Professional Documents
Culture Documents
INDUSTRIAL ATTACHMENT I
REPORT
T : +250 788 90 30 30
: +250 788 90 30 32
E: inesruhengeri@yahoo.fr
W : www.ines.ac.rw
December, 2023
CERTIFICATE
This is to certify that the Industrial Attachment report carried out Eight Weeks from
30th September, to 22nd December 2023 in CHINA STAR Construction Co. Ltd. This
is record of the original work done by KAYUMBA Aimee Liliane in partial
fulfillment for the requirement for the award of Bachelor in Civil Engineering in
INES-RUHENGERI.
Date: …………………….
Signature: ……………..
i
DECLARATION
I KAYUMBA Aimee Liliane, student in faculty of Applied fundamental sciences, Civil
engineering department, am hereby declaring that the content presented in this report is my
own work carried out during industrial attachment program from 30 October up to 23
December 2023, in a construction company called CHINA STAR Co Ltd. in one of their sites
located at KIREHE District and to be submitted to meet the requirements for Bachelor
degree in Civil Engineering at INES-RUHENGERI.
Signature: …………………
Date: 27/December/2023
ii
DEDICATION
I am pleased to dedicate this report to:
Almighty God
My beloved Family
Lovers and haters
INES-RUHENGERI civil engineering department staff especially my supervisor
Eng. Anne Valerie ISHIMWE and all classmates.
Whoever contributed to the successful of my IAT especially my workmates.
iii
ACKNOWLEDGEMENT
I wish to acknowledge and express my profound gratitude to almighty God for all his love,
guidance, help and protection and to present my sincere thanks to my parents and my
siblings for their unconditional love, advice and support along this whole period of
Industrial Attachment I.
I would also like to express my gratitude to all site engineers who shared me their
engineering knowledge and experience and all workmates for the skills they have shared
with me and for that, each time of the Industrial attachment was an opportunity to learn new
things.
To everyone who has contributed either directly or indirectly in the successfulness of my
IAT, you are highly appreciated, without your support, this industrial attachment would not
have been successful.
iv
Abbreviations
INES-RUHENGERI: Institut d’Enseignement Supérieur de Ruhengeri
RCC: Reinforced concrete
IAT: Industrial Attachment
CABC: China-Africa Business Council
List of figures
Figure 1: Administration chart
Figure 2: Batch concrete mixer
Figure 3: Construction hoist and its remote
Figure 4: Concrete vibrator
Figure 5: Handheld circular saw
Figure 6: Table saw with circular saw
Figure 7: Hammer drill machine
Figure 8: Bar bending machine
Figure 9: Bar cutting machine
Figure 10: Grinders
Figure 11: Electric bolt tightening machine
Figure 12: Construction laser level
Figure 13: Engineering drawing
Figure 14: Dumpy level surveying
Figure 15: Type of Scaffolding used on site
Figure 16: Column shuttering
Figure 17: Slab and beam shuttering before placing reinforcements
Figure 18: Slab shuttering after placing beam reinforcement
Figure 19: Stair and ramp formwork before placing reinforcing mesh.
Figure 20: Stair and ramp after placing reinforcing mesh.
Figure 21: Manual bar bending place.
Figure 22: Formulas for curtailment of reinforcement
Figure 23: Hanger bars
Figure 24: Cement bags
Figure 25: Column concreting
Figure 26: Screeding for stair and ramp
Figure 27: Curing method employed on site
List of tables
Table 1: Formwork Stripping Time
Table 2: Standard Grades of Concrete
v
ABSTRACT
Industrial attachment is one of the main courses in civil engineering programme. The period
of the training was 8 weeks which started at 30th October to the 22th December 2023.
The purpose of this course is to apply the class theoretical knowledge into real practical
work. The student can be trained as site engineer; it gives opportunity to supervise the
construction work closely.
In order to comply the industrial attachment objectives, I gained and learnt more from my
summer internship. I participated in all technical works done at construction site include site
preparation; interpretation of technical drawings; rebar reinforcement works such as cutting,
bending, reinforcement binding of structural members, carpentry works such as formwork
preparation, scaffolding; quality assurance and quality control of concreting operations such
as volumetric batching, concrete ingredients mixing, transportations, placing into well
prepared formworks, compactions with the aim of consolidating fresh concrete to remove
void and avoiding bleeding and segregation, curing with aim of achieving cement hydration
which leads to the strength of concrete, removal formwork and finishes; stone and brick
masonry works; checking quality of construction materials; human resources management;
site management; practical skills of using tools and equipment at construction site.
During the industrial attachment, I also increased knowledge about team work skills, time
management skills, working under pressure, meeting with deadline, multitask management.
Industrial attachment played great role in my studies where I practiced the class theoretical
knowledge. So, I am hopeful and confident that the future will be bright in my career as a
civil engineer.
vi
Table of content
CERTIFICATE ...................................................................................................................... i
DECLARATION ................................................................................................................... ii
DEDICATION ...................................................................................................................... iii
ACKNOWLEDGEMENT ................................................................................................... iv
Abbreviations ..........................................................................................................................v
List of figures ..........................................................................................................................v
ABSTRACT .......................................................................................................................... vi
CHAP I: GENERAL INTRODUCTION .............................................................................1
1.1. OBJECTIVES OF INDUSTRIAL ATTACHMENT ............................................1
1.2. Site selection ..............................................................................................................1
1.3. SITE LOCATION AND BACKGROUND ............................................................2
1.4. BRIEFLY DESCRIPTION OF CHINA STAR Construction Co. Ltd. ..............2
1.5. MISSION & VISION ...............................................................................................2
1.5.1. Mission statement...............................................................................................2
1.5.2. Vision statement .................................................................................................3
1.6. ADMINISTRATION CHART OF CHINA STAR Construction Co. Ltd. .........3
CHAP II: LITERATURE REVIEW ....................................................................................3
2.1. TRAINING BENEFITS AND MOTIVATION .....................................................3
2.2. CHALLENGES FACED DURING INDUSTRIAL ATTACHMENT ................4
2.3. BRIEF DESCRIPTION OF THE SITE TOOLS AND EQUIPMENTS .............4
CHAP III: DESCRIPTION OF THE WORKS DONE DURING INDUSTRIAL
ATTACHMENT .....................................................................................................................8
3.1. INTERPRETATION OF ENGINEERING DRAWINGS ....................................8
3.2. SURVEYING USING DUMPY LEVEL ................................................................9
3.3. SCAFFOLDING .......................................................................................................9
3.3.1. Advantages of steel scaffolding. ......................................................................10
3.3.2. Requirements for scaffolding. .........................................................................10
3.3.3. Parts of steel scaffolding (Scaffolding components) .....................................10
3.4. FORMWORK .........................................................................................................11
3.4.1. Requirements of Good Formwork .................................................................11
3.4.2. TYPES OF FORMWORK ..............................................................................12
3.4.3. Construction of formwork ..............................................................................13
3.4.4. Factors affecting striking time of concrete formwork..................................17
3.4.5. Order and method of formwork removal ......................................................17
vii
3.5. STEEL BAR WORKS ............................................................................................18
3.5.1. Cutting and bending of stirrups. ....................................................................18
3.5.2. Curtailment of bar in continuous beam .........................................................19
3.5.3. Overlapping ......................................................................................................19
3.5.4. Hanger bars ......................................................................................................20
3.6. CONCRETE ............................................................................................................20
3.6.1. Ingredients of Concrete ...................................................................................21
3.6.2. Steps of concrete manufacturing processes ...................................................22
3.6.3. Grade of concrete .............................................................................................25
3.6.4. Septic tank ........................................................................................................26
CHAP IV: RECOMMENDATIONS AND CONCLUSION ............................................26
4.1. Conclusion ...............................................................................................................26
4.2. Recommendations ...................................................................................................27
4.2.1. Recommendations towards CHINA STAR Construction Co. Ltd .............27
4.2.2. Recommendations towards INES-RUHENGERI .........................................27
Reference ...............................................................................................................................27
viii
CHAP I: GENERAL INTRODUCTION
Industrial attachment, also known as work placement, is a structured program that allows
students to gain practical work experience in an industry related to the field of study. It
provides an opportunity for students to apply theoretical knowledge to real-world situations,
develop essential skills, and establish professional connections. During industrial
attachment, individuals work under the guidance of experienced professionals, gaining
insights into the industry’s operations and enhancing the employability for future career
endeavours.
1.1. OBJECTIVES OF INDUSTRIAL ATTACHMENT
Linking theoretical knowledge with practical skills is the most important experience to be
acquired by every student before graduating as it appears on the schedule of the academic
activities of INES-RUHENGER that is why industrial attachment is very crucial for the
following objectives:
My site selection was firstly based on my desire and curiosity about building construction.
Building construction combines many class modules which are fundamental theoretical
knowledge required to be applied into practical experience of the civil engineering as a
career. From this perspective I chose to apply to the local civil engineering company that
shares nearly all its practice with the majority of other firms in the country. This influenced
my decision of working on a construction site under the supervision of a site engineer of
CHINASTAR Co. Ltd. I also wished to use that opportunity to gain more knowledge in
construction works. Hence, I chose to work with CHINASTAR Co. Ltd which is a
construction company and it was executing the project of Kirehe district hospital
upgradation and this has always been my wish to be involved on site works where I have to
take some responsibilities. I had already studied some subjects related to building
constructions so, I wanted to match the theory learnt in class and how it is applied on the
site.
1
1.3. SITE LOCATION AND BACKGROUND
Kirehe District Hospital was established in 2007, Kirehe Hospital is located in Eastern
Province, Kirehe District, Kirehe Sector and Gahama Cell.
Kirehe district is one of seven district within Eastern province having 12 sectors, 60 cells
and 612 villages and it is located at south-East of Rwanda for 133 Kilometres (Km) from
the capital city of Kigali.
Kirehe district also has Akagera river which makes border between the district and the
country of Tanzania (Rusumo point point) in East, makes border with the country of
Burundi in South, it also makes border with Ngoma district in West and Kayonza district in
North. Kirehe district has area of 1,118.5 Kilometre square (Km2) and its population is
estimated at 460,860 inhabitants.
About the project I was working on during this period of two months of industrial
attachment which was about upgrading Kirehe district hospital.
Basically this hospital serves 17 public operational health Centres and 2 Health Centres of
Mahama Camp. Kirehe Hospital has 4 units: Director General Office Unit, Director of
Administration and Finance Unit, Medical and Allied Health Sciences Services Unit and
Nursing and Midwifery Unit and the project was about upgrading hospital facilities by
constructing a new G+2 building.
1.4. BRIEFLY DESCRIPTION OF CHINA STAR Construction Co. Ltd.
China Star Construction Group is located at Kigali – RWANDA, B1 Plot, Free Trade Zone,
Sector of Masoro.
China Star Construction Group is the Vice-Chairman Unit of China-Africa Business
Council (CABC). It has a subsidiary founded in Rwanda in 2010. And in 2013, another sub-
company in Uganda was also established. The group has contracted to projects of 2 phases
of Rwanda development zone, Kigali International Airport, Rwanda RPF conference centre,
etc.
China Star Group holds a good annual productivity of steel structure of 40 thousand tons
and has become the largest steel structure contractor in Rwanda. In fact, its subsidiaries are
the first-by-now steel structure processing plant in East Africa. And the group got on The
Lion of Africa.
1.5. MISSION & VISION
1.5.1. Mission statement
Its mission is to actively guide Chinese enterprises in their commitment of “going into
Africa” and help African enterprises with their operations in China; work with domestic and
international public and private sectors to promote China-Africa economic and trade
exchanges, push forward China-Africa and South-South Cooperation, and to promote
cultural and people-to-people exchanges and it is committed to Africa's sustainable
development.
2
1.5.2. Vision statement
Its vision is to become a specialized and internationalized platform that facilitates China-
Africa economic and trade cooperation, and thus serves as a model for China-Africa and
South-South Cooperation.
1.6. ADMINISTRATION CHART OF CHINA STAR Construction Co. Ltd.
It is commonly planned for qualified graduates to be competitive and motivated when they
are looking for job opportunities, training helps them to open their mind and relate
theoretical knowledge in practical skills, in fact I chose to work with construction of
building due to the following motivation:
3
2.2. CHALLENGES FACED DURING INDUSTRIAL ATTACHMENT
In our everyday life we face difficulties especially when you are experiencing new thing, in
fact there are some challenges I faced during this industrial attachment as follow:
The first challenge was about the terminologies used on site, in our studies
English is everything but on site it is totally different because French and
Kinyarwanda is mostly used, it takes time to be familiar with those
terminologies.
The other was IAT season. It was in rainy season, so it was sometimes hard to
reach to the site and sometimes work doesn’t progress as expected.
2.3. BRIEF DESCRIPTION OF THE SITE TOOLS AND EQUIPMENTS
1. Batch concrete mixer: enable you to mix cement, sand and aggregates with water in
concrete production. These mixers are commonly used in construction projects,
allowing for efficient and controlled mixing of materials to achieve the desired
concrete consistency.
4
3. A concrete vibrator: is a concrete tool that produces stronger concrete by vigorously
shaking the concrete right after you pour it to eliminate the air bubbles or air pockets
5
Fig 7: Hammer drill machine
7. Bar bending machine: This facilitate the construction of reinforced concrete
structures by bending rebars into various shapes and angles
6
Fig 10: Grinders
10. Electric bolt Tightening Machine: This machine is used for rapid bolt tightening on
steel scaffold.
7
12. Tie Wire Twister or binding hook (Tenaille): is a fabricated tool used to tie rebars of
various diameters together at intersection using galvanized tie wires.
13. Manual rebar bender: usually made of rebar itself and it is used for unfolding steel
bars
14. Chalk line: is a tool for marking long, straight lines on relatively flat surfaces, much
farther than is practical by hand or with a straightedge.
15. Plumb bob: is a pointed weight attached to the end of the string and is used to find a
vertical reference line called plumb.
16. Hose level: is a simple device that can provide an accurate elevation comparison
between multiple points that rival each other to be a county high point, or to be the
highest summit of a major peak.
17. Tape measure: is a flexible instrument used for measuring lengths and distances.
18. Safety belt: Should wear while doing work at heights.
8
3.2. SURVEYING USING DUMPY LEVEL
Surveying is defined as the art, science and technology of making measurements of objects
on, above or beneath the ground to show their relative positions on paper. The position
required is either horizontal, vertical or both.
The main objective of surveying is to collect field data so a map or plan can be prepared
based on the calculations of the field parameters before an engineering operation is actually
executed to begin a construction project.
Plumbing professionals use surveys to confirm sanitary waste line and septic tank locations,
confirm code compliance of water heaters, check for pressure regulators, and more.
3.3. SCAFFOLDING
Scaffolding is a temporary structure used in construction to support workers who needs to
work at height and their materials during the building, renovation or maintenance of the
structure. Scaffolding is typically made from metal poles and wood planks.
There are many types of scaffoldings being used in building activities but the most used
type is Steel scaffolding for its advantages over other kinds of scaffolding and it is the one
being used on the I was working on.
Steel scaffolding is made primarily with construction steel pipes and tubes. These
components are joined together using steel couplers and other fittings. It is the most widely-
used temporary structure in construction, aside from its durability, it also offers workers
convenience, safety, and fire resistance and It is easier to dismantle than other types.
9
3.3.1. Advantages of steel scaffolding.
1. Standards: They are perpendicular tubes that transfer the load to the baseplates
which stabilize the scaffolding and create working platforms.
2. Ledgers: These are horizontal tubes that connect the standards and help in
distributing the load evenly across the scaffolding structure.
3. Transoms: are horizontal tubes spanning ledgers, normally at right angles (90°) to the
face of the building and they may also be used to support a working platform.
4. Bracings: This bracing helps to keep the structure rigid and stable, preventing it from
collapsing or tipping over.
5. Base plates: Scaffolding base plates are small square metal plates that the standards
(uprights) rest on to prevent them from sinking into the ground.
6. Sole boards: These are flat pieces of timber placed under the base plates of
scaffolding to distribute the load over a wide surface area.
7. Scaffold Boards (Planks): Are wooden or metal planks that create the working
platform for workers and materials.
10
8. Couplers and clamps: These are fittings which connect scaffolding tubes together
securely.
9. Guardrails: Horizontal and vertical barriers installed along the open sides of
scaffolding platforms to prevent falls.
10. Toe boards: are one of the most important safety features of scaffolding which
prevent tools and materials from falling off the scaffold and injuring people below.
The construction of formwork takes time and involves expenditure up to 20 to 25% of the
cost of the structure or even more. The design of these temporary structures are made to
economic expenditure. The operation of removing the formwork is known as stripping.
Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable
are called stationary forms.
Timber is the most common material used for formwork. The disadvantage with timber
formwork is that it will warp, swell, and shrink. The application of water-impermeable cost
to the surface of wood mitigates these defects.
3.4.1. Requirements of Good Formwork
It should be strong enough to withstand all types of dead and live loads.
It should be rigidly constructed and efficiently propped and braced both horizontally
and vertically, to retain its shape.
The joints in the formwork should be tight against leakage of cement grout.
11
Construction of formwork should permit removal of various parts in desired sequences
without damage to the concrete.
The material of the formwork should be cheap, readily available, and should be suitable
for reuse.
The formwork should be set accurately to the desired line, and levels should have a
plane surface.
It should be as light as possible.
The material of the formwork should not warp or get distorted when exposed to the
elements.
It should rest on a firm base.
3.4.2. TYPES OF FORMWORK
Concrete formworks (shuttering) are required for fresh concrete constructions such as walls,
slabs, beams, columns, footings etc… Formworks requirements for different structural
members are different and they are named based on type of structural member. Formwork
(shuttering) is a temporary mould to provide support to fresh concrete when placed in
structural member until the concrete has set. This helps the structural member to gain
sufficient strength to carry its self-load and load from other members. There are many types
of structural formwork or shuttering based on its material, their use and the type of
structural members. They can be named based on that. However, core functioning of the
formwork remains the same.
According to the site I was working on, the type of formwork used there based on material
was Plywood formwork which was moulded into different shapes based on the structural
member.
3.4.2.1. Based on materials
1. Timber formwork: Timber used for shuttering for exposed concrete work should have
smooth and even surface on all faces which come in contact with concrete.
Timber for formwork should satisfy the following requirement:
It should be:
1. Well-seasoned
2. Light in weight
3. Easily workable with nails without splitting
4. Free from loose knots
2. Plywood formwork: Resin-bonded plywood sheets are attached to timber frames to make
up panels of the required sizes. The cost of plywood formwork is favourably compares
with that of timber shuttering, and it may even prove cheaper in some instances given the
following considerations:
1. It is possible to have a smooth finish in which case on cost in surface finishing
is there.
2. By the use of large-size panels, it is possible to affect saving in the labour cost
of fixing and dismantling.
3. The number of reuses are more as compared with timber shuttering. For
estimation purposes, the number of reuses can be taken as 20 to 25.
12
3. Steel formwork: This consists of panels fabricated out of thin steel plates stiffened along
the edges by small steel angles. The panel units can be held together through the use of
suitable clamps or bolts and nuts.
3.4.2.2. Types of formwork based on different structural members (Beams,
columns, slabs and footings)
Formworks are used in construction of reinforced concrete foundations, columns, slabs,
walls etc., and these are named as follows:
Footing Forms – Formworks for foundation
Beam Forms – Formwork for beam
Column Forms – Formwork for RCC Column construction
Wall Forms – Formwork for RCC wall construction
Floor Forms – Formwork for construction of RCC Slabs
Ramp and stair Forms – Formwork for construction of RCC ramp and stair.
Formwork construction as a part of my IAT, I had chance to work on some of these kinds or
types of formwork based on the structural member which I will be explaining below except
Footing and wall formwork.
3.4.3. Construction of formwork
Normally the construction of formwork normally involves the followings operations:
1. Propping and Centering.
2. Shuttering.
3. Provision of camber.
4. Cleaning and surface treatment.
1. Propping and centering:
The props used for centering may be of steel, timber posts or bullies. Pillars made up of
brick masonry in mud mortar are also sometimes used as props.
It involves the installation of temporary support structures, such as props or braces, to hold
up a building or structure while work is being done on it.
2. Shuttering:
The shuttering can be made up of timber planks, or it may be in the form of panel units
made either by fixing plywood to timber frames or by welding steel plates to angle framing.
In any case, the shuttering should be constructed in such a manner that the joints should be
tight against leakage of cement grout.
Sometimes the architect specifies the provision of moulding in slabs or columns or
provision of chamfers at corners of beams and columns.
3. Provision of camber:
Certain amount of deflection in structure is unavoidable. It is, therefore desirable to give an
upward camber in the horizontal members of the concrete structure (especially in members
having long spans) to counteract the effect of deflection.
The provision of desired camber should be made in the formwork itself during erection.
4. Surface treatments:
Before laying concrete the formwork should be cleaned of all rubbish particularly the
sawdust shavings and chippings etc.
13
All surfaces of timber shuttering that are to come in contact with concrete should be well
wetted with water.
This is necessary to prevent the chances or dry shuttering absorbing water from the concrete
which may cause warping, swelling and distortion of timber besides resulting in defect of
honeycombing in concrete.
3.4.3.1. Column shuttering
Column formwork comprises of the following:
3. Side and end planks
4. Yokes
5. Bolts and nuts
Construction sequence for a column:
Before placing column formwork, verify that steel for the column is checked and
cleared for casting.
Place formwork for the column from prearranged grids.
Plumb formwork both ways and safely support with modifiable steel props.
Make sure that the steel props are securely attached to the column formwork and the
floor. Modification for pushing & pulling is going on.
Arrange the placements of column clamps from a storey rod.
Move the column damp positions from the storey rod onto column formwork.
Apply nails to provide support to the arms of column clamps at the time of wedging.
Place and wedge the bottom, middle and top clamps sets.
Examine the formwork at the top for square.
Place and wedge the rest of the column clamps.
Plumb the column with a plump bob that is hanging from a gauge block.
14
Installation sequence for beam formwork:
Preparing the Construction Site
Marking and Aligning the Beam Positions: Properly marking and aligning the
positions of the beams is crucial for accurate installation. Use string lines, laser
levels, or other alignment tools to ensure precise positioning of the beams. This step
helps in maintaining the desired dimensions and alignment of the structure.
Assembling the Beam Formwork Panels: These panels are typically made of timber,
plywood, steel, or aluminium and are designed to provide support and shape to the
concrete during pouring and curing.
Placing and Securing the Formwork Panels: Once the formwork panels are
assembled, carefully place them in position according to the marked beam positions.
Ensure that the panels are securely attached to each other and to the supporting
structure. Use appropriate fasteners or clamps to hold the formwork panels in place.
Installing the Shuttering and Reinforcements: After securing the formwork panels,
install the shuttering, which is a temporary support structure used to hold the
formwork panels in place. After, add reinforcements to enhance the strength and
load-bearing capacity of the beams.
Pouring and Curing the Concrete: With the formwork panels and reinforcements in
place, it is time to pour the concrete into the formwork.
3.4.3.3. Slab shuttering
Slab Formwork essentially consists of a horizontal load-bearing structure which supports
the form lining and transfers the forces into the shoring.
The procedures for installing slab formworks is the same as for beam shuttering. The most
essential thing is while erecting slab and beam formworks is marking, once it is done
properly the remaining is normal.
15
Fig 18: Slab shuttering after placing beam reinforcement.
3.4.3.4. Stair & ramp shuttering.
For stair and ramp shuttering, also the first thing is to mark the position of landings
and headroom and their supporting beams and columns.
Once all marked, the next step is to build the landings and head room where marked.
After, by fixing two building lines both from landing to the starting point of the stair
or ramp and other to the stair or ramp end, respectively you install bottom plywood
board or panels which will support your structure element.
Next, you fix the side boards on both sides of ramp or stair.
For stair the next step is to mark riser and goings on the side board.
The concrete steps are to be reinforced with steel bars so as it carries the loads
coming upon the stairs or ramp and transfer them to the ground.
Construct the riser forms: These are the vertical elements of the formwork. The riser
forms should be spaced evenly and should be the same height as the risers of the
stairs.
Fig 19: Stair and ramp formwork before placing reinforcing mesh.
16
Fig 20: Stair and ramp after placing reinforcing mesh.
3.4.4. Factors affecting striking time of concrete formwork
The striking time of concrete formwork depends on the strength of the structural members.
The strength development of concrete member depends on:
1. Grade of concrete
2. Grade of cement
3. Type of Cement
4. Temperature
5. Size of the concrete member
6. Accelerated curing
17
Type of Formwork Formwork Removal Time
Sides of Walls, Columns and Vertical 24 hours to 48 hours (as per engineer’s
faces of beam decision)
i) Span up to 6m 14 days
18
Here, one hook of the stirrups is neglected because steel has the property of elasticity
and it simply means that when you bend a steel bar, it stretches. So as to avoid that
risks, we neglect one hook length.
The straight length of the stirrups depends upon the cross-section of the member.
Important values for calculating bend length are mentioned below,
For 45-degree bend = Add 1D
For 90-degree bend = Add 2D
For 135-degree bend = Add 3D (Theoretically but it is not applicable in practices)
19
The main functions of overlapping of reinforcement are; To maintain the continuity of steel.
To transfer the load safely from one bar to the next bar.
Lapping of reinforcement is usually done where minimum bending stress is required. In
general, the minimum lap length is 50d which means 50 times the bar diameter is provided
if both bars are of same diameter.
3.5.4. Hanger bars
Hanger bars are provided in beams to support and distribute the load of the structure. They
help to prevent the beam from sagging or bending due to the weight it carries. By providing
additional support underneath the beam, hanger bars help to maintain the structural integrity
of the overall construction.
Hanger bars shall be provided in concrete beams which supports secondary beams.
Reinforcement shall be provided in the primary beam, and they shall be placed around the
joint of the two beams. Latter figures shows the method of detailing of reinforcements.
Design Technique
Generally, we provide primary beams to support the secondary beams. Reaction of the
secondary beams is carried by the primary beam. We normally design the primary beams for
the reaction of the secondary beams, and most of the time many engineers miss the design at
the joint. Joint should be design to carry the reaction of the secondary beam. We provide
hanger reinforcement at the joint, in the primary in addition to the normal shear
reinforcements.
20
3.6.1. Ingredients of Concrete
1. Cement.
Cement is the main binder material used to bind other building concrete materials together.
It is used for making mortar and concrete during the construction process.
21
3.6.2. Steps of concrete manufacturing processes
Quality control ensures concrete is produced with consistent strength from batch to batch.
To achieve this, some principles must be followed during the different concrete production
stages.
Concrete-making steps include:
1. Material batching
2. Mixing
3. Transportation
4. Placing
5. Compacting
6. Treatment
1. Material batching:
For good quality concrete a proper and accurate quantity of all the ingredients should be
used. Measure the aggregates, cement, and water with a 3% accuracy of the batch quantity
and the admixtures with a 5% accuracy of the batch quantity. The two most common
methods of batching materials are volume batching and weight batching.
2. Mixing:
Concrete can be mixed either with hand mixing or machine mixing depending on the type or
quantity required for a given job. Machine mixing is the one we used in my IAT site.
3. Transporting:
Move the freshly mixed concrete to the construction site using various techniques, including
wheelbarrow and hand hauling, conveyor belt operations, and more complex projects,
including cranes and pumps. All of these techniques required some level of manual labour
and sophisticated protective gear. Also the technique employed on my IAT site is
Construction elevator and wheelbarrow technique.
4. Pouring and placing:
Pour the concrete into the forms or moulds at the construction site. This can involve various
techniques, such as pumping or bucketing. Concrete must be placed with the utmost care to
ensure homogeneity during mixing and prevent segregation during transportation.
22
Fig 25: Column concreting.
5. Compacting:
Fresh concrete is consolidated by compaction around embedded components, reinforcement
steel, and moulds or frames to remove air voids and ensure that it fills the forms completely.
6. Finishing:
Smooth the surface of the concrete to achieve the desired appearance and texture. This may
involve screeding, floating, and trowelling.
23
The time to start the curing of concrete depends on the evaporation rate of moisture from the
concrete. The evaporation rate is influenced by wind, radiant energy from sunshine,
concrete temperature, climatic conditions, relative humidity.
The curing of concrete for longer duration increases the strength and durability of concrete
structural members. However, after 28 days of the casting of a concrete, 99% of the
hydration process of the concrete is completed. Further to which continuation of curing is of
no use.
Why the curing of concrete is required?
To prevent the concrete from drying out prematurely (plastic shrinkage) due to solar
radiation and wind.
The hydration process requires water to carry on and releases heat in fact this helps to
maintain the concrete temperature.
This helps the development of impermeable, crack-free, and durable concrete.
Curing helps the concrete to harden and bond with internal materials and
reinforcement.
Methods of curing.
There are various methods of curing concrete, which are used on the site depending upon
the size and nature of the work.
1. Immersion curing: This is the best water curing method. Here, finished concrete is
immersed in the curing tank or curing pond. This method is practically not possible
unless the concrete is a laboratory test specimen for small precast units.
2. Ponding method: Here, small rectangular or square artificial ponds are built using
bunds of clay or lean mortar or sand across and along the concrete surface. Water is
filled in two or three times per day depending upon the atmospheric conditions. This
method is very efficient but the amount of water required is huge.
3. Spraying or fogging method: Here by using nozzles or sprayers, water is sprayed on
the concrete members, which are to be cured and it is an efficient method for curing
by supplying additional moisture during hot weather.
4. Wet covering method: Here jute bags, cotton mats, Hussain cloth, etc. are used to
maintain moisture on the concrete surface by completely covering the surface
immediately after the concrete has hardened sufficiently.
5. Concrete curing compound
6. Steam curing.
During my IAT period, the curing methods used on site were wet covering and spraying or
fogging method as shown in the following picture.
24
Fig 27: Curing method employed on site.
3.6.3. Grade of concrete
Grade of concrete is defined as the minimum strength the concrete must possess after 28
days of construction with proper quality control. Grade of concrete is denoted by prefixing
M to the desired strength in MPa. For example, for a grade of concrete with 20 MPa
strength, it will be denoted by M20, where M stands for Mix. These grade of concrete is
converted into various mix proportions. For example, for M20 concrete, mix proportion will
be 1:1.5:3 for cement: sand: coarse aggregates.
The concrete grade is divided into three categories: Ordinary, standard, and high. The grade
of concrete depends on various factors, including durability, comprehensive strength, and
water-cement ratio, among others.
Regular grades of concrete are M15, M20, M25 etc. For plain cement concrete works,
generally M15 is used. For reinforced concrete construction minimum M20 grade of
concrete are used.
The grade of concrete being used on my site was M25.
Concrete Mix ratio Compressive strength
Grade MPa(N/mm2) psi
M25 1:1:2 25 3625
M30 Design mix 30 4350
M35 Design mix 35 5075
M40 Design mix 40 5800
M45 Design mix 45 6525
Table 2: Standard Grades of Concrete.
25
3.6.4. Septic tank
A septic tank is an underground chamber made of concrete, fiberglass, or plastic through
which domestic wastewater (sewage) flows for basic sewage treatment.
The septic tank is a buried, water-tight container usually made of concrete, fiberglass, or
polyethylene. Its job is to hold the wastewater long enough to allow solids to settle down to
the bottom forming sludge, while the oil and grease floats to the top as scum.
3.6.4.1. Functions of septic tank
Septic tanks receive all wastewater from the house
Septic tanks separate solids from the wastewater flow
Septic tanks cause a reduction and the decomposition of solids.
Septic tanks provide storage for the separated solids (Sludge and scum)
Septic tanks pass the clarified wastewater (effluent) out to the absorption area.
3.6.4.2. Working principle of septic tank
A typical septic system consists of a septic tank and a drain field (or soil absorption field).
The septic tank digests organic matter and separates floatable matter (e.g., oils and grease)
and solids from the wastewater. In conventional, or soil-based systems, the liquid (known as
effluent) is discharged from the septic tank into a series of perforated pipes buried in a leach
field, chambers, or other special units designed to slowly release the effluent into the soil.
This area is known as the drain field.
Alternative systems use pumps or gravity to help septic tank effluent trickle through sand,
organic matter (e.g., peat and sawdust), constructed wetlands, or other media to remove or
neutralize pollutants like disease-causing pathogens, nitrogen, phosphorus and other
contaminants. Some alternative systems are designed to evaporate wastewater or disinfect it
before it is discharged to the soil.
26
4.2. Recommendations
In order to make Industrial attachment more beneficial for the future trainees and meet its
objectives, according to the observations and findings during mine (IAT), I would like to
recommend to:
4.2.1. Recommendations towards CHINA STAR Construction Co. Ltd
The company should provide many qualified supervisors in order to give
more time and attention to internees.
Motivation should be given to trainees, if motivated, they can do more things
of great importance to the company.
4.2.2. Recommendations towards INES-RUHENGERI
Most student have struggled in getting companies which hosted them in
period of industrial attachment that is why INES should seek partnership
with different construction companies which will host the student.
They should seek information from various companies regarding new site
procedures and technology of performing work before elaborating academic
curriculum and to update their teachings to comply with company owners’
expectations.
To put more effort in practical teachings like in workshop courses in order to
balance both theoretical and practical skills.
Reference
27