SITE MATERIAL REQUEST (SM

Prepared by: Name/ Deptt. Date (yyyy-mm-dd) SMR reference no.

Adeel Alam 15/02/2024 A


Project Name ONE Site WBS no. Site NW number no. Site ID
NEXT NA NA 5308
Requested Delivery Date (yyyy-mm-dd) Contact person Telephone no.
As per call off As per call off
Site type (Tick one) Geographical Coordinates

xx Green Field Roof top Basement Exch. Building


Access permission (Tick one) Distance from WH (if available) Height of the building/ number of storeys (if roof top)

x Available Not required


Remarks:

Product number Description Unit Quantity


(Ea, Mtr, set etc)

DELTA FR48-2000W NON ERICSSON RECTIFIER MODULE pc 1

Technical approval (Signature) Ordering approval by (Signature)

Name in print Name in print

Adeel Alam Adeel Alam


Date (yyyy-mm-dd) Date (yyyy-mm-dd)

15/02/2024 15/02/2024