NAME OF PROJECT : INSTALLATION OF SOLAR ST. LIGHTS


LOCATION : Brgy. Motrico, La Paz, Tarlac
ESTIMATED BUDGET : ₱ 450,000.00
NO. OF DAYS TO COMPLETE : 25 Working Days

A. MATERIALS REQUIREMENTS:
1 P. Cement 45 bgs @ ₱ 250.00 ∕ bgs ₱ 11,250.00
2 C. Gravel 5 cu.m @ 2,250.00 ∕ cu.m 11,250.00
3 Sand 3 cu.m @ 350.00 ∕ cu.m 1,050.00
4 9mm dia RSB 80 pcs. @ 130.00 ∕ pcs. 10,400.00
5 10mm dia RSB 80 pcs. @ 210.00 ∕ pcs. 16,800.00
6 2" dia G.I. Pipe 45 pcs. @ 2,400.00 ∕ pcs. 108,000.00
7 100 watts Solar Lights 45 pcs. @ 3,500.00 ∕ pcs. 157,500.00
8 #16 G.I Wire 20 kgs. @ 90.00 ∕ kgs. 1,800.00
9 Form Lumber 60 bdft @ 55.00 ∕ bdft 3,300.00
10 1/2" Marine Plywood 4 pcs. @ 750.00 ∕ pcs. 3,000.00
11 Cutting Disc 30 pcs. @ 50.00 ∕ pcs. 1,500.00
12 Grinding Disc 5 pcs. @ 50.00 ∕ pcs. 250.00
13 Assorted CWN 4 kgs. @ 90.00 ∕ kgs. 360.00
14 Welding Rod 2 boxes @ 450.00 ∕ boxes 900.00
TOTAL MATERIALS REQUIREMENTS ₱ 327,360.00

B. MANPOWER REQUIREMENTS:

2 Welder @ ₱ 600.00 ∕ day for 25 days ₱ 30,000.00


2 Mason @ 600.00 ∕ day for 25 days ₱ 30,000.00
6 Laborers @ 400.00 ∕ day for 25 days 60,000.00
TOTAL MANPOWER REQUIREMENTS ₱ 120,000.00

TOTAL PROJECT COST ₱ 447,360.00

Prepared by:

ARTURO B. AGUSTIN ROBERTO S. CORONEL


Brgy Secretary Brgy. Kagawad - Comm. On Public Works

Approved by:

DOMINGO A. ALBERTO
Punong Barangay