Marking & Setting Up using hand held GPS may not give
accurate
location, The ROW is very narrow so there are chances
that the marking and setting up of point could be out of
ROW. It is advised to use Total Station for Marking and
8 Setting up Noted and incorporated.
Page 2 of 4
Only 3 Reporting Format has been submitted. It is advised Formats for Laboratory testing
19
that all the Formats to be submitted incorporated.
Page 3 of 4
All the formats should be machine numbered for easy Unique format numbers assigned
23
traceability. for each format for traceability.
Page 4 of 4
CONSTRUCTION OF
MUMBAI – AHEMADABAD HIGH SPEED
RAIL Package No. MAHSR-C-4
O20361-S-VIA-01-DC-03000 Rev-01
Date: 24th December 2020
CONSTRUCTION OF
MUMBAI-AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR – C – 4
Document No.
O20361-S-VIA-01-DC-03000 Rev-01
1 INTRODUCTION 1
2 SCOPE 1
3 REFERENCE 2
4 DEFINITIONS OF TERMS 4
5 RESOURCES 4
9 SAMPLING 11
10 PREPARATION OF BORELOG 14
11 PLUGGING OF BOREHOLES 14
12 MUCK DISPOSAL 14
13 LABORATORY TESTING 14
14 REPORT 15
QUALITY ASSURANCE AND QUALITY CONTROL ( Including
15 17
ITPs)
16 SAFETY ASPECTS 19
1. INTRODUCTION
Purpose of this document is to describe the methodology for carrying out Geotechnical
investigation for the proposed project “Mumbai-Ahmedabad High Speed Rail Project
Package No. MAHSR – C-4”.
2. SCOPE
Scope of work includes:
➢ Drilling of 2448 numbers of boreholes at 100 m intervals for viaduct area and at every
pier location for river/canal/SH crossing locations. Depth of borehole shall be as per
details given in Table 2.
➢ Conducting Standard Penetration Tests in the boreholes
➢ Collection of Disturbed and Undisturbed soil samples
➢ Collection of Soil sample and Water sample from boreholes
➢ Conducting all the relevant laboratory tests on soil & water samples
➢ Submission of a detailed Geotechnical investigation report as per specifications and
BOQ
Note : Where drastic geological changes are expected with 100m, the additional borehole
shall be carried out based on the initial assessed.
Page |1
3. REFERENCES
a) Project Technical Specification - Section VI-2, Employer’s Requirements (Design
Requirements and Criteria), Clause 2020: Survey and Investigations.
d) IS - Indian Standards
➢ SP - 36-Part 1 – 1987 (R 2006) : Compendium of Indian standards on soil
Engineering;
➢ SP - 36-Part 2 - 1988 (R 2006): Compendium of Indian standards on soil Engineering;
➢ IS : 1498 -1970 (R 2016) : Classification and identification of soils for general
Engineering purposes;
➢ IS : 1892 -1979 (R 2016) : Code of practice for subsurface investigation for
foundations
➢ IS : 2131 -1981(R 2016) : Method for standard penetration test for soils;
➢ IS : 2720 - Part-1- 1983 (R 2016) : Methods of test for soils: Part 1 - Preparation of dry
soil samples for various tests;
➢ IS : 2720 - Part-2 – 1973 (R 2015) : Methods of test for soils : Part 2 - Determination
of water content
➢ IS : 2720 - Part-3/Sec-1 – 1980 (R 2016) : Methods of test for soils : Part 3 -
Determination of specific gravity, Section-1 Fine grained soils
➢ IS : 2720 - Part-4 – 1985 (R 2015) : Methods of test for soils: Part 4 - Grain size
analysis
➢ IS : 2720 - Part-5 – 1985 (R 2015) : Methods of test for soils: Part 5 - Determination
of liquid and plastic limit
➢ IS : 2720 - Part-6 – 1972 (R 2016) : Methods of test for soils: Part 6 - Determination
of shrinkage factors.
➢ IS : 2720 - Part-12 – 1981 (R 2016) : Determination of shear strength parameters of
soil from consolidated undrained triaxial compression test with measurement of pore
water pressure
Page |2
Page |3
4. DEFINITIONS OF TERMS
ABBREVATIONS MEANING
ER Employer’s Requirements
TC Tungsten Carbide
5. RESOURCES
5.1 Field Equipment
• Rotary type drilling machine
• Standard penetration test setup
• Drilling Accessories for soil and rock
• Core Boxes
Page |4
5.4 Manpower
▪ Geologist / Engineer
▪ Geotechnical Engineer
▪ Drilling supervisor
▪ Drilling assistants
▪ Lab-in-charge
▪ Lab assistants
Engineering − Overall management of Laboratory testing and provide technical support to the
Manager project related Geotechnical aspects
(Geotechnical) − Review and approval of the Laboratory and geotechnical report
Page |5
− Interact with client representative, HQ design team and site team for geotechnical
related clearances
Page |6
PROJECT MANAGER
ARUN
N R SATHISHA SHANTANU
BALAMURUGAN
SITE ENGINEER SITE ENGINEER SITE ENGINEER SITE ENGINEER SITE ENGINEER SITE ENGINEER
Page |7
The borehole locations will be marked on the ground by using total station, as per the co-
ordinates provided in borehole layout.
In case of congested areas and road crossings, a utility checking test pit shall be excavated up to
a depth of 1.5m below ground level to check the presence of any utility, accordingly the borehole
location will be adjusted locally. If required, the utility checking pit shall be excavated upto 3.0
m depth for sewer, OFC machine slots.
Fully automatic / semi-automatic rotary drilling rigs will be mobilized at identified test location
and drilling shall commence as below:
▪ The borehole shall be advanced by rotating a drill string consisting of a series of drill rods to the
bottom of which a cutting bit is fixed during drilling in soil. The rotating drill bit cuts the subsoil
at the bottom of the borehole to provide 150 mm size borehole and the fragment of soil are
removed by circulating drilling mud (Bentonite). The drilling mud shall be used to stabilize the
borehole and guide casing of SX size shall be used for the initial depth while drilling in sandy or
other non-cohesive soil below water table. Standard penetration test (SPT) will be conducted at
1.0m intervals. Undisturbed samples (UDS) will be collected from cohesive soil layers at 3 m
interval by using thin walled open-ended fixed head Shelby tubes from 4m depth onwards.
▪ Rock coring shall be carried out by using diamond bits/TC bit of NX size. The drilling operation
shall be conducted by attaching bits to core barrels through reamer shells. The drilling equipment
shall be either hydraulically operated. Methodology followed for boring confirmed IS:1892-1979
and IS:6926-1996. The rock core samples shall be preserved as per IS:4078-1980.
Page |8
Page |9
Note:
Maximum drilling in rocks shall be limited to 12m.
Maximum depth of borehole shall be limited to 40 m below ground
level.
Immediately on completion of a borehole, bore log shall be prepared indicating detail description
of soil and geological description of rock in the approved pro-forma.
After completion of borehole the contaminated water shall be removed by pumping out and allow
the water to rise in the borehole. Observation shall be made at regular interval to monitor the rise
in water level and shall be continued till the level balance at one level. This level shall be
considered as the original water table. To measure the seasonal variation, PVC pipe encased in
concrete shall be installed at every 5 Km.
The procedure for measuring ground water level and its variation using PVC standpipe. The
Typical sketch is shown in Fig 1.1.
Water table observation well consists of PVC pipe of 150 mm diameter is set in borehole which
is drilled upto 20-40m (approx.) below existing ground level. The PVC slotted pipe of 75 mm
diameter is placed inner of 150 mm PVC pipe. The PVC slotted pipe is connected by a socket to
same diameter plastic riser pipes extending to the surface. The annulus between the outer
diameter and inner diameter PVC pipe is filled with 10mm gravel. The Outer PVC casing pipe
is removed once the gravel material is filled. The top of PVC slotted pipe is sealed with protection
cap and protection P.C.C (1:4:8) above the ground level.
The water level sounder is designed to measure the elevation of ground water in standpipes. The
water level sounder shall be light weight and convenient to use. The water level sounder probe
is lowered from the surface with the help of the connecting flat cable for taking observations.
The Frequency of water level measurement shall be monthly once in day of a time interval of
9.30 am, 12 pm ,2.30 pm ,4 pm and 6 pm. The record of monitoring will be maintained and
submitted for Owners observation and record.
P a g e | 10
Fig -1.1
P a g e | 11
Standard Penetration Test (N values) shall be conducted by using standard mechanised drilling
rig with semi-automatic trip hammer along with split spoon sampler completely with a drive shoe
and drive head fitted with non-return valve. The SPT equipment shall be duly calibrated for
Energy Ratio (ER) equal to or more than 67%. The ER shall be calibrated as per guideline given
in ISO: 22476-3 for equipment mobilized at site.
The basis of the test consists of dropping of a hammer of mass 63.5 kg on to a drive head from
a height of 75 cm. The number of such blows (N) necessary to achieve a penetration of the split
spoon sampler by 30cm (after its penetration under gravity and below the seating drive) is
regarded as the Standard Penetration Resistance. The blow counts for each 15cm penetration is
recorded. The test shall be conducted at 1m intervals. If at any location SPT refusal is achieved
(i.e. more than 50 blows for 15cm penetration or more than 100 blows for 30cm penetration or
10 blows produce no advancement) the testing shall not be halted. Drilling shall be continued
and SPT carried out at next level.
Enough quantity of disturbed soil samples shall be collected from the split spoon sampler for
identification and laboratory testing. The sample shall be visually classified and recorded at the
site and shall be properly preserved without loss of moisture content and labelled for future
identification.
9. SAMPLING
Enough soil samples shall be collected from the boreholes for reliable estimation of soil
properties. The samples collected shall be either disturbed or undisturbed. Disturbed soil
samples shall be collected for field identification and conducting tests such as sieve analysis,
index properties, specific gravity, chemical analysis, etc. Undisturbed samples shall be collected
to estimate the physical, strength and settlement properties of the soil.
Precaution shall be taken to ensure that there shall not be any change in moisture content and
disturbance of the soil samples, and they shall be placed in a temporary store at the end of the
day’s work.
P a g e | 12
transferred to a double walled polythene bag. A sample label (as per the format O20361-S-VIA-
01-DC-03000/F04) shall be attached and the bag tightly tied with thread to avoid loss of
moisture.
Sample obtained from the split spoon sampler during SPT is to be tested for water content within
24 hours. Further, index properties such as soil classification, Atterberg limits and free swell
index shall be carried out.
In each borehole undisturbed sample shall be collected at regular intervals of 3.0 m starting from
4.0 m below ground level (i.e. 4 m, 7 m, 10 m, 13 m and 16 m below ground level)as per the site
and soil condition or as directed by the Engineer. While conducting visual inspection of sample
collected during SPT, if it is observed that is weak soil layer (N<=5) or change in strata is
encountered then additional UDS samples shall be collected. Undisturbed samples shall be
obtained from the cohesive layers by using open ended fixed head thin walled sampler of 10cm
dia. and 45cm long seamless tubes. Samples shall be collected in such a manner that the structure
of the soil and its moisture content do not get altered. The area ratio of sampling tubes shall be
less than 10%. However, in case of stiff soils, area ratio up to 20% shall be permitted.
The sampler shall be pushed / driven to the bottom of the borehole at the appropriate depths.
After reaching sufficient depth, the sampler shall be gently turned and taken out of the borehole.
After removal, both the ends of the sampler shall be cleaned off of any loose material and sealed
using good quality molten wax. Then the sample shall be numbered & labeled and sent to
laboratory for testing. UDS sample shall be tested for engineering properties within one week of
collection from field.
When the collection of undisturbed soil sample at a specified depth is not possible, the reason
for the same shall be indicated in the bore log.
P a g e | 13
a. Sub-soil water samples shall be collected for carrying out chemical analysis thereon.
Representative samples of ground water shall be collected when it is first encountered in
bore holes before the addition of water to aid boring or drilling. Water samples shall not
be collected when bentonite slurry or mud has been used for drilling operation. If water
has been added for drilling purposes or if ground water has been diluted by surface rain
water, then the bore hole shall be dewatered, and water allowed to rise from which the
sample may be taken.
b. The sampling apparatus shall be such that the water at the desired depth can be collected
directly without any disturbance and any change in the concentration of the constituents
like dissolved gases, etc. Undue agitation shall be avoided. An ordinary suction pump
with the suction end inserted up to the required depth in the borehole shall be used for
this purpose.
c. The sample shall be collected in a clean vessel and allowed to settle so that the
supernatant liquid can be poured into a clean well-rinsed glass or polythene bottle.
Enough quantity and number of samples shall be collected to carry out the chemical
analysis and sent to a laboratory in airtight bottles with proper labelling, chemical
analysis of water samples shall include determination of pH value, turbidity; sulphate,
carbonate, chloride contents; presence of organic matter and suspended solids.
d. In some cases, constituents may be mixed and analysed later as specified in the specific
test methods. Chemical preservatives may be added to the sample for cases as specified
in the test method or IS codes. This shall only be done if analysis cannot be conducted
within an hour of collection and shall have the prior written permission and approval of
the Engineer.
All core pieces shall be placed in standard core boxes in a serial order in correct sequence from
top downwards. The shallowest core shall be placed to the top left-hand corner and for every
compartment the shallower core shall be to the left, the top being considered adjacent to the
hinged section. Core boxes shall be according to IS 4078-1980, soundly constructed of good
quality timber painted with good quality paint on both inside and outside surface. Each box shall
have following information painted with black enamel paint on the lid.
P a g e | 14
The depth at which the core obtained shall be written on core box and placed in the respective
places.
During drilling, in-situ testing and sampling observation shall be made and recording shall be
done continuously.
On completion of each borehole, the data collected shall be compiled and prepared
i) Bore log for soil/Core
ii) Consolidated log for Core drilling
These final logs shall be prepared on the basis of, the consolidated drilling log, visual
examination of the soil samples on the rock cores and laboratory testing data.
Borelogs shall contain the date when the boring was made, the location of the boring with
reference to the co-ordinate system used for the site, depth of boring and the elevation with
respect to a fixed datum. The log shall also include the elevation of the top and bottom of boring
and the level at which water table and the boundaries of soil and rock strata that encountered, the
classification and description of the soil and rock layer, blow count values obtained from SPT
tests, percentage recovery of rock core, quality of core lost or not recovered for each core interval
P a g e | 15
or drill run and Rock Quality Designation (RQD). The type of tools used in making in boring
shall be noted. Notes shall be provided of everything significant to the interpretation of sub-
surface conditions such as lost drilling fluid, rod drops and changes in drilling rate etc.
After completion of activities in the borehole and after removal of casing, if any, each
borehole shall be back filled with existing soil material.
The contaminated bentonite slurry is not eco- friendly and hence this slurry has to be disposed
safely. The semi solid muck out of borehole shall be mixed with dry soil and then disposed safely.
Laboratory Tests as indicated in this specification and as called for by the Engineer shall be
conducted. These tests shall include but not be limited to the following:
a. Tests on Disturbed Soil Samples
• Water content (within 24hrs of sample collection)
• Soil classification using wet sieve analysis & hydrometer analysis
• Liquid limit, plastic limit and plasticity index
• Free Swell Index
• Swelling pressure test
• Chemical analysis of sub-soil shall include determination of pH value, sulphate (both SO3
and SO4) and chlorides.
• Chemical analysis of sub-soil water sample includes the determination of the properties
such as pH value and chemical contents such as sulphates (both SO3 and SO4) and
chlorides.
14. REPORT
14.1 General
a. On completion of the entire field and laboratory works, a report containing Geological
information of the region, procedure adopted for investigation, field observations,
summarized test data, and factual report shall be submitted. The report shall include
detailed bore logs, subsoil sections, field test results, laboratory observations and test
results both in tabular as well as graphical form, practical and theoretical considerations
for the interpretation of test results, etc. Initially, the draft report shall be submitted for
the Owner’s review.
b) Exploratory bore logs, in-situ test records, laboratory test results (grain size analysis,
Atterberg limits, Free Swell Index), plan with locations of exploratory bore logs and site
location plan
P a g e | 17
The site plans shall be to a stated scale and shall include a north point. Additional
information shall be provided where required in the requisition.
Report for shallow foundation locations:
a) A statement on the purpose and rationale of the investigation, description of the work
carried out, including reference to the specification and standards adopted and any
deviations from them
b) Exploratory bore logs, in-situ test records, laboratory test results (including grain size
analysis, Atterberg limits, Free Swell Index, Swell pressure test, triaxial test
(Consolidated Undrained Test) and consolidation test) plan with locations of exploratory
bore logs and site location plan
d) Calculation of ultimate bearing capacity shall be carried out for the relevant boreholes
where shallow foundations are adopted.
The site plans shall be to a stated scale and shall include a north point. Additional
information shall be provided where required in the requisition.
a) A true cross-section of all individual boreholes with reduced levels and coordinates
showing the classification and thickness of individual stratum, position of ground water
table, various in-situ tests conducted, and samples collected at different depths and the
rock stratum, if met with.
b) Results of all laboratory tests shall be summarised and a consolidated table giving the
layer-wise soil properties in a standard format. The relevant tables, graphs, figures,
supporting calculations, conclusions shall be furnished.
c) Analyses and recommendations based upon loads and limiting settlement criteria as
appropriate
d) The interpretative report will include clear guidance on the classification of the soil and
groundwater properties with respect to the effect on the specification of reinforced
P a g e | 18
- All material testing shall be witnessed by the Engineer and approved prior to use.
Rejected material shall be removed from site.
P a g e | 20
1. Stack material 1m away or more than 1/3 distance depth of the excavated pit
2. Heavy vehicle movement near drilling area is prohibited
3. Check the Tripod for any physical damage
4. Base of the tripod shall be anchored sufficiently to avoid toppling
5. Fix the tripod in stabled ground.
6. Check the Bottom flaps
7. Check the Ladder steps and follow 3 point contact while ascending and descending
8. The area should be free from flammable materials.
9. Competent operator only should operate hydraulic core drilling machine
10. All Openings & Cut out to be covered in core drilling machine, once the job is completed
11. All the Rotating parts should be guarded properly.
12. Check battey condition and terminals with protection caps
13. Check the condition of lifting hooks
14. Select the Workers and screen for competency and physical fitness to perform the
activity.
15. Ensure EHS induction training provided before engaging on work.
16. PEP talk specific to the erection activity shall be conducted explaining hazards associated
with the job and the safety measures should be provided.
17. All workers at site to wear Safety shoe, helmet, hand gloves/ reflective jackets.
18. Ensure the emergency contact number is available with the operator / Supervisor.
19. All the electrical connection to be taken through 30 mA ELCB only
20. All site Distribution boards shall be of rating IP 45.
21. All the connections to be taken in proper way by authorized electrician
P a g e | 22
2. Supply of sufficient quantity of potable water. All Drinking water locations must be
legible marked "Drinking Water" in a language understood by a majority of the workmen
employed.
3. Surrounding areas of drinking water tanks/taps should be hygienically cleaned/
maintained.
4. Proper sanitation & sewage system in the camp
5. Separate toilets/bathrooms for men and women Waste disposal facility. Toilet / urinals
must be properly cleaned and maintained at regular intervals
6. Drinking water, toilet and rest place shall be suitably located for the easy access to
workers. All the facilities shall be properly cleaned and maintained during the entire
period of operation.
7. During summer season rest shed must be ensured at erection site. Dehydration powder
must be readily available at site.
8. If concrete splatters on the skin, wash off as soon as possible.
9. Sufficient toilet rooms with proper facility to drain the sewage shall be provided at
reasonably accessible distance.
P a g e | 23
ANNEXURE - 1
INSPECTION TEST PLAN
P a g e | 24
Reference
Sl. No. Component / Process Nature of Check / Test Method of Check / Test Frequency of Check Document/ Format of Record L&T Client
Acceptance criteria
Measurement O20361-S-VIA-
1 Surveying Borehole location survey For Every Bore Hole Approved drawings C R
01-DC-03000/F01
Technical specification,
Measurement 1 per borehole C R
IS 1892 Bore log
Water table
C : CHECK
R : REVIEW
P a g e | 25
ANNEXURE-2
SITE FORMATS
P a g e | 26
Project :
Area : Date :
Description of Work / Drg. Ref : Time :
Remarks:
Signature: Signature:
L&T Construction: Client:
Date & Time: Date & Time:
P a g e | 27
BORELOG - O20361-S-VIA-01-DC-03000/F02
P a g e | 28
P a g e | 29
PROJECT :
BORE HOLE NO :
DEPTH :
TYPE OF SAMPLE :
SAMPLE NO :
DATE :
TIME :
SPT DETAILS
0-15(IN CM) 15-30 (IN CM) 30-45 (IN CM) N' VALUE
REMARKS:
P a g e | 30
ANNEXURE 3
P a g e | 31
Tested by :
SAMPLE ID
CONTAINER NUMBER
WT. OF OVEN DRY SOIL, g (w3-w1) 0.00 0.00 0.00 0.00 0.00 0.00
SAMPLE ID
CONTAINER NUMBER
WT. OF OVEN DRY SOIL, g (w3-w1) 0.000 0.000 0.000 0.000 0.000 0.000
Result:
Water content, % =
P a g e | 32
TRIAL NO 1 2 3 4
NUMBER OF DROPS
CONTAINER NO.
WT. OF CONTAINER,
(W1) g
WT. OF CONTAINER +
WET SOIL (W2) g
WT. OF CONTAINER +
DRY SOIL (W3) g
WT. OF WATER, g
WT. OF OVEN DRY
SOIL, g
MOISTURE CONTENT,
%
60
58
56
54
52
50
48
46
44
42
40
1
NUMBER OF DROPS
Result:
I. LIQUID LIMIT, wL %
II. FLOW INDEX, If
P a g e | 33
Tested by : Oven ID :
SAMPLE ID.
TRIAL NO. 1 2 3
CONTAINER NO.
WT. OF WATER, g
MOISTURE CONTENT, %
SAMPLE ID.
TRIAL NO. 1 2 3
CONTAINER NO.
WT. OF WATER, g
MOISTURE CONTENT, %
Result: 1 2
Plastic Limit, %
=
P a g e | 34
Job ID Oven ID
Tested by
Weight of sample taken for the test, g
Trial No. 1 2 3
P a g e | 35
Job ID : Oven ID :
Date of testing : Electronic balance ID :
Thermometer ID :
Relative density of water at 27 oC, 27 : 0.9965
Timer ID :
SAMPLE ID
DATE OF TESTING
DENSITY BOTTLE ID
TEMPERATURE, ToC
SAMPLE ID
DATE OF TESTING
DENSITY BOTTLE ID
TEMPERATURE, oC
TEMPERATURE CORRECTION, K
Result:
Specific gravity at
27oC =
P a g e | 36
IS SIEVE (mm) 4.750 2.000 1.000 0.600 0.425 0.212 0.150 0.075 Pan
ID No.
Weight of soil
retained (g)
Sample ID : Wt. of sample taken (g): Oven drying period:
Weight of soil
retained (g)
Sample ID : Wt. of sample taken (g): Oven drying period:
Weight of soil
retained (g)
Sample ID : Wt. of sample taken (g): Oven drying period:
Weight of soil
retained (g)
Sample ID : Wt. of sample taken (g): Oven drying period:
Weight of soil
retained (g)
Sample ID : Wt. of sample taken (g): Oven drying period:
Weight of soil
retained (g)
Remarks:
P a g e | 37
% OF MATERIAL CUMULATIVE % OF
WT.OF MATERIAL
S.No IS SIEVE, mm
RETAINED ON SIEVE, g
RETAINED ON MATERIAL CUM. % PASSING
SIEVE RETAINED ON SIEVE
1 4.75
2 2.00
3 1.00
4 0.600
5 0.425
6 0.212
7 0.150
8 0.075
80
Percentage passing
60
40
20
0
0.010 0.100 1.000 10.000
Grain size in mm
Result:
SAND %
GRAVEL, % SILT, % CLAY, %
COARSE MEDIUM FINE
P a g e | 38
Job ID : 75 sieve ID :
Sample ID : Balance ID :
Tested by : Timer ID :
Thermometer ID :
Hydrometer ID :
Wt. of sample taken for combined testing : Hydrometer reading in distilled water :
0.5
1.0
2.0
4.0
8.0
15.0
30.0
60.0
120.0
240.0
360.0
480.0
1440.0
Remarks:
P a g e | 39
Job ID : 75 sieve ID :
Sample ID : Balance ID :
Date of testing : Measuring jar ID :
Tested by : Timer ID :
Thermometer ID :
Wt. of sample taken for combined testing, g : Hydrometer ID :
Rh+Mt
ELAPSED HYDRO CORRECTED EFFECTIVE EQUIVALENT PERCENTAGE COMBINED SPECIFIC VISCOSITY
-X
TIME TEMPERATURE METER HYDROMETER DEPTH, cm DIAMETER FINER THAN PERCENTAGE GRAVITY OF WATER
DATE TIME,
OF
HRs READING READING, cm
t D WATER
(min) To C R'h Rh = R'h + Cm HR (mm) (%) (%)
0.5
1.0
2.0
4.0
8.0
15.0
30.0
60.0
120.0
240.0
360.0
480.0
1440.0
P a g e | 40
Job ID : Equipment ID :
Sample ID : Loading Frame ID :
Date of testing : Consolidation ring ID :
Tested by : Dial gauge ID :
Diameter of specimen, D (cm) : Vernier ID :
Thickness of specimen, (Ho) cm : Oven ID :
Type of water used : Electronic balance ID :
Timer ID :
Normal weights ID :
Oven set temperature :
Container No.
Weight of container, g (w1)
Weight of tray, g
P a g e | 41
ELAPSED
DIAL GAUGE READINGS (Thousands of mm) FOR DIFFERENT PRESSURES (kg/cm2)
TIME (t)
0.25 0.50 1.00 2.00 4.00 8.00
(min) Date & time Date & time Date & time Date & time Date & time Date & time
0.00
0.25
1.00
2.25
4.00
6.25
9.00
12.25
16.00
20.25
25.00
36.00
49.00
64.00
81.00
100.00
121.00
144.00
169.00
196.00
225.00
1440.00
B. Un loading condition
Pressure range ( kg / cm2 ) 8.00-2.00 2.00 -0.50 0.5 - 0.05
P a g e | 42
Job ID : Equipment ID :
Sample ID : Loading Frame ID :
Date of testing : Consolidation ring ID :
Tested by : Dial gauge ID :
Diameter of specimen, D (cm) : Vernier ID :
Area, A (cm2) = p D2/4 : Oven ID :
Thickness of specimen, (Ho) cm : Electronic balance ID :
Volume of specimen, (V) cm3 = A x Ho : Timer ID :
Type of water used : Normal weights ID :
Specific gravity, Gs :
P a g e | 43
ELAPSED t DIAL GAUGE READINGS (Thousands of mm) FOR DIFFERENT PRESSURES (kg/cm2)
TIME (t) (min) 0.25 0.50 1.00 2.00 4.00 8.00
(min) Date & time Date & time Date & time Date & time Date & time Date & time
0.00 0.00
0.25 0.50
1.00 1.00
2.25 1.50
4.00 2.00
6.25 2.50
9.00 3.00
12.25 3.50
16.00 4.00
20.25 4.50
25.00 5.00
36.00 6.00
49.00 7.00
64.00 8.00
81.00 9.00
100.00 10.00
121.00 11.00
144.00 12.00
169.00 13.00
196.00 14.00
225.00 15.00
1440.00 37.95
2011
Compression dial reading in thousands of mm
1922
1984
1912
2009
1979 1902
1974 1892
2007
1882
1969
1872
2005 1964
1862
1959
2003 1852
1954
1842
P a g e | 44
1404
Compression dial reading in thousands of mm
1329
1279
1719
1254
1502
1694 1229
1204
11
12
13
14
15
0
10
11
12
13
14
15
0
10
11
12
13
14
15
0
9
av vs log s cv vs log s
1.00 1.000
0.90 0.900
Coefficient of compressibility, av (cm2/s)
0.80 0.800
Coefficient of consolidation, cv (cm2/s)
0.70 0.700
0.60 0.600
0.50 0.500
0.40 0.400
0.30 0.300
0.20 0.200
0.10 0.100
0.00 0.000
0.10 1.00 10.00 0.10 1.00 10.00
P a g e | 45
0.25
0.50
1.00
2.00
4.00
8.00
2.00
0.50
0.05
e vs log s
0.480
0.460
0.440
0.420
0.400
Void ratio, e
0.380
0.360
0.340
0.320
0.300
0.280
0.00 0.01 0.10 1.00 10.00
Applied pressure, s (kg/cm2)
Result:
Compression index = Slope of straight line portion of the curve
P a g e | 46
(mm) kN ( ) (kPa) (kPa) (mm2) kPa kPa kPa kPa (mm) kN ( ) (kPa) (m2) kPa kPa kPa kPa (mm) kN ( ) (kPa) (kPa) (m2) kPa kPa kPa kPa
P a g e | 47
0.7 0.7
0.6 0.6
0.5 0.5
0.4 0.4
0.3 0.3
0.2 0.2
0.1 0.1
0.0 0.0
0.00 0.05 0.10 0.15 0.20 0.25 0.00 0.05 0.10 0.15 0.20 0.25
Axial strain, e Axial strain, e
P a g e | 48
Mode of failure :
P a g e | 49
Job ID : Equipment ID :
Date of testing
Vernier caliper ID:
:
Tested by : Loading device ID :
Timer ID :
Oven ID :
Oven set temperature:
Sample ID :
Type of test Soaked / Unsoaked (field) / dry Mode of failure :
Date/time to keep specimen in water:
Soaking period,
days Date/time to remove specimen from
water:
Date/time to keep the sample in oven:
Drying period
Date/time to remove the sample from oven:
Length of specimen, mm (L)
Distance between contact point and the nearest free end, mm (For even ends of
specimen)
Shortest horizontal distance from any point at the nearest uneven end to the loading
point, mm (For uneven ends of specimen)
Diameter of specimen at the contact of platens in direction of, 1 to 2
mm (D) 3 to 4
Starting
Duration of test Finishing time
time
Failure load, P (kN)
Sample ID :
Type of test Soaked / Unsoaked (field) / dry Mode of failure :
Date/time to keep specimen in water:
Soaking period,
days Date/time to remove specimen from
water:
Date/time to keep the sample in oven:
Drying period
Date/time to remove the sample from oven:
Length of specimen, mm (L)
Distance between contact point and the nearest free end, mm (For even ends of
specimen)
Shortest horizontal distance from any point at the nearest uneven end to the loading
point, mm (For uneven ends of specimen)
Diameter of specimen at the contact of platens in direction of, 1 to 2
mm (D) 3 to 4
Starting
Duration of test Finishing time
time
Failure load, P (kN)
Remarks :
P a g e | 50
Diameter of
Point load Uni axial
specimen at Failure
Type of strength compressive
Job ID Sample ID contact of Load, P
test Index, IS(50) strength, qc
platens, D (kN)
(MPa) (MPa)
(mm)
Result:
Point load strength Index, IS(50)
(MPa) :
Uni axial compressive strength, qc
(MPa) :
P a g e | 51
Sample ID
Date of testing
Glass graduated cylinders ID
Wt. of sample taken into distilled water graduated cylinder,g
Wt. of sample taken into kerosene graduated
cylinder,g
Time Vd (ml) Time Vd (ml)
Sample ID
Date of testing
Glass graduated cylinders ID
Wt. of sample taken into distilled water graduated cylinder,g
Wt. of sample taken into kerosene graduated
cylinder,g
Time Vd (ml) Time Vd (ml)
P a g e | 52
Job ID : Equipment ID :
Sample ID : Electronic balance ID:
Date of testing : Mould ID :
Tested by : Dial gauge ID :
Type of sample : Undisturbed / remoulded Oven ID :
Density, g/cc : MDD / Filed / any other Proving ring ID :
OMC / Filed / Shrinkage
Water content, % : Timer ID :
limit
Oven set
Liquid limit, % :
tesmperature,oC:
Plastic limit, % : Diameter of mould, cm :
Height of the of mould,
Soil fraction below 0.002mm, %:
cm:
Shrinkage limit, %:
Swell pressure:
Remarks:
P a g e | 53
Job ID : Mould ID :
Sample ID : Timer ID :
Date of testing: Thermometer ID :
Tested by : Electronic balance ID:
Diameter of the specimen,D (cm): Oven ID :
Area of the specimen, A (cm2) : Weight of sample taken:
Length of specimen, L (cm) : Type of sample : Disturbed/undisturbed
Volume of the specimen, V (cm3): Moisture content, % : OMC/field
Diameter of the standpipe, d (cm): Density, g/cc : MDD/field
Area of the stand pipe, a (cm2) : Specific gravity of sample, Gs :
Constant, C = 2.303 a L / A : Temperature of water, oC (T) :
Density of water at temp T oC, γT:
Density: Density of water at temp 27 oC, γ27:
Weight of empty mould, g (w1)
Weight of empty mould + compacted soil,g (w2)
Weight of compacted soil,g
Bulk density, g/cc
Result:
Permeability at temperature 30oC, k30 (cm/s) :
Permeability at temperature 27oC, k27 (cm/s) = k30 x γT / γ27 :
water content, w (%) = (Wt-Ws) 100 / Ws :
void ratio, e = (V x Gs - Ws) / Ws :
Degree of saturation, S (%) = Gs x w / e :
P a g e | 54
P a g e | 55
Result:
Unconfined compressive strength, qc Mpa :
P a g e | 56
pH OF SOIL - O20361-S-VIA-01-DC-03000/F19
As per IS: 2720 Part 26 - 1987, Reaffirmed 2016
Equipment ID
Electronic balance ID :
pH meter ID :
Thermometer ID :
Tested by :
P a g e | 57
Sample ID No:
Date of receipt:
Date of testing:
Equipment ID:
Electronic balance ID:
425μ sieve ID:
Tested by:
Test data:
Remarks:
P a g e | 58
2 Volume of silver nitrate consumed by the blank sample (distilled water), ml (V2)
Chloride,
mg/l
= (V1-V2) X N X 35450
V3
P a g e | 59
PH OF WATER - O20361-S-VIA-01-DC-03000/F22
As per IS: 3025 Part 11 – 1983, Reaffirmed 2017
Thermometer ID No :
Job ID :
pH meter Temperature of
S.No. Sample ID
reading the test solution
1
2
3
4
5
6
7
8
9
10
P a g e | 60
Results
Sl. No. Details
Obtained
P a g e | 61
2 Volume of silver nitrate consumed by the blank sample (distilled water), ml (V2)
Chloride, mg/l
= (V1-V2) X N X 35450
V3
P a g e | 62
P a g e | 63
ANNEXURE 4
LIST OF LABORATORIES AND LAB
EQUIPMENT
P a g e | 64
P a g e | 65
SL NO EQUIPMENT QUANTITY
3 PERMEABILITY TEST 10
P a g e | 66
ANNEXURE-5
HAZARD IDENTIFICATION AND RISK
ASSESSMENT
O20361-S-VIA-01-DC-03000/HIRA
P a g e | 67
Hazard
Residual Risk –
Severity Rating
Low /Medium/
Requirement
Additional Control Measures
Probability
Risk Level
Responsibility
Rating
Sl. (If the list is exhaustive, give
Legal
High
Activity Existing Control Measures
No Source / Situation / only a Doc. ref no. of Safe
N/A/E
H/S
Possible Outcome People at Risk Work Method)
Act
Strict supervision
P a g e | 68
P a g e | 69
1 First Aid treatment only Not likely to cause ill health 1 Most Unlikely
Colour
Description
legends
L Acceptable, the activity shall be performed under supervision
Unacceptable, effective control measures must be taken up to
M
ALARP level
Totally unacceptable effective control measures must be taken up to
H
ALARP level
P a g e | 70
ANNEXURE 6
CURRICULUM VITAE
P a g e | 71
Education:
Year of
S. No. Degree(s)/Diploma(s) College /University
passing
M. Phil., (Geology) Presidency College, University of Madras,
1 2003
Chennai
M.Sc.,(Geology) Presidency College, University of Madras,
2 2001
Chennai
B.Sc.,(Appl. Geology) College of Engineering Guindy, Anna
3 1999
University, Chennai
Employment Record:
P a g e | 72
P a g e | 73
Education:
Year of
S. No. Degree(s)/Diploma(s) College /University
passing
1 MSc Applied Geology KUVEMPU University, Shimoga Karnataka 1998
Sahyadri Science College from KUVEMPU
2 BSc 1996
University, Shimoga Karnataka
Employment Record:
July 1998 to May 1999 M/s CEE SOUTH, BENGALURU Project Hydrogeologist Consultant
Piling, Pile cap and Pile test, pile cap and Construction of 10000 piles.
pedestal works, Panki, 2018-2020
Conducted 275 load tests ( maximum in India )
Kanpur
Construction of Intake well Deputy project Manager - Construction of 48.6 metre depth,
with 14 metre diameter 14 metre diameter intake well and 2.6 km length pipeline
2016-2018
and 2.6 km pipeline bridge
over the Sone River. bridge over the Sone River.
P a g e | 74
P a g e | 75
Education:
S. Year of
Degree(s)/Diploma(s) College /University
No. passing
Post Graduate Diploma in
1 Remote Sensing & Geographic NPTI 2008
Information System
Pt. Ravishankar Shukla University, Raipur
2 Master of Science in Geology (Chhattisgarh) 2003
Employment Record:
P a g e | 76
Airport, United concourse building (CD) situated on the west side of Dubai
Arab Emirates International Airport, and linked to Terminal 1 (T1) by an Automated
People Mover (APM) system. CD is a fully airside structure
developed under a metal shell to accommodate 17 aircraft stands (12
Code E , 4 Code F and one Code C) with contact gates and boarding
lounges. It consists of the apron floor that includes most of the
technical and support areas as well as a bussing area for remote gates;
a first floor dedicated to the departure level, comprising boarding
lounges and a main concession area (retail, duty free, food and
beverage, and other services); a second floor housing arrival galleries
and different first/business lounges; and a partial third floor for MEP
services. Works comprise all infrastructure utilities and networks,
and landscaping. Footprint area: 64,460 m2. Gross built-up area:
149,600 m2.
Detailed design and tender documents (under BIM management), and
supervision of construction for two main steel and concrete structures
namely, (1) the main Ground Support Equipment Maintenance
(GSEM) facility on a site area of 32,947 m2 and a total built-up area
Dubai Airports
of 24,400 m2, comprising a ground level for 3 large maintenance
Strategic Plan 2020
(SP2020) Support spaces, workshops, electromechanical and storage areas, and 2
Facilities - mezzanine levels for staff facilities, offices and additional
2011-2013
GSE/ULD electromechanical and storage spaces in addition to a surrounding
Maintenance area for car-parking, external washing bays, painting workshop and
Facilities, United security control gates; and (2) the ULD Maintenance single-storey
Arab Emirates.
building on a site area of 10,532 m2 and a total built-up area of 8,027
m2, comprising welding and metal workshops, dolly maintenance
area, welding laboratory, offices, and storage and electromechanical
spaces.
Dubai Airports Detailed design and supervision of construction for the relocation of
Strategic Plan 2020 the existing Horse Quarantine facility so as to have its site available
(SP2020) Support for the relocation of the GSEM building and ULD facilities. Works
2011-2013
Facilities - Horse
comprise all infrastructure utility networks and systems
Quarantine, United
Arab Emirates.
Detailed design and supervision of construction for stands' upgrading
and airfield improvement works to meet the growth of Emirates
Airlines, FlyDubai fleets and other airlines as well as to improve the
level of service at the airport. This includes an additional remote
Enhancement of stand north of fuel farm, marking works for temporary stands at the
Airfield Capacity at Royal Airwing (five for Code E and one for Code D aircrafts),
Dubai International 2011-2013 additional stands at Charlie Apron, 7 temporary pre-Concourse
P a g e | 78
Airport, United D stands for wide-bodied aircrafts, northern runway upgrading and
Arab Emirates resurfacing, various airfield improvements (south runway and all
taxiways/taxilanes) in addition to all related electromechanical and
low-current systems, marking and signing schemes, fire-fighting, wet
infrastructure utilities and networks, and upgrading the Jet fuel
hydrant system.
Design and supervision of construction for eight nine-storey
residential buildings (91,000 m2), a large nine-storey
commercial/office building (31,000 m2), the Public Authority of
Social Insurance (PASI) headquarters building (11,470 m2) and 3
Mixed-use basement levels for car-parking and services (69,000 m2). The
Development at
2010 project also includes a 955 m2 health club. Works comprised internal
Bausher, Oman
roads, wet infrastructure and irrigation systems, power supply, low-
current and telecommunication systems, parking areas and site
landscaping. Total site area: 37,327 m2. Total built-up area: 202,059
m2.
Topographic survey, subsoil investigation, geologic mapping,
preliminary engineering design and environmental impact
assessment, design of slope stabilisation measures, and design of
sophisticated bridge foundation systems and tunnels bored through
rock, for the railway network in Jordan. The network includes main
line and spurs/links with a total length exceeding 1,000 km. The
Jordan Railway project consists of a single-track platform suitable for standard gauge
Network, Jordan. 2009 track, running North-South and East- West across Jordan with train
speeds of 160 km/h for passengers and 120 km/h for freight. The
route passes through 5 tunnels having a total length of 18 km, 24
viaducts totalling 18 km, 118 wadi bridges, and more than 200
overpasses/underpasses, with all drainage facilities. The project also
includes 11 terminals and all electromechanical systems for tunnels
and other project components.
P a g e | 79
Education:
Year of
S. No. Degree(s)/Diploma(s) College /University
passing
M.Tech.(Geotechnical National Institute of Technology, Warangal
1 2006
Engineering)-
2 B.Tech. (Civil Engineering)- National Institute of Technology, Warangal 2004
A.A.N.M&V.V.R.S.R Polytechnic
3 Diploma. (Civil Engineering)- 2000
Gudlavalleru
Employment Record:
June 2010 – March 2014 Haridwar Infrastructure Limited Sr. Manager(Quality & Geotechnical)
July 2006 – August 2007 Ijm India Infrastructure Limited Senior Site Engineer
P a g e | 80
P a g e | 81
P a g e | 82
Executing of support anchor piles for Pile load test and pull out test
conductions on site and interpreting the data to estimate the
settlements criteria tolerance. Lead the timely implementation of IS
Test procedures, NDT Testing, reviewed the GFC drawings
Checking the BBS for the Pile cages prepared on site and also Pile
cap before laying of Concrete
Preparation of site daily Geotechnical activities and maintaining the
DPR and tracking for the same.
Monitoring construction activities of shoring works such as
Contiguous & Secant Piles, Diaphragm & Retaining wall, Reinforced
Earth walls, Rock bolting.
Reviewing all methodologies such as ground improvement works
such as Compaction, Reinforced Earth walls, Gabion walls, Shoring
systems, Dewatering etc.,
Lead the timely implementation of IS Test procedures, NDT Testing,
reviewed the GFC drawings.
Monitoring Rock Bolting activity and cross checking the same by
conducting pull out test in compliance with IS 11309.
Reviewing the GFC Drawings according to the convenience by
raising SER.
Reviewing the mix design of concrete and giving suggestions if any
required according to site conditions complying with IS 10262.
Preparation of brief report for each and every test indicating results,
classifying the soil properties with reference to IS 1498 – 1970 and
calculating the bearing capacity complying with the requirements of
IS 1888 - 1982 and conclusions for the same.
P a g e | 83
P a g e | 84
Monitoring and checking the soil investigations and all field and in
situ tests such as SPT, USC, Point Load Strength, TCR, SCR, RQD,
etc. in Compliance to BS 5930 and also aligning the same with QCS.
Reviewing the design calculations of shoring works such as
Contiguous & Secant Piles, Diaphragm & Retaining wall, Reinforced
Earth walls, Rock bolting.
Review and approval of Contractor Submittals GFC Drawings, Bar
Bending Schedules, Geotechnical reports, methodologies, Onsite
tests and coordinating with Concerns
Involved in Design of Pile Foundations, Raft Foundations and Spread
Footings
Monitoring Earth work excavation in compliance to Slope satiability
analysis
Coordinating and helping in external and internal coordination to all
Hydro Power,
Geotechnical Works.
Wind Power and
Involved in review of shoring Structures as Contagious Piles, Secant
Solar Power
Piles and Retaining Walls, Reinforced Earth walls, Rock bolting.
Projects (Dikchu
Preparation of brief Geotechnical Desktop Study report for in House
Hydro Electric 2010-2014
Projects from the past reference reports as Base and indicating test
Project – SIKKIM
results, classifying the soil properties with conclusions.
and Surang Hydro
Coordinating with the geotechnical agencies, Contractors on site and
Electric Project
reviewing the soil investigation methods and Tests required as per the
Himachal Pradesh)
IS requirement.
Executing of support anchor piles for Pile load test and pull out test
conductions on site and interpreting the data to estimate the
settlements criteria tolerance.
Conducting and Monitoring Pile Load Tests on site on Trial piles
casted.
Preparation of site daily Geotechnical activities and maintaining the
DPR and tracking for the same.
P a g e | 85
P a g e | 86
P a g e | 87
ANNEXURE-7
SAFE OPERATING PROCEDURE FOR
PREVENTION OF COVID-19
P a g e | 88
TABLE OF CONTENTS
1 PURPOSE 3
2 SCOPE 3
3 ABBREVIATIONS 3
4 DEFINITIONS 3
5 RESPONSIBILITY 4
6 PPE TO BE USED 4
FLOW CHART RESUMING OPERATIONS AFTER
7 5
LOCKDOWN
8 PROCEDURE 7
ADDITIONAL MEASURES FOR PROJECT SITES/COUNTRY
9 22
OFFICES
10 RATIONAL USE OF PPE BY ESSENTIAL STAFF 23
11 24
12 ANNEXURES 27
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
1.0 Purpose
2.0 Scope
This SOP is applicable to all L&T Construction employees, Sub contractors and their employees.
It shall be applicable to activities at site for various projects in L&T Construction operation while
restarting activities post lock down due to Covid-19 and maintaining thereafter till normalcy is
declared by the Government authorities.
3.0 Abbreviations
4.0 Definitions:
COVID-19 is a new strain of virus belonging to the family Coronaviridae and sub-family
Coronavirinae. It is a zoonotic virus which means that it can be transmitted between animals and
humans, presently being transmitted uncontrollably between human to human.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Competent person: A person who possess adequate knowledge about COVID-19 and possess
abilities or skills to carry out the work as prescribed by WHO recommendations/other Government
prescribed standard operating procedure etc. without risk to health.
PPE: Any equipment/device/gadget that will protect the user against health or safety risks from
infecting the user and protect others from spreading it. It can include items such as face covers,
face masks, Goggles, Gloves, Hazmat Coats / Aprons, Shoes etc.
5.0 Responsibility
It shall be the responsibility of the line function (Project Manager /Construction Manager / Admin
/ Section in charges/ Site Engineer / EHSO) to implement this Procedure.
6.0 PPE to be used
Face Mask
N-95 face mask the respirator blocks at least 95 percent
of very small (0.3 micron) test particles.
Preferred with proper fit nose clip, hypoallergenic,
polyisoprene head band
Apron
Body protection Apron according to IS 6153:1971
Apron of 70gsm non-woven fabric also shall be issued
to First Aid or Health care personnel at site.
Face shield:
Reusable face shield with good transparency and anti-
fogging characteristics shall be used. Reusable face
shield shall be sanitized for every use.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
COVID -19
Meetings/training/mass tool
Avoid public transport box shall be avoided. Virtyal
meetings shall be preferred Disinfect portable hand
tools
8.0 Procedure
Controlled access inside the project and workmen habitat
All entry inside the site shall be monitored with thermal scanner to ensure temperature < 99.4
degree Fahrenheit (including staff, workmen, visitors, etc.)
Pre-approval for deployment of new workmen from PM
Avoiding entry of new workmen from known hotspots of COVID 19
Allocate separate rooms for the new workmen in the workmen habitat minimum for 14 days.
Ensuring availability or visit of medical practitioner at workmen habitats.
O -Declaration Form (ANNEXURE C)
the COVID-19 risk level of workmen
Medical check-up by doctor on periodicity as required.
Contact less thermal scanning
The modality of operation, can be decided by the CEO, HR Head & PM based on the workload,
official need, local administration factors enforced by Government authorities, employee
convenience etc.
Few significant actions need to be ensured and followed for all the activities/ process.
operated.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
During the restarting activities, LOTO shall be strictly followed while cleaning drum, conveyor in
batching plant and other plants.
Cables shall be routed overhead avoiding the contact with any other vulnerable equipment/human.
e. Excavation
Any work in/near excavation shall be allowed after checking the soil condition, slope, access,
dewatering and other requirements. Soil condition around the excavation shall be verified for any
chances of sliding or collapse.
Access and slope to the excavation shall be checked
Dewatering pump and electrical installations to the pump shall be inspected for its safe siting.
Barricades & sign boards shall be ensured for its safe condition.
Site offices
Sanitation of all tables, system, files, cabins, office machines shall be done.
Temporary electrical connections and access ways shall be checked with the office inspection
checklist.
Double bin system shall be implemented to collect the waste after first day of resuming, the
collected waste shall be kept unattended for at least 24 hours.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Individual water bottle shall be provided/each staff shall be advised to keep their personal water
bottles.
Wearing mask is mandatory for all while entering site office premises
Avoid gathering of people in lobby, parking and other common places
Temporary electrical connection and access ways should be checked with the office inspection
checklist.
To ensure safe and portable drinking water, clean water coolers and test the water quality (at outlet)
for at least bacteriological contaminant and report should be recorded.
Pantry
Health condition of office boy/assistant shall be checked before deployment and daily temperature
monitoring shall be done.
All the garbage shall be cleared off and area & bins disinfected.
Gas connections shall be checked, and supply line & wire shall be inspected if it is an induction
strove.
Expired items in pantry shall be disposed off from use.
Office snacks shall be packed food items, handling of loose items/unpacked items shall be avoided.
Old vegetables and expired items shall be disposed off safely.
P&M Workshop
All the machines shall be guarded and tagged for safe condition.
Connections and earthing shall be verified
All the tools shall be safely secured.
Housekeeping shall be done initially.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Store
Expiry date of chemicals and consumable items shall be verified
All the area inside the stores shall be verified for insects / pests.
Diesel storage area and other flammable liquids shall be checked for any Leakage and
accumulation of flammable / toxic gases. The space shall be ventilated well before use.
All store persons shall wear protective PPEs (nose mask, hand gloves, goggles)
Quality workshop
Any chemical used/ exposed shall be removed
All the machines shall be checked for safe condition.
Arrange for calibrations of equipment, if its overdue.
Carpentry workshop
Guard shall be ensured in rotating parts of circular saw and other machines.
Saw dust and other wastages shall be disposed off .
Remove all the cut pieces, scattered wooden pieces and nails scattered in the surrounding
Sanitize conveyance vehicle / bus of staff and workmen prior to start of each trip
Social distancing (min.1 meter) shall be maintained in conveyance vehicles of workers/staff
Plan to execute the work sequence only with minimum number of workmen.
Deploy workmen in different locations, wherever feasible to ensure social distancing.
Deployment of workmen in staggered manner in case of congested work locations
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Medical Checkup
New induction of workmen shall be done after stringent medical checkup by the medical
practitioner.
The medical practitioner shall consider the additional information provided by the workmen in the
screening, while checking the workmen
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Any employee having cough, cold or fever must stay at home and WFH until they become
symptom free and get medical certificate.
Employees with bronchitis/ emphysema/ asthma/ chronic respiratory ailment chronic immune
suppressed condition, pregnant employee and lady employee having children below 6 years
coming from hotspots/ containment zone is recommended to WFH up to 2 weeks from resumption.
All employee / workmen are encouraged to use Aarogya Setu app on their mobile whenever
residence and in the premises / work area till the time employee / workmen reaches back home.
EHS Induction
Number of workmen participating in EHS Induction shall be restricted to maintain the social
distance during training.
Apart from the regular EHS induction, workmen will be trained on COVID--9 risks and the
precautionary measures covering the following topics,
Symptoms of COVID-19
How virus spreads
Importance of maintaining social distancing
ANNEXURE A
Reporting in case of symptoms like Flu
Attendance System
Bio metric (finger touch) swiping for attendance shall be reinstalled.
1. Wash finger with hand sanitizer
2. Place finger on sensor
3. Wash finger again with hand sanitizer
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Visitors Entry
Allow with proper compliance such as SDF, facemask, social distancing and temperature scanning.
B. Staff Members
Strategy adopted for COVID 19 risk management
Practice the action items from this SOP related to staff members
Specific roles & responsibilities related to COVID 19 response
Social distancing measures
Promoting self-hygiene & respiratory hygiene
Handling suspected cases of COVID 19 & informing to ERT members
C. Frontline Supervisors
Practice action items corresponding to Frontline supervisors from this SOP
Specific roles & responsibilities related to COVID 19 response
Social distancing measures
Promoting self-hygiene & respiratory hygiene
Handling suspected cases of COVID 19 & informing to Staff / ERT members
F. Resources
Resources required specifically required to manage the COVID 19 risk shall be identified, planned,
procured and made available at workplaces in adequate quantities. The resources which are
required to manage COVID-19 risks may include:
Thermal scanners
Contactless attendance system
Availability of liquid soap / hand sanitizer in strategic locations and stock for refilling them.
Hand washing facilities
Team for cleaning & disinfecting workplace locations.
Appropriate PPE like face covers, masks, goggles, coats / aprons shoes and appropriate
disinfecting gadgets like sprayers, brush etc. shall be made available.
Nose masks for teams who are screening workmen, conducting medical checkup & disinfection.
Wearing face mask is mandatory at all the times inside the site premises.
Disposable mask will be treated as bio medical waster and will be disposed as per BMW rules (
yellow bad)
Reusable / washable mask will be disposed off after through wash with surface disinfectant.
Strictly ban gutka / tobacco products in all work premises
Hand gloves for teams who are screening workmen, conducting medical check-up & disinfection
Quarantine facilities for accommodating symptomatic workmen in workmen habitats.
Posters & Promotional material for creating awareness
Sample poster from Ministry of Health & Family Welfare given below
Additional posters, videos & audio resources for COVID-19 can be accessed from the following
website link https://www.mohfw.gov.in/ ( under resources section) Additional rest areas and
dining spaces
Additional exit & entry points to avoid over crowding
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
G. Operational Control
A specific meeting shall be organized at the site including PM all Section In-charges and senior
staff members.
This SOP shall be discussed pointwise and site-specific action plan shall be drawn including,
Action points location wise / department wise
Allocation of responsibilities and accountabilities for each action item
Resources required
Target dates
Pre-requisites before starting the activities
Periodic disinfection of tools and tackles
Disinfecting all PPEs
Display contact details of ERT members in isolation facilities
Manual attendance register for workmen.
Targeted inspection specific to COVID-19 risks shall be conducted to verify compliance to this
SOP.
The summary of the compliance shall be reported to PM / Head- EHS before starting the operations
and after that on a weekly basis.
The cooperation of all persons shall be strictly ensured and any violation shall be viewed seriously.
Refer ANNEXURE B
An employee having cough, cold and fever must stay at home and WFH till they become symptom
free and get a medical certificate
I. Management Review
The implementation status of this all applicable SOP and site-specific action plan shall be complied
with and reviewed pointwise before according permission for restarting the activities.
The compliance level shall be reviewed there after every week till the COVID 19 risks are
completely mitigated.
Maintain regular housekeeping practices, including routine cleaning and disinfecting of surfaces,
equipment, and other elements of the work environment.
When choosing cleaning chemicals for disinfection, projects shall consult with local authorities or
Subject Mater Expert for appropriate disinfectant against emerging viral pathogens of COVID19.
Chemicals having quaternary ammonium, sodium hypochlorite or hydrogen peroxide as active
ingredient should be used for area disinfection.
Ensure sufficient supplies and materials, including tissues and hand sanitizer for all participants.
Have surgical masks available to offer anyone who develops respiratory symptoms.
Advise participants in advance that if they have any symptoms or feel unwell, they should not
attend.
Briefly explain the participants on the actions being taken to prevent COVID-19
Avoid handshake and practice ways to say hello without touching
Encourage regular handwashing or use of an alcohol rub by all participants at the meeting
Encourage participants to cover their face with the bend of their elbow or a tissue if they cough or
sneeze. Supply tissues and closed bins to dispose of them.
Display dispensers of alcohol-based hand rub prominently around the venue.
Arrange seats so that participants are at least one meter apart.
Open windows and doors whenever possible to make sure the venue is well ventilated.
Soon after the meeting, the area shall be dis-infected and dust bins shall be cleared.
Put the door stopper until all the participants arrived to avoid multiple times opening/closing of
door.
In addition to the regular PPE, nose masks and hand gloves for teams who are screening workmen,
conducting medical checkup & disinfection and others those who need to work in proximity to a
greater number of people.
Cooking
Daily thermal screening and symptom checking of cooks.
Cleaning and disinfection on daily basis once the cooking is over.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Disinfection
Disinfection of the workmen habitat in all the places shall be carried out on a periodical basis and
closely monitored by camp boss and verified by IR officers.
9.0 Additional Measures for Project Sites / Yards and Country Offices
Type of Recommended
Activity Risk Remarks
personnel PPE
Screening of
person with non- Security guard , N-95 mask and
Moderate risk
touch volunteers gloves
thermometer
Triple layer
Receptionist Low risk
medical mask
When aerosol
Phlebotomist (lab
Laboratory Full complement generating
sample High risk
sample collection of PPE procedures are
collection)
anticipated
Non-Invasive
procedure such N-95 mask and
Technician, nurse Moderate risk
as, ECG, x-ray, gloves
sonography
Pharmacy
Triple layer
dispensing of Pharmacist Low risk
medical mask
medicines
Emergency
Transport of a Medical
N-95 mask and
patient in an Technician Moderate risk
gloves
ambulance (EMT), attendant
/ escort
Canteen serving
Triple layer
the cooked food, Canteen staff Low risk
medical mask
cleaning
N-95 mask
Housekeeping
Sanitation, deep staff Moderate risk gloves shoes/
cleaning, gum boots
housekeeping House keeping Triple layer
Low risk
supervisor medical mask
11.0
Do
Stand one behind the other closely Maintain social distancing while in queue
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Sitting by side and opposite to each other and Alternative seating. Air conditioning off.
air condition is on Doors kept open. If AC is required, then
ensure micro filter.
Visitors stand close to security reception, do not Maintain social distancing. Wear mask
wear mask. Not checking temperature. compulsorily. Check body temperature.
Floor washing and dust cleaning Disinfection done before and each shift
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Strict ban on use of tobacco and alcohol Eat more Vitamin C foods
products in all work premises.
12.0 Annexures
Annexure A
Responsibilities and Accountabilities matrix for Project Sites
Preparing a site- A R R R R
specific action Plan
Screening of workmen A R R R R R
EHS Induction R A R R
Access Control A R R R R R
measures
Training on COVID 19 R R A R R
response
Dis infection A R R R R
Risk Control in A R
Workmen Camp
Social distancing in site A R R R R R R
office & facilities
Pre start up checks A R R R R R R
location / area wise
Promoting Self Hygiene R R A R R
&
Respiratory Hygiene
Display of posters for R R A
COVID 19 Response
Organizing resources A R R R
for COVID 19 response
Maintaining social A R R R R R R R R
distance
Monitoring of A R R R R R
compliance
Reporting in case of A R R R R R R R
symptoms
Checks for COVID A R R
during safe to start of
activities
Periodical review A R R R R
Emergency Response A R R R R R
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Annexure B
Medical Fitness on resuming the duty after lockdown is lifted
Below are the guidelines for employees, staff, workmen, associates resuming the duty at
workplace in office/shop floor, after lockdown is lifted.
Category 1:
Employee/ Person with
No inter-city travel during last 14 days
No travel from overseas in last 14 days
No close exposure to individuals including single exposure short meetings with, family, relatives,
visitors, acquaintances who have travelled abroad during the last 14 days
No visit to a location declared as containment zone / micro containment zone.
Has not resided in a residential building / floor which is sealed / declared as a containment zone
in last 14 days
AND
Does not have any symptoms of dry cough, fever above 99.4 F, loss of smell, loss of taste, or
flu like symptoms, sore throat, diarrhea, difficulty in breathing, chest pain or pressure in last
7 days.
Employee is fit to resume the duties. He/ She will fill up self-declaration form (See Annexure C)
and submit to their HRBP before joining. Medical fitness certificate and /or lab test report are not
required.
Category 2:
If any employee / person has symptoms of dry cough, fever above 99.4 degree, loss of
smell, loss of taste, or flu like symptoms, sore throat, diarrhea, difficulty in breathing, chest
pain or pressure in last 07 days, will not be allowed to resume duties. He/ she is advised for
home quarantine & take treatment from his treating doctor.
However, after 7 days he/she will require to produce fitness certificate from his/her treating doctor
with / without laboratory test report.
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
At the time of resuming, he/she will require to produce fitness certificate from his/her
treating doctor with / without laboratory test reports
IF ANSWER TO ANY OR ALL OF THE BELOW QUESTION/S IS YES, THEN YOU ARE
NOT ALLOWED TO RESUME DUTIES IN OFFICE/ SITE AND SEEK MEDICAL
ATTENTION:
A. I, including my family members have come in close contact* with a COVID-19 +ve case or any
person suffering from Fever or Cough in last 14 days. YES/ NO
* This means living in the same house/room for even a short period of time during the last 14 days
B. My house / floor/ building / area is sealed / declared as a containment zone and I am not allowed
for movement out of my house / area: YES / NO
C. I, including my family members have visited any fever clinic / dedicated COVID Health Centre
(DCHC) in the last 14 days. YES / NO
D. I, including my family members suffering from any of the following symptoms in the last 7 days
: (TICK YES OR NO)
I, the undersigned hereby declare that all information provided above is correct to the best
of my knowledge and any incorrect self-
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-01-DC-03000
SPEED RAIL
QUALITY MANAGEMENT SYSTEM
Package No. MAHSR C 4
SAFE OPERATING PROCEDURE FOR PREVENTION OF COVID-19 REV No.: 0 1 Date: 23-12-2020
Annexure D
Annexure E