You are on page 1of 8

DOC NO.

: SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 1 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD

Rev. Description of Change Clause

A Initial Release N.A.

Prepared/Reviewed By

PUSH 20 Jan 2022


________________________ __________________________ ____________________
(Signature) (Project Manager ) (Date)

Approved By

SHEN ZHU YOU 20 Jan 2022


____________________ __________________________ ____________________
(Signature) (Director) (Date)
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 2 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD


1. Purpose : To define a procedure for proper erection, alteration and dismantling of
scaffolding so as to protect the worker and public from the hazard associated
with free falling and falling object.

2. Scope : This procedure is applicable to all workplace. Where work is carried out at main
contractor/ client’s premises/ site and the main contractor/ client has a SWP, the
main contractor/ client’s SWP shall be followed.

3. Reference : SWP - 05 Personal Protective Equipment


SWP - 08 Working at Height

4. Definition : Nil

5. Responsibility :

5.1 The Supervisor and Scaffold Supervisor are overall responsible for proper erection, alteration,
dismantling of scaffolding.

5.2 Qualified Scaffold Supervisor is responsible for regular monitoring of legal compliance.

5.3 Only qualified scaffold erector is responsible for scaffold erection.

6. Procedure :

6.1 Erection / Dismantling

6.1.1 The Supervisor and Scaffold Supervisor shall ensure that the affected area is barricaded to avoid
unnecessary incident. Scaffold Supervisor and Supervisor shall monitor the operation closely.

6.1.2 The Supervisor / Scaffold Supervisor shall check the certificate and valid permits of worker working on
the scaffolding.

6.1.3 The Supervisor / Scaffold supervisor shall ensure that the scaffold is being erected, added to, altered
or dismantled in accordance with the Factories (Scaffolds) Regulations 2004 and PE design.

6.1.4 Sub-contractor and site supervisor shall ensure that his worker use proper PPE i.e. safety belt,
lifeline, etc. when they are working on scaffold. Scaffold Supervisor / Supervisor shall monitor the
usage of PPE.

6.1.5 Only scaffold contractors approved by MOM will be allowed to erect scaffolds exceeding 4 meters in
height (with the exception of tower and trestle scaffolds).
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 3 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD

6.1.6 Scaffolds erected around buildings are to be provided with proper platforms at vertical interval not
more than 2 meters.

6.1.7 Prohibit the use of single row wooden scaffold because such scaffolds cannot cater for the placement
of work platforms.

6.1.8 Scaffolds to be fully enveloped with overlay nets to prevent incidents of person falling from height and
struck by falling objects.

6.2 Inspection

6.2.1 Supervisor / Scaffold Supervisor shall inspect the scaffolding at least once in a week (use
Attachment 7.2: 7.2 Weekly Inspection By Scaffold Supervisor and Attachment 7.3:
Checklist for Metal Scaffold) and also after severe weather conditions if it is likely to affect
its strength or stability or have been displaced any way.

6.2.2 During inspection they should carefully look for critical components of the scaffolding:
 Working platform and its loading condition
 Adequacy of tie back / tie rod, horizontal & cross bracing, guard rail / hand rail, sole
plate & base plate, proper joints
 Firmness & availability of toe board, overhead protection, etc.

6.3 Maintenance of scaffold

6.3.1 Supervisor / Scaffold Supervisor shall ensure that every part of the scaffold is fixed,
secured or placed in position as to prevent accidental displacement.

6.3.2 Sub-contractor shall rectify all the defects and deviations / displacement of component
immediately.

6.3.3 No person is allowed to open / dismantle any component of the scaffolding without prior
approval of PIC/ Scaffolding Supervisor.

6.4 Non-conformance and rectification

6.4.1 During inspection, if Supervisor / Scaffold Supervisor come across with any non-
conformance they shall rectify it and inform the PM / PIC about the incident. The PM shall
take action against the responsible parties.
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 4 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD


6.4.2 In the event of any warning letter or fine imposed by the authority i.e. Client, Ministry of
Manpower (“MOM”), the particular PM / PIC shall stop affected site activities associated to
the complains on the usage of scaffold and shall rectify the non-conformance to the
satisfaction of the Client’s or MOM’s requirement

6.5 Record keeping

6.5.1 Scaffold Supervisor shall keep all the inspection forms and other records as per the
Factories (Scaffolds) Regulations 2004 & Client’s requirement.

7. Attachment :

7.1 Dos and Don’ts for Scaffold

7.2 Weekly Inspection By Scaffold Supervisor

7.3 Checklist for Metal Scaffold


DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 5 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD


Attachment 7.1

DOS AND DON’TS FOR SCAFFOLD

S/N DOS DON’TS


During working on scaffolding always use life-line, Don’t use any defective or weak materials
1
safety belt/ harness, safety helmets etc. during scaffolding erection

Don’t accumulate unnecessary materials /


Barricade the affected area to avoid falling object
2 tools on working platform. Maximum loading
hazard.
220 kgf/m2 in one bay.

Use proper ladder / staircase to move into the next


3 Don’t use scaffold as a ladder.
working platform level.

Use at least 500mm wide working platform while Don’t dismantle scaffold without a valid
4
working on a scaffold. permit-to-work.

Remove concrete and all other debris from the Don’t work on a scaffold during severe
5
working platform weather like rainstorm.

Follow emergency procedure i.e quickly & safely Don’t panic during emergency situation
6
move toward the assemble area in case of fire. while working on a scaffold

Don’t remove any component of the


Before shifting of tower scaffold ensure no man/or
7 scaffold without Scaffold Supervisor’s
heavy material on the working platform.
permission.

Attachment 7.2
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 6 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD

WEEKLY INSPECTION BY SCAFFOLD SUPERVISOR

Site :
Location of Scaffold:
Type of Scaffold :
Height of Scaffold :

Inspection No. Inspection Date/Time Scaffold Supervisor/Professional Engineer


Name/Signature

Contractor

Conditions of
Components Correct
Scaffolds/
(inadequate, Method of Rectification
Scaffold Components Component
undersized, Installation Remarks
Corroded / bent
etc.) (Yes/No)
dented… etc

a. Ties-back Y/N
b. Cross Bracing Y/N
c. Horizontal Bracing Y/N
d. Joint Pins & Armlock Y/N
e. Base Plates / Sole Boards Y/N
f. Foundation Y/N
g. Working Platforms Y/N
h. Toe Boards Planks & Decking used
Y/N
for working platform
i. Guardrails (At roof top) Y/N
j. Housekeeping on scaffold Y/N
k. Debris netting Y/N
Others
Note:

1. This register shall be entered by a Scaffold Supervisor and shall be kept at the worksite for inspection by an Inspector,
pursuant to Factories Act (Chapter 104) - Factories (Scaffolds) Regulations. 2004

2. This inspection register should be kept available at the worksite for inspection by a Factory Inspector

3. If the scaffold is designed by a Professional Engineer (PE) the erection shall be done strictly according to the PE's design. A
copy of this design must be kept at the site for checking by an Inspector. If amendments are necessary, the PE must be
informed and design of scaffold amended by the PE accordingly.

Attachment 7.3
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 7 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD

CHECKLIST FOR METAL SCAFFOLD

Site : Block Nos :

Inspection No. Inspection Date/Time Name


Designation
Signature

Report of
S/N Items Remarks
Visit*

1. Record of Inspection
- Weekly scaffold register by qualified Scaffold Supervisor
2 Foundations
- Scaffold erected on firm ground
- Scaffold not endangered by open excavation
3 Sole plates
- Proper sole plates used
4. Base plates
- Proper base plates fitted to all standards or legs of scaffold
5. Foot-Ties
- Foot-Ties fitted to both inner and outer standards
6. Alignment of Scaffold Components
- Standards or Frames vertical
- Ledgers and transoms levelled
7. Torsion Cable
Tensioned torsion cable at every cantilever brack and C-Channel
8. Frames

- Standards connected end to end with either sleeve couplers or joint pins

- Armlocks installed at all vertical joints between frames


- Cross bracings are fitted and connected to frames
9. Scaffolds erected one lift above the top most level
10. Tie Back
- At every 2 lifts or at every floor starting from base
- Spaced not more than 3 bays or 7.5m apart whichever is lesser

- Spaced no further than one bay from ends in a staggered manner

- To every standard above the level of the peripheral overhead shelter

- Effective temporary tie immediately below top most level


11. Horizontal Bracings or "Lacing"

At every 5 lifts of frame, tube or modular scaffold to bother inner and outer standards

12. Debris Net


Debris screening net erected to prevent particles and debris dislodged from the
scaffold
13. Scaffold Component Material
DOC NO. : SWP-07
Fikdtec Pte Ltd
REV. : 0

SAFE WORK PROCEDURE SHEET : 8 OF 8

EFF DATE : 02 Jan 2021

TITLE: SAFE PRACTICES IN SCAFFOLD

- Scaffold components and fittings showing no signs of deterioration

- All fittings are tight and undamaged


14. Guard rails are fitted and connected to standards
15. Working Platform
- Closely decked continuous working platform with toe boards immediately below top
most level (Minimum width 500 mm)
- Closely decked continuous working platform with toe boards at every sixth lift of metal
scaffolding

- Closely decked isolated working platform with toe boards with guard rails

- Metal deckings are held down securely to prevent uplift and cantilever effects
- For timber and metal deckings, the plank used shall be at least 200mm wide and
38mm thick and it is not projecting beyond its end support by more than 4 times its
thickness
- The maximum loading for persons and materials on any work platform in any bay
shall not exceed (220 kgf) per square metre.
16. Peripheral Overhead Shelter

Continuous peripheral overhead shelter provided not endangered by moving machinery

17. Professional Engineer's Drawing


Scaffolds are erected strictly in accordance with the Professional Engineer's design
and drawings
18. Scaffold Dismantling/Erection
Warning Signboards
- Warning signboards stating "Caution. Do not use the Scaffold" in 4 official languages
placed at strategic locations
Tie Backs
- Tie backs are not released in advance of scaffold dismantling
Barricades
- Barricades erected to restrict access to the scaffold
Dismantled Scaffold Components

- Dismantled scaffold components brought to the ground by safe method

Qualified Scaffold Supervisor

- Qualified scaffold supervisor supervises the scaffold erection / dismantling operation

Qualified Scaffold Erectors


- Qualified scaffold erectors erecting / dismantling the scaffold

- Working Platform 500mm provided at working level erecting / dismantling the scaffold

- Safety belts and lifelines used by the scaffold erectors


19. Others
* / = Satisfactory / Yes x = Not provided / Not Satisfactory / No
NA = Not A.pplicable - = Briefing Remark / Advice

You might also like