RIG N-4 (Dhok Hussain Well # 01 Workover) To: C.E. (Prod.)-NB FAX NO. From P.E / OM RIG N-4 Date: 01-04-2024 C.C 1. M (PROD)-NB 2. S.E (Prod)-NB 3. A.E (Prod)-NB SUBJECT: WORKOVER JOB REPORT REPORT DATE : 31-03-2024 TO 01-04-2024 FORMATION : Hangu & Lumshiwal WORKOVER DAY : 14 7” PERMANENT PACKER (TOP & BOTTOM) : 4807 M & 4516.7 M 7” LINER TOP (35 PPF) : 3577 M PBTD : 5001 M TD : 5008 M Perforation Interval : 4983 M – 4835 M (Gross Int:106M, Net Interval: 70M) FLUID IN HOLE (BRINE) : S.G 1.01 Time Log Hrs OPERATIONS From To 2nd Trip with Over Shot: Reciprocated the string to release LSA between 90 to 120 Tons, but no success. 0600 1800 1200 Increased over pull with increment of 2 to 4 tons up to 140 tons, string remained under tension for 30 to 40 mints at each increment. Again reciprocated the string between 140 Tons to 90 tons to release LSA, but no success. During work out at fishing string with increase over pull increment of 4 tons (from 140 to 144 tons), string got break and weight dropped down to 1800 2100 0300 23 Tons. Total Over pull applied: 54 Tons String neutral weight: 90 Tons 2100 2200 0100 Carried out circulation with brine of SG 1.01 and Found well static. POH Over Shot fishing assembly along with fish up to surface. Found 19 No's PH-6 TBG joints recovered with full length and 02 broken joints. 2200 0400 0600 19 TBG Joints= 178.528 M 1 broken joint= 9.125 M 2nd broken Joint= 8.54 M Total Recovered length: 196.193 M 3rd Trip with Over Shot OD 5-3/4”: Prior to RIH fishing assembly, observed minor gas bubbles, made 0400 0600 0200 circulation with system brine 1.01. Observed well found static. M/up & RIH overshot fishing assembly down to 290M. At 0600 Hrs: RIH fishing assembly down to 290 M and in progress.