Professional Documents
Culture Documents
Brent Robinson
Vice President, PDI
Principal Engineer, GRL Engineers, Inc.
216-831-6131
brobinson@pile.com
Manufacturer of deep Provider of deep foundation
foundation testing equipment testing and analysis services
Who are you ? Do you:
• Structural Engineers • Perform testing yourself?
• Geotechnical Engineers • Hire out testing?
• Testing Consultants
• Deep Foundation Contractors
• General Contractors
• Construction Managers
• Government Agencies
• Owners / Developers
Session I
– Overview of the benefits of testing
– Method selection
– How to implement testing into a project
Session I
– Overview of the benefits of testing
– Method selection
– How to implement testing into a project
Overview of the Benefits of Testing
• Design Verification / Optimization
Overview of the Benefits of Testing
• Economics – Driven Piles
ASD: Ru = DL x FS LRFD: Rn = FL /
( based on redundant foundations, for single columns supported by one shaft use 0.8 )
Overview of the Benefits of Testing
• Risk Mitigation
Overview of the Benefits of Testing
• Risk Mitigation
Wave Dynamic Dynamic Saximeter Visual Dynamic Low Strain Static Dynamic Dynamic
Equation Pile Pile or Observation Pile Integrity Load Pile Load
Analysis Monitoring Monitoring Energy of Stroke Monitoring Testing Test Monitoring Test
(WEAP) (PDA) (PDA) Saximeter (PDA) (PIT) (SLT) (PDA) (DLT)
QA/QC Method Selection for Drilled Shafts
During Excavation
* Brown D.A., Turner, J.P., Casteli, R.J., and Loehr, E.J. (2018). FHWA GEC-10, Drilled Shafts: Construction
Procedures and Design Methods, National Highway Institute, U.S. Department of Transportation, Federal
Highway Administration, Washington D.C.
Implementing Testing on a Project
Dynamic Monitoring – PDA
Why ?
o Installation stress control / hammer performance (initial driving),
o Capacity (restrikes),
o Quantify soil setup / relaxation (initial drive and restrike)
The number of dynamic test piles is based upon the structure type and size as well as the
subsurface variability. A typical recommendation may be one test pile plus one additional test
pile for every 5000 square feet of building footprint.
For bridges, two piles per site condition but not less than 2% of the production piles is a common
requirement (AASHTO).
Implementing Testing on a Project
Dynamic Monitoring – PDA
Why ?
o Identify major integrity problems within the testable depth (typically 30 L/D +/-).
Quick test allows testing many piles per day (10 to 50) subject to pile access and pile head
preparation.
When ?
ASTM D5882 states that the tests shall be performed no sooner than 7 days after casting or after
strength achieves at 75% of its design strength.
Per AASHTO Bridge Construction Specification (2017), CSL testing is used as a regular inspection
method for wet placed shafts using tremie concrete methods.
When ?
ASTM D6760 states that the tests shall be performed no sooner than 3 to 7 days after casting
depending on concrete strength and shaft diameter (larger diameter shafts may take closer
to 7 days)
The shafts or piles to be tested must be identified on the plans or designated by the Engineer in
advance so that the required lengths of Thermal Wire Cables can be ordered and available at the
time of foundation installation.
When ?
Data analysis typically performed between ½ peak and peak temperature. For most shafts, this
data analysis window occurs between 12 and 48 hours after casting. Larger diameter shafts or
shafts with substantial mix retarders may take longer.
Performed By ? TIP data sent to Cloud in real time or stored on shaft, Engineer in office.
What Level of Integrity Testing is Needed?
Item Description Numerical Risk Factor Weighting
Weighting
Factor
Factor
1 2 3
1 Magnitude of Foundation ≤≤$300,000
$300,000 $300,000 to $1,000,000 ≥ $1,000,000 1.0 1.0
Contract (1997 USD) (2021 $) $586,000 to $1,955,000
2 Experience and Equipment of Excellent Adequate
Adequate Marginal 1.5 3.0
Drilled Shaft Contractor
3 Thoroughness of Subsurface High
High Medium Low 1.5 1.5
Exploration & Geotechnical
Experience of the Inspector
4 Anticipated Construction Low
Low Medium High 1.5 1.5
Difficulties
5 Uniformity (predictability) of High
High Medium Low 1.5 1.5
Subsurface Conditions
6 Load Resistance Mechanism Shaft
Shaft Combined Base 1.0 1.0
Assumed in Design
7 Anticipated Construction Dry 1.0
Method
Perm. Casing 0.5
Temp. Casing 1.5
Wetw/
Wet w/ Temp
Temp Casing
Casing 2.5 7.5
Wet w/o Temp Casing 3.0
8 Type of Loading Axial Axial Battered Lateral
Lateral 1.0 3.0
9 Load Duration Mainly Static, Short
Short Mainly Static, Long 1.0 1.0
Term Live Loads Term Dead Loads
Impact or Seismic 2.0
Reference: FHWA-IF-99-025 O’Neill and Reese (1999)
FHWA-RD-92-004 Baker et al., (1993) NRF x WF Subtotal = 21.0
What Level of Integrity Testing is Needed ?
Item Description Numerical Risk Factor Subtotal
1 2 3
1-9 Subtotal
21
10 Stress Ratio ≤ 0.4 > 0.4 but < 0.8 ≥ 0.8
> 0.4 but < 0.8
sdesign / smax allowable design
( Subtotal 1-9 ) x ( NRF 10 )
42
11 Risk Level for Loss of Low Medium High
Medium
Human Life or Economic
Catastrophe
9dB
Questions?
0
0 15% 30%
First Arrival Delay