Section3.2.2/ Page 24
10 of 44
Please remove the word Bidder from paragraph 1. word "bidder" is not used in this document
Section 3.2.3/ Page 25 Please change the word ER requirements as Employer/ ER/Engineer
11 of 44
Document is updated as per ERPS conditions
requirements in paragraph 1.
Sectioon 3.2.4/ Page 1) Please change the word ER requirements as Employer/ ER/Engineer
12 25 of 44
Document is updated as per ERPS conditions
requirements in paragraph 1.
Sectioon 3.2.54/ Page Please change the word ER requirements as Employer/ ER/Engineer
13 26 of 44
Document is updated as per ERPS conditions
requirements in paragraph .
EMI EMC will be provided in detailed design.
Regarding EMI/EMC it has been stated that IEC 61000-4-X Standard shall be
followed and further details to be provided in detailed design document.
Section7 /EMI & EMC/
14 Page 40 of 44
In this regard attention is drawn to EMI/EMC Standards given in chapter 11
Section 6, Relevant codes and standards of ERPS. This may be kept in view
in detailed design stage.
As regards the System Requirement SRS and DVVT for ACS the firm has revised SRS is submitted
10/ Annexure1/ Page 1 been separately advised vide letter no GEC/SURAT/HFCL/PH-
15 of 24 to 24 of 24 1/2023/0006780 Dated 24th May 2023 to carry out necessary
modifications and resubmit.
DVVT will be provided with Detailed design
Annexure 1 /Page 1 of In the DVVT table please provide Section details of PDD for compliance .
16 24 to 24of 24
Note: 1.Review comments, Advice of No Objection and/or approval by the Employer’s Representative on this submission shall not relieve the Contractor of any of its obligations,
liabilities or responsibilities under the contract nor shall create any obligations or liability on the part of the Employer.
Name Position Signature