Report No: 01 Duration: 16 Nov, 2023 31 Dec, 2023
o
Name: Abdul Rafay Date: 15 January 2024
Designation: Management Associate
P.No: 30000661 APP. Batch: 27 To: IN CHARGE - L&D UNIT
Unit/DEPTT: PSG-Operations Thru:
1. API study: Following APIs were learnt and evaluated including Cooling tower, Steam turbine,
Furnace, Combustion and fuels, Process & Control, Introduction to compression, Heat and
temperature.
2. AUTOCAD training: Basic level AutoCAD training was attended, grabbed an opportunity to learn
how to read and sketch 2D diagrams on AutoCAD.
3. Safety Guidelines: Overview of plant safety was discussed thoroughly including emergencies and
responses.
4. Departmental Orientations: Orientations were attended to have an overview of organogram and
job duties of every department.
Comprehensive learning of PIDs along with lines tracing at plant site was carried out for following
circuits.
Water and Steam Circuit (Steam Drum, Economizer, Attemperators, Super heaters).
Air Circuit (Primary, Secondary & Loop seal air).
Vent and Drain Circuit (Flash Tank & Blow Down Tank).
Solid feeding circuit (Coal, Limestone & Sand feeding).
Productive discussions were held, and tests were conducted for P&IDs from Department end.