CONSTRUCTION OF MASJITH BUILDING(First Floor) for NASRUL ISLAM

sunnath jamath at ARIVOZHI NAGAR , KOVAI.


DETAILED ESTIMATE.
SlNo DESCRIPTION Nos L B D QTY

1 R.C.C M20
a. COLUMN C1 12 1 1 12 144.00
b. COLUMN C2 2 1 1.75 12 42.00
c. LINTEL 1 140 0.75 0.75 78.75
d. ARCH SUNSHADE 27 8 2 0.33 142.56
e. ARCH BEAM 9 8 0.75 0.75 40.50
f. ROOF BEAMS RB2 1 171 1 1 171.00
g. ROOF BEAMS RB1 2 28 1 1.5 84.00
h. ROOF SLAB 1 34.5 34.5 0.5 595.13
i. WAIST SLAB 1 23 5 0.58 67.08

TOTAL 1365

2 STEEL RODS 8mm 10mm 12mm 16mm 20mm


a. COLUMN C1 80 1280
b. COLUMN C2 320 280
c. LINTEL 640 520
d. ARCH SUNSHADE 220 360
e. ARCH BEAM 360 280
f. ROOF BEAMS RB1 560 480.00
g. ROOF BEAMS RB2 1360 200
h. ROOF SLAB 4240 3360
i. WAIST SLAB 220 120
8000 4240 2160 0 480
200 106 54 0 12
964 797 586 0 362
. TOTAL 2709
3 BRICK WORK

a. Main building 1 144 0.75 12 1296.00


b. (-)W -8 5 0.75 5 -150.00
c. (-)D -1 6 0.75 7 -31.50
d. Parapet 1 140 0.75 3 315.00
e. Staire siep 14 5 0.75 0.4 21.88
f Head room 1 62 0.75 10 465.00
34.65
TOTAL 1951
4 PLASTERING

a. Main building 2 144 1 12 3456.00


b. sofits W 8 18 1 0.75 108.00
c. sofits D 1 20 1 0.75 15.00
d. Parapet 1 144 1 6.75 972.00
e. Head room 2 62 1 10 1240.00
f. Deduct W -8 4.5 4.5 2 -324.00
g. Deduct D -1 6 7 2 -84.00
h. Ceiling 1 33 33 1 1089.00
i. Mehrab 1 36 1 1 36.00
j. Sunshades 9 6 2 2 216.00
k. Waist slab 1 23 1 5 115.00
l. Landing 1 11.5 3 1 34.50
m. Steps 14 5 0.75 0.42 21.88
5.00
TOTAL 6900
5 WOOD WORKS
a. Main Door 1 6 7 1 42
b. Headroom Door 1 3 7 1 21
c. Window(withglass,fitt
ings&painting.) 8 4.5 4.5 1 162
6 GRILL WORK
a. Windows 8 1.25 4 1 40.00
b. Staire handrails 1 25 1 3 75.00
5.00
TOTAL 120

7 WALL FINISH 14500

8 FLOOR FINISH 1250

9 ELECTRICAL WORKS 1250

10 ROOF FINISHING 1250

11 MASONDRY LABOUR 1190

12 ELEVATION L.S