Professional Documents
Culture Documents
Mumbai
EMP is designed for mitigating the possible adverse impact of a project and for
ensuring to maintain the existing environmental quality. The EMP talks about all aspects of
planning, construction and operation of the project, which are relevant to environment. It is
important to implement the EMP right from the planning stage and then continuing it
throughout the construction and operation stage. Therefore the main objective of the EMP is
to identify the project specific activities that would have to be considered for investigation of
the adverse impacts and the mitigation measures required.
Management Environmental
Act Review Policy Plan
Implementation
• Roles and
Check Responsibilities
Do
• Training and
Communication
• EMS Document Control
• Emergency Preparedness
and Response
9.1
Environment Impact Assessment Report for Proposed SRA project at Oshiwara,
Mumbai
This EMP is planned towards strategizing in reduction of impacts on following factors, both
in construction and operational phase:
Air environment
Noise environment
Surface and Ground Water
Ecological aspects
Transportation
Human Health
Land use
Socio Economics
Table 9.1shows the mitigation measures will propose during Construction and Operation
phase
Table 9.1: Details for Mitigation measures for Construction Phase
The Environmental Management Plan (EMP) is a site specific plan developed to ensure
that the project is implemented in an environmental sustainable manner where all contractors,
including consultants, understand the potential environmental risks arising from the proposed
project and would accordingly take appropriate actions to properly manage that risk.
9.2
Environment Impact Assessment Report for Proposed SRA project at Oshiwara,
Mumbai
Adequate planning would aid in mitigating some of the negative impacts and also lead
towards betterment of human health and environment. Short term negative impact of the
proposed project would be during the construction phase.
A management structure that includes an organizational chart encompassing all staff
responsible for environmental work is to be included within the EMP. An administrative
structure will help create a framework and denote roles and responsibility to personnel during
operation and construction phase. This will set out to eliminate or reduce the risks from
possible negative impacts of proposed project. Illustrative key roles and responsibilities are
set out in Table 9.2
Role Responsibility
Construction Manager Responsible for management of the construction phase of the
project. Has overall responsibility for the environmental performance
of the project
Site Materials & Responsible for implementing the Site Waste Management Plan
Waste Manager during the construction phase to ensure that waste is disposed of
legally, economically and safely.
Construction Compliance with environmental legislation, consents, objectives,
Environmental targets and other environmental commitments, including those arising
Manager from the Environmental Statement.
Site staff To receive general environmental awareness training, and
Undertake work in accordance with Method Statement Briefings and
toolbox talks. Trained personnel to manage particular tasks such as
refueling plant and equipment, managing the stores, water quality
monitoring and supervising the segregation and collection of waste.
Client Project Manager To ensure that the Contractor complies with all the relevant legal
requirements, commitments and targets agreed for the scheme.
Designer To provide information relevant to construction that may assist the
Contractor to manage environmental aspects of the scheme.
Community Liaison Communications with the public and interested parties, outreach and
Officer education, where appropriate.
9.3
Environment Impact Assessment Report for Proposed SRA project at Oshiwara,
Mumbai
During operation phase; environment cell shall report to chairman of the society and it
must comprise of in house and empanelled experts. The role of the environment cell
during operation phase will be:
Maintaining STPs, SWM units, RWH, carrying out environmental audits, safety
audits, etc.
Maintaining landscape and safety of the society
Maintaining compliance monitoring as per direction of MoEF
9.4
Environment Impact Assessment Report for Proposed SRA project at Oshiwara,
Mumbai
Table 9.3 and 9.4 gives the details of EMP costing for Construction Phase and Operation
Phase.
9.5
Environment Impact Assessment Report for Proposed SRA project at Oshiwara,
Mumbai
9.6