B
qb =1/nb (h)5/3 (S)1/2
pekerja org 17,854.00 0.192 3,427.97
mandor org 25,789.00 0.019 489.99
operator alat berat org 33,063.00 0.1 3,306.30
sopir truk org 27,111.00 0.1 2,711.10
kenek truk org 19,838.00 0.1 1,983.80
tanah urug m3 16,500.00 1.35 22,275.00
exavator backhoe 5jam/hr hari 525,000.00 0.15 78,750.00
dump truck 3-4 m hari 184,000.00 0.05 9,200.00
buldozer 100-150 HP hari 542,000.00 0.054 29,268.00
tandem roller 6-8 ton hari 205,000.00 0.125 25,625.00
177,037.16
(Rp. 106) keuntungan 10% 17,703.72
3.86 Biaya Total 194,740.87
3.51
3.25 hs = h + d
3.05 Qs =1/ns (h+d)5/3 (S)1/2.B
2.91
2.81 Qb = qb. W
2.74 qb =1/nb (h)5/3 (S)1/2
2.69 8.70
2.67 f(x) = 8.4288817319x^2 - 13
8.60 R² = 0.9768304908
2.67
0.59 8.44 8.50
biaya (Rp.)

0.64 8.24
0.69 8.13 8.70 8.40
0.74 8.08 8.60
f(x) = - 12.156364845x^3 + 37.9688483052x^2 - 36.5323451008x + 19.2479097007 8.30
0.79 8.09 8.50
R² = 0.9993156492
0.84 8.14 8.40 8.20
0.89 8.23 8.30
8.10
0.94 8.34 8.20
0.99 8.48 8.10 8.00
1.04 8.64 8.00
7.90
7.90
7.80 7.80
0.50 0.60 0.70 0.80 0.90 1.00 1.10 0.50 0.60 0.70 0.80
h (m)
dy/dx = 0
16.856 13.05
h = 0.77421
cost = 8.108
f(x) = 8.4288817319x^2 - 13.0501990389x + 13.1481527697
R² = 0.9768304908

0.60 0.70 0.80 0.90 1.00 1.10

m ekonomis/efektif
Rp. 106