METHOD STATEMENT OF
AUTOCLAVE/ STERILIZER
STEAM 28CUFT PASS
THROUGH VACUUM TYPE
(ASTR3005) – 2ND PHASE
PREPARED BY:
1
Prepare by Hexamine
Objective
This method statement aims to provide information concerning the installation, testing and
commissioning for the Autoclave/Sterilizer Hospital UITM Puncak Alam 2 nd Phase Project.
Scope of Work
This method statement is to define the method of handling and installation requirement of
Autoclave/ Sterilizer and utility M&E services to be provided by others.
All the testing and commissioning documents including delivery Order (DO), relevant T&C
inspection checklist form, and warranty certificate.
User Training
1. User training to be conducted by class covers such as:
a. On-site training system, in order to ensure users understand how to operate the
equipment as well.
b. Technical training for maintenance and technical part in order for them to assess
the breakdown.
2
Prepare by Hexamine
ID Task Name Duration Start 2023
Q3 Q4 Q1 Q2 Q3
1 Project Title: New Autoclave for Future Position for CSSD 173 days Thu 24/11/22
(UiTM Hospital Puncak Alam) - Phase 2
2 Received Purchase Order (PO) 1 day Thu 24/11/22
3 Ordering of Equipment & Fabrication 148 days Fri 25/11/22
4 Installation Works 7 days Sun 16/4/23
5 Delivery and Uncrate the Autoclave 1 day Sat 22/4/23
6 Connection all the utility services with Equipment 1 day Sun 16/4/23
including Water Softener
7 Testing & Comissioning 29 days Mon 17/4/23
8 JKKP 28 days Mon 17/4/23
9 Hydrostatic Test (HT) 14 days Mon 17/4/23
10 Steam Test (ST) 14 days Mon 1/5/23
11 T&C with Hospital 1 day Mon 15/5/23
Page 1
Radius Radius Radius
Radius Radius Radius
BERSEKUTU
BER
TAMBAH
MU TU
KONSULT
T I T I J A S A
LANDSCAPE CONSULTANT
STERILISER
N/A 50
L4.CSD.540
VAMED
SUB CONTRACTOR
H
SHOP DRAWING
Number Date Description
1 DECEMBER 2022 L4.CSD.540 STEAM STERILIZER
1. ASTR3005 AUTOCLAVE
2. ASTR0006 TROLLEY AUTOCLAVE
L4.CSD.533
PACKING Attachment A