MONTHLY PROGRESS REPORT

(FOR MANAGEMENT ASSOCIATES)

T
Report No: 04 Duration: March 01, 2024 April 01, 2024
o
Name: Muhammad Saqib Date: 16.04.2024
Designation: Management Associate - PSG
P.No: 30000663 APP. Batch: 27 To: L&D UNIT
Unit/DEPTT: PSG-Operations Thru:

DETAIL OF ACTIVITIES& LEARNING

Planned Activities Completed Activities


 Boiler Auxiliary  Understanding of ID fan , SA fan & PA fan startup
Startup and procedures.
Changeover  Understanding of startup and changeover
Procedures procedures of lube oil pump system & blowers.
 Test conducted regarding training at operation
depart

 Boiler Analog and  Study of analog and motor logic.


Motor Logics.  Understanding of layout of boiler analog control
circuits and also tripping value of boiler equipment .
 Understanding boiler permissive and interlock
condition.
 Test conducted regarding training at operation
depart.

 PTW Training  Introduction to PTW procedure.


 Understanding SOPs of PTW outline guidelines for
requesting, issuing, and closing permits.
 Test conducted regarding training at L&D.

 P&ID of STG-04 &  STG-04 & STG-03 circuit of P&IDs studied, and line
STG-03 Circuit. tracing carried out in area. .