WORK ORDER

Requestor Admin : Rina Juniati Work Order No. : FR/CNSTRC-RFP/262/III/2024


Proposed Request Order to : SCM Department I-Solution PIC : Erlanga Andy Rasyid
Rekomendasi Subkon : PT Fava Hasun Mandiri
Request Wok Order : 26 Maret 2024
Project ID Number : Project Start :
Node ID Number : Target Done :
Project Name : RFP Kuningan (BU-3)

Bersama ini kami ajukan Project Request Order Pekerjaan Construction, dengan Volume Pekerjaan terlampir sebagai berikut :

No. Item Description Part Number Unit Quantity


1 XL32KNG02366 Desa Nusaherang FLM-RFP Homepass 221

Detail Pekerjaan :
FDT 96C installation in pole PNRO-INSTFDT96C
Pemasangan Install FAT Aerial PNRO-INSTFAT
FO spareloop (incl crosssection frame) PNRO-FOFRM
Penempatan FO (AE), incl lashing PNRO-FOAIR
Install strand wire + pole bracket PNRO-MESSINS
Supply + install FAT & FDT label (paint) PNRO-SUPINSTFATFDT
Splicing FO cable(+closure installation) PNRO-SPLFO

NOTES / REMARK PROJECT :

26 Maret 2024
Requested by, Reviewed by, Approved by,

Amrah Budiansa Houtsma Simontomboy Risan Zunaedhi


Head of BU Head of PMO Chief of Project