PMM32-e-07-2024 –Clarification to Pre-bid Queries

Clarification furnished by
Ref. Cl. Clarification points raised
APTransco as corrigendum
Eligibility criteria- we request you to kindly confirm that will As per specification
clause (1) of sec-I you consider the supplies made to Joint
Venture companies such as BSES for pre-
qualification. BSES has 51% stake of
Reliance and 49% is of Govt of Delhi.
5.0 Technical May also consider accepting credentials Performances of battery
requirements available for integrated DCDB chargers with inbuilt
DCDB will also be
considered.
Section IV Request for a maximum of 3 locations for As per specification
delivery
5.0 Technical 220 V 100 AH DC multifunction meter
requirements (10 A FC/ 20 A FCBC) charger: should be provided with
According to Market standard there is No RS-485 with single line
manufacturer have 2 Line display. So, we display.
will provide DC multifunction meter with
RS-485 with single line display.
5.0 Technical 220 V 100 AH MCCB/MCB shall be
requirements (10 A FC/ 20 A FCBC) charger: mounted inside Battery
For previous order we done the same. Chargers Panels.
However during inspection , they changed
the flush mounted into inside of the
charger. Same as we need clarification.
5.0 Technical 220 V 400 AH Either HMI display as per
requirements (60 A FC/ 100 A FCBC) charger: specification (or) TFT
Instead of HMI display we will provide display with Manual/Auto
TFT display additional with AC & DC mode selector switch,
Multifunction meters and TFT display VRLA/Tubular mode
only display the parameters can’t able to selector switch and
control charger function. FC/FCBC selector switch
shall be provided.
5.0 Technical For DCDB panels
requirements We can perform and submit the report As per the specification
during Supply – Degree of protection test
as per IEC60529 –IP42.

We can perform and submit the report


during Supply

We can perform and submit the report


during Supply

We can perform and submit the report


during Supply
We can perform and submit the report
during Supply

 Due dates of Bid are extended as follows


Bid Submission Closing Date & Time : 10.04.2024 upto 05:00 PM
P.Q / Technical Bid Opening Date : 10.04.2024 at 05:15 PM
All other Terms and Conditions remain unaltered as per APTRANSCO Specification

Sd/-
Chief Engineer/Transmission