You are on page 1of 37

Project

Management
What is a Project?

 A project is “a temporary endeavor


undertaken to create a unique product,
service, or result”
(PMBOK® Guide, fourth Edition, 2008, p. 5)

 Operations is work done to sustain the


business
Project Attributes

 A project:
 Has a unique purpose
 Is temporary (Start and End date)
 Is developed using progressive elaboration
 Requires resources, often from various areas
 Should have a primary customer or sponsor
The project sponsor usually provides the direction and
funding for the project
project lifecycle

initiation planning execution close out

EFFORT control

execution

planning

control
initiation
close Out

TIME

AUC
Project Management Framework
Project Charter

 This is the certificate of birth for a project


 It includes many items like:
 1.01_PCoE_Project_Charter_Guide.doc
Stakeholders Management

 Stakeholders are the people involved in or affected by project


activities
 Stakeholders include:
 The project sponsor
 The project manager
 The project team
 Support staff
 Customers
 Users
 Suppliers
 Opponents to the project
Project
Scope
Management
Partial WBS (Work Breakdown Structure)
Organized by Project Phase
Intranet WBS and Gantt Chart in
Microsoft Project
Project Time Management
Activity-on-Node (AON) Network Diagram:
Example

B C
A

D E
Activity-on-Arrow (AOA) Network Diagram for
Project X
Three-Point Estimates

 Instead of providing activity estimates as a


discrete number, such as four weeks, it’s
often helpful to create a three-point
estimate:
 An estimate that includes an optimistic, most
likely, and pessimistic estimate, such as three
weeks for the optimistic, four weeks for the most
likely, and five weeks for the pessimistic estimate.

 Three-point estimates are needed for PERT


estimates and Monte Carlo simulations.
Gantt Chart for Project X
Determining the Critical Path for Project X
Using the Critical Path to Shorten a
Schedule

 Three main techniques for shortening schedules:

 Shortening the duration of critical activities or tasks by


adding more resources or changing their scope.

 Crashing activities by obtaining the greatest amount of


schedule compression for the least incremental cost.

 Fast tracking activities by doing them in parallel or


overlapping them.
Project Cost Management
How Estimating Done?

Example:
Bottom-up
Estimating
Project Human Resources
Management
Maslow’s Hierarchy of Needs

SELF-ACTUALIZATION

SELF-ESTEEM

SOCIAL / BELONGING

SAFETY

PHYSIOLOGICAL
Herzberg's Motivation-Hygiene Theory

Hygiene factors - "environmental factors" such as salary, inter-


personal relationships, working conditions, style of leadership and
types of supervision, security, type of work, working hours, status.
In a management context this means that hygiene factors don't
motivate people to do their very best but they are needed to stop
people becoming dissatisfied with their jobs.
Motivating factors - factors within a job which allow for such things
as achievement, responsibility, recognition, advancement,
challenge.
Conflict Management
(Cont’d)
The PM must carefully select the method of managing
conflict appropriate for his/her organization so that an
atmosphere conducive to constructive results is
developed .

Five methods of managing conflict :


1. Withdrawal
2. Smoothing
3. Compromising
4. Forcing
5. Problem Solving (confrontation)
Responsibility Assignment Matrix(RAM)

 2.23_PCoE_Responsibility_Assignment_Matrix.pdf
Project Communications Management

What Who

When
Where
Why
How
It is not what you say, it is how you say
it!
Model of Communication
 Sender-Receiver Model
Project Procurement
Management
Receive
Clearly Define
Issue RFI Information Evaluate Suppliers Create Short-list
Business Needs
Reports

Can be Part of RFP (Following Steps will occur after RFP)

Prepare RFP/ Host Bidders


Prepare SOW Issue RFP/RFQ
RFQ/IFB Conference

Receive
Prepare Contract Proposals/
Quotations

Select Supplier
Negotiations Sign Contract Initial Payment
and Offer

Delivery Testing Close-out Final Payment


AUC
Project Quality
Management
Total Project Quality Management
2.20_PCoE_Quality_Management_Plan_Guide.doc

Quality Assurance

Total Project
Quality Design
Quality
Control Management Basis

Continuous Improvement
Project Risk Management
Risk Management Process

Identify Risk

Analyze Risk

Respond to Risk

Document Risk
Project Close-out
Project Closeout - Major Phases
 Obtain client acceptance
 Conduct the post implementation audit
 Issue the final report
 Document the Lessons Learned
THANK YOU
Chapter 1 Outline
 The systems analyst.
 The Systems Development Life Cycle (SDLC).
 Information system project identification and
initiation.
 Feasibility analysis.

© Copyright 2011 John Wiley & Sons, Inc. 1-40

You might also like