Sequence Vacuum Construction
Sequence Vacuum Construction
Introduction
1 April 2024 1
Original Condition
+0.00
GWL
Original Ground
2
Platform Construction
+2.50
+0.00
Platform Construction
GWL
3
Platform Construction
+3.40
+2.50
+0.00 Settlement Compensation Backfill
Platform Construction
GWL
Backfill for Settlement Compensation, Assume the settlement is 90cm, Later the amount of
settlement compensation can be estimated using D-Settle after the improvement load and
operational load already being finalized
4
Platform Construction
+5.10
+3.40
Backfill until Finish Grade Level +2.50
+0.00 Settlement Compensation Backfill
Platform Construction
GWL
5
Platform Construction
+5.10
+3.40
Platform Construction
GWL
6
Vacuum System Installation
+5.10
+3.40
GWL
PVD is
installed
7
Vacuum Running
+3.40
Backfill until Finish Grade Level +2.50
Settlement Compensation Backfill
+0.00
Platform Construction
Negative Pressure
GWL (Min. 80kPa)
Atmospheric Atmospheric
Pressure Pressure
(1Atm) (1Atm)
8
Vacuum Running for 120 days
+2.50
Backfill until Finish Grade Level +1.40
Platform Construction
GWL Negative Pressure
(Min. 80kPa)
Atmospheric Atmospheric
Pressure Pressure
(1Atm) (1Atm)
9
Vacuum Off
Heaving Heaving
+4.30
+2.60
Backfill until Finish Grade Level
+1.50
Platform Construction
GWL
During vacuum Off, the level at vacuum area might increase a little
bit because of the unload of 80 kPa vacuum pressure. The amount of
heaving is quite varies from 5cm – 10cm at the vacuum area.
10
During Operational (Ex : Soccer Field)
The GWL is will remain at the
original level, before and after
vacuum.
+4.20
+2.50
Backfill until Finish Grade Level
+1.40
11