Final Bill of Lining
Final Bill of Lining
1 EARTH WORK/DRESSING
IN BED PORTION
L = 374M., B = 5.355 M.
2 IN SLOPING PORTION 394 5.355 2109.87
L = 374M., B = 7.052 M. 394 7.052 2778.488
TOTAL EARTH WORK DERESSING 4888.36 SQ.M. 13.07048 10 130.7048
4 BEAM CONCRETE
A BEAM LONGITUDINAL IN BED
L = 394 M., B = 0.2 ,M., D = 0.15M.
NO. = 2 2 394 0.2 0.15 23.64
A BEAM LONGITUDINAL IN SLOP
L = 394 M., B = 0.3 ,M., D = 0.15M.
NO. = 2 2 394 0.3 0.15 35.46
B TRANSVERSE BEAM IN BED , no. = 1
L = 4.655 M., B = 0.2 ,M., D = 0.15M.
NO. = 394/3.2 =
123.125
SAY, 123NO. 123 4.655 0.2 0.15 17.18
2.7
TRIVENI ENGICONS. PVT. LTD.
NAME OF CONTRACTOR : - RAJU MAHTO
FINAL BILL FOR LINING WORK ABSTRACT
s.no. Description Unite QTY. Rate (Rs.) Thise bill Total this Previouse Total Bill Adv. Against Net amount
Amount Bill amount Bill Amount Amount Previous Bill
4 BEAM CONCRETE
a BEAM LONGITUDINAL IN BED
L = 293 M., B = 0.2 ,M., D = 0.15M.
NO. = 2 2 293 0.2 0.15 17.58
b BEAM LONGITUDINAL IN SLOP 0
L = 293 M., B = 0.3 ,M., D = 0.15M.
NO. = 2 2 293 0.3 0.15 26.37
c TRANSVERSE BEAM IN BED , no. = 1 0
L = 4.346-0.2 = 4.146 M., B = 0.2 ,M., D = 0.15M. 0
NO. = 293/3.2 = 0
91.5625 0
SAY, 92 NO. 92 4.146 0.2 0.15 11.44
0
d TRANSVERSE BEAM IN slope no. = 2 0
L = 2.471+0.537-0.1 = 2.908 M., B = 0.2 ,M., 0
D = 0.15M.
NO. = 293/3.2 = 0
91.5625 0
SAY, 91.56 NO.= 91.56*2 = 183 183 2.908 0.2 0.15 15.96
0
5 Dawel , 0
L= 293 m., B =( 0.3+0.15) /2 = 0.225m, 0
D = 0.3m. No. = 2 2 293 0.225 0.3 39.56
(4+5+6) Total Qty. of conc. Of Beam +Dawel = 111
7 Bed linning =
L = 293 M., B = 4.346 M., D = 0.1M. 1 127.34
293 4.346 0.1
sq.m.
CU.M.
71.36
0.243542
39.56
CU.M.
CU.M. 0.4346
CU.M.
CU.M. 0.6616
TRIVENI ENGICONS. PVT. LTD.
NAME OF CONTRACTOR : -
FINAL BILL FOR LINING WORK (MEASUREMENT BOOK) in second reach
s.no. Description no. L B D/H
1 EARTH WORK/DRESSING
IN BED PORTION
L = M., B = 4.346+0.5= 4.846M. 1 4.846
IN SLOPING PORTION
L = M., B =( 0.537+2.471+0.3+0.1)-0.25 = 3.158*2=6.316 1 6.316
TOTAL EARTH WORK DERESSING
SAY, NO.
c TRANSVERSE BEAM IN SLOPING,NO = 2
L = 0.537+2.471 - 0.25 -0.1
5 Dawel ,
L= m., B =( 0.3+0.15) /2 = 0.225m,
D = 0.3m. No. = 2 2 0.225 0.3
6 Stair
L = 1.5 , section area of one step =
0.0225 sq.m
no. of stair = 6*no.of step = total no 1.5 0.0225
(4+5+6) Total Qty. of conc. Of Beam +Dawel +stair =
7 Bed linning =
L = M., B = 4.346 M., D = 0.1M. 1 4.346 0.1
SAY , NO.
b Slope linning manual in r/s =
L = m., L= 3.308 M., B= 3.00M. D = 0.1M.
no. = L/3.2
SAY , NO.
1 3.308 3 0.1
9 TOTAL SLOPE LINING MANUAL
10a Slope linning left side (Paver)=
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.9924
0
0
0.9924
1.9848
0
0
0
0
0.9924
0.9924
TRIVENI ENGICONS. PVT. LTD.
NAME OF CONTRACTOR : -
FINAL BILL FOR LINING WORK (MEASUREMENT BOOK)
s.no. Description no. L B
1 EARTH WORK/DRESSING
IN BED PORTION
L = 667 M., B = 5.355 M.
IN SLOPING PORTION
L = 667 M., B = 7.052 M.
TOTAL EARTH WORK DERESSING
5 Dawel ,
L= 374m., B =( 0.3+0.15) /2 = 0.225m,
D = 0.3m
6 Stair
L = 1.5 , section area of one step =
0.25 sq.m
no. of stair = 6
(4+5+6) Total Qty. of conc. Of Beam +Dawel +stair =
7 Bed linning =
L = 374 M., B = 4.855 M., D = 0.1M.
NAME OF CONTRACTOR : -
FINAL BILL FOR LINING WORK (MEASUREMENT BOOK)
s.no. Description no. L B D/H
1 EARTH WORK/DRESSING
IN BED PORTION
L = 917.4 M., B = 5.355 M. 1
917.4 5.335
IN SLOPING PORTION
L = 917.4 M., B = 7.052 M. 1
917.4 7.052
TOTAL EARTH WORK DERESSING
NO. = 917.4/3.2 =
286.6875
SAY, 287 NO. 287 4.355 0.5 0.15
c TRANSVERSE BEAM IN SLOPING,NO = 2
L = 0.627+2.699 - 0.25 -0.1
NO. = 917.4/3.2 =
286.6875
SAY, 286.6875 NO.= 286.6875*2 = 573.375 573 2.976 0.5 0.15
d IN BED NO.
L = 4.855-0.2
NO. = 917.4/3.2 =
286.6875
SAY, 286.69 NO. 286.69 4.655 3 0.15
e IN SLOPE
L = 0.627+2.699-0.1
4 BEAM CONCRETE
a BEAM LONGITUDINAL IN BED
L = 917.4 M., B = 0.2 ,M., D = 0.15M.
917.4
NO. = 2 2 0.2 0.15
b BEAM LONGITUDINAL IN SLOP
L = 917.4 M., B = 0.3 ,M., D = 0.15M.
NO. = 917.4/3.2 =
286.6875
SAY, 287 NO. 287 4.655 0.2 0.15
d TRANSVERSE BEAM IN slope no. = 2
L = 3.226 M., B = 0.2 ,M., D = 0.15M.
NO. = 917.4/3.2 =
286.6875
SAY, 286.6875 NO.= 286.6875*2 = 573.375m 573 3.226 0.2 0.15
TOTAL BEAM CONCRETE
5 Dawel , r/s
L= 917.4-1.5 -80-167 = 668.9m., B =( 0.3+0.15) /2 = 0.225m,
D = 0.3m , NO. = 2 1 668.9 0.225 0.3
Dawel , l/s
L= 917.4 -1.5 - 167 = 748.9m., B =( 0.3+0.15) /2 = 0.225m,
D = 0.3m , NO. = 2 1 748.9 0.225 0.3
6 Stair
L = 1.5 , section area of one step =
0.0225
no. of stair = 2, NO. OF STEP = 8 16 1.5 0.0225
(4+5+6) Total Qty. of conc. Of Beam +Dawel +stair =
7 Bed linning =
L = 917.4 -3.2 = 914.2 M., B = 4.855 M., D = 0.1M.
914.2
one panel bed lining not done due to stoe in bed 1 4.855 0.1
8a Slope linning manual in left side =
L = 9.6 = 9.6 m., B = 3.626 M., D = 0.1M.
no. = 1 1 9.6 3.626 0.1
b Slope linning manual in r/s =
L = 9.6 m., B = 3.626 M., D = 0.1M.
no. = 1 1 9.6 3.626 0.1
9 TOTAL SLOPE LINING MANUAL
4894.329
6469.5048
93.741375 CU.M.
127.8936 CU.M.
600.543878 CU.M.
842.1381
1939.537 CU.M.
55.044
82.566
40.07955
55.45494
233.14 CU.M.
45.15 CU.M.
50.55
0.54 CU.M.
329.39 CU.M.
443.84 CU.M.
3.48
3.48
6.96 CU.M.
326.92
18.6809
S
FINAL BILL FOR LINING WORK ABSTRACT OF SABIR ALAM 1ST REACH+SECOND REACH
s.no. Description Unite QTY. Rate (Rs.) Thise bill Total this Previouse
Amount Bill amoun Bill Amou
5 Dawel ,
L= 2490.6 m., B =( 0.3+0.15) /2 = 0.225m,
D = 0.3m. No. = 2 2 2490.6 0.225 0.3
(4+5+6) Total Qty. of conc. Of Beam +Dawel =
7 Bed linning =
L = 500 M., B = 4.346 M., D = 0.1M. 1
500 4.346 0.1
Qty. unit
2423
3058
5481 sq.m
150
45.00
62.20
291.52
408.94
957.65 CU.M.
30
45
19.43
27.26
336.23
458 CU.M.
217.30 CU.M.
330.80 CU.M.
330.80 CU.M.
sabir alam
S. NO. CH. NO DEFRENCE OF
CHANAGE
1 32.5734 to dn.stre 0.500 km
TOTAL LENGTH 0f first reach= 0.5
TOTAL LENGTH OF secondreach
REACHIN (M) = 500