You are on page 1of 4

HOSPITAL UITM PUNCAK ALAM

THE SUPPLY, DELIVERY, INSTALLTION TESTING, COMMISSIONING AND


COMPREHENSIVE MAINTANACE FOR MEDICAL EQUIPMENT: STERILIZER

METHOD STATEMENT OF
AUTOCLAVE/ STERILIZER
STEAM 28CUFT PASS
THROUGH VACUUM TYPE
(ASTR3005) – 2ND PHASE

PREPARED BY:

HEXAMINE SDN BHD


NO 49, LORONG RAHIM KAJAI 13,
TAMAN TUN DR ISMAIL
60000 KUALA LUMPUR
WILAYAH PERSEKUTUAN
TEL: 03 7725 0250
FAX: 03 7725 0251

1
Prepare by Hexamine
Objective
This method statement aims to provide information concerning the installation, testing and
commissioning for the Autoclave/Sterilizer Hospital UITM Puncak Alam 2 nd Phase Project.

Scope of Work
This method statement is to define the method of handling and installation requirement of
Autoclave/ Sterilizer and utility M&E services to be provided by others.

The scope of work shall be:


1. Site visits/inspections shall be carried out before proceeding with any installation works
of the Autoclave/ Sterilizer.
2. Ensure that all necessary utility M&E services by the hospital are under functionality.
3. Relocation of the stainless steel paneling wall is by others, as the attached shop drawing
required to offset 600mm from the RC column (refer to attachment A shop drawing).
Hexamine will be provided for the setting out. (Remark: Must be completed before the
Autoclave/Sterilizer been arrived)
4. Prior to any installation will be applied and get a permit from the hospital maintenance
department or relevant party.
5. Delivery of the Autoclave/ Sterilizer will be notified in advance 2 days, to ensure that
the loading bay area is sufficient to be placed for the Autoclave/ Sterilizer.
6. Along the journey to transfer the Autoclave/ Sterilizer from the loading bat area to the
CSSD room have a protected cover by plywood on the floor to avoid damage.
7. Once Autoclave/ Sterilizer is delivered to the CSSD, to be position and level the
Machine as per the requirement needed. Then, to do the connection work for plumbing
and electrical works. (All the installation work shall be applied on Saturday and Sunday
only as requested by the hospital to avoid any obstruction to operation work.)

Testing and Commissioning


In Malaysia standard for Autoclave/Sterilizer build with a steam generator and the pressure
vessel is required to go through JKKP inspection to pass the Hydrostatic Test (HT) and Steam
Test (ST). Before to proceed the T&C works.

All the testing and commissioning documents including delivery Order (DO), relevant T&C
inspection checklist form, and warranty certificate.

User Training
1. User training to be conducted by class covers such as:
a. On-site training system, in order to ensure users understand how to operate the
equipment as well.
b. Technical training for maintenance and technical part in order for them to assess
the breakdown.

2
Prepare by Hexamine
ID Task Name Duration Start 2023
Q3 Q4 Q1 Q2 Q3
1 Project Title: New Autoclave for Future Position for CSSD 173 days Thu 24/11/22
(UiTM Hospital Puncak Alam) - Phase 2
2 Received Purchase Order (PO) 1 day Thu 24/11/22
3 Ordering of Equipment & Fabrication 148 days Fri 25/11/22
4 Installation Works 7 days Sun 16/4/23
5 Delivery and Uncrate the Autoclave 1 day Sat 22/4/23
6 Connection all the utility services with Equipment 1 day Sun 16/4/23
including Water Softener
7 Testing & Comissioning 29 days Mon 17/4/23
8 JKKP 28 days Mon 17/4/23
9 Hydrostatic Test (HT) 14 days Mon 17/4/23
10 Steam Test (ST) 14 days Mon 1/5/23
11 T&C with Hospital 1 day Mon 15/5/23

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline

Date: Wed 14/12/22 Summary Manual Task Progress


Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 1
Radius Radius Radius
Radius Radius Radius

Radius Radius Radius

BERSEKUTU

BER
TAMBAH
MU TU

KONSULT

T I T I J A S A
LANDSCAPE CONSULTANT

STEAM Oratis Consulting Sdn.Bhd.


( 1118265-A )

STERILISER
N/A 50
L4.CSD.540

VAMED
SUB CONTRACTOR

HEXAMINE SDN BHD

H
SHOP DRAWING
Number Date Description
1 DECEMBER 2022 L4.CSD.540 STEAM STERILIZER

1. ASTR3005 AUTOCLAVE
2. ASTR0006 TROLLEY AUTOCLAVE

L4.CSD.533
PACKING Attachment A