Professional Documents
Culture Documents
Page 67 of 110
Pearl GTL
Lift Planning & Risk Assessment Sheet
Page 67 of 110
7. Lift Categorization Questionnaire
Routine Lift
1. Do you know weight and COG of the load? YES
2. Is the weight of the load less than 10 tonnes? YES
3. Is crane capacity utilization within 75%? YES
4. Are you using a standard rigging arrangement? NO
5. Are the lift points above or in-line with COG and are verified as fit-for purpose? YES
6. Does crane operator see the load at all times? YES
If answer to ALL questions above is YES sign off and proceed. Otherwise move to the next section
Non-Routine Simple Lift
7. Is the weight of the load between 10 and 30 tonnes? NO
8. Is crane capacity utilization between 75% and 85%? NO
9. Is COG location not in the centre of the load? NO
10. Is it a sensitive or fragile load? NO
11. Does rigging arrangement require basic slinging? YES
12. Do lift points require verification? NO
13. Does the lift require suspended load transfer (cross hauling)? NO
14. Is the work area restricted in any way? NO
If answer to ANY of the question is YES request AP approval. Otherwise move to the next section
Non-Routine Complex Lift
15. Is the load weight over 30 tonnes? NO
16. Does the lift involve use of aerial bundle extractor? NO
17. Is it a multiple crane or top and tail lift? NO
18. Does the lift require special ground preparations? NO
19. Is the crane maximum capacity above 200 tonnes? NO
20. Does crane set up require more than one shift? NO
21. Does the lift duration extend over one shift? NO
22. Is it a lift in or out of confined space or through a hatch? NO
23. Is it a blind lift? YES
24. Does the load path go over live process lines or equipment? NO
If answer to ANY of the questions above is YES request AP and SHELL SME approval.
Special Consideration
1. Does the lift involve lifting of personnel? NO
If the answer to the above question is YES seek Shell VP Production approval
Lift deviation (If any)
Lift Categorization
Routine ☐ Non-Routine Simple ☐ Non-Routine Complex ☒
I confirm that the risks associated with this lift are as low as reasonably practicable
Date & Time:
Person In Charge Name: Signature
Date & Time:
Appointed person Name: Prasanthan N Signature 25.01.2024 08:30AM
HANDOVER (In case of change of PERSON IN CHARGE)
Person In Charge Name: Signature Date:
Person In Charge Name: Signature Date:
Prasanthan N
25.01.2024
1A-3185
PLANT
THIS DRAWING CRANE & LOAD INFORMATION
NORTH
NORTH
PLOT PLAN P.N
CRANE MODEL : TADANO GT 600EX
CRANE CAPACITY : SWL 60 TON
PREVAILING
WIND
APPLICABLE FOR AA / BA Boom Combination Main Boom
Main Boom Length 35.00 m
Telescopic Sec.- 1-2-3-4 100-066-066-066 -
Outrigger Dimension 6.80 x 5.48 m
Min. Crane Mats Size 1.0 x 1.0 m
MOBILE TELESCOPIC CRANE
KEY PLAN Crane Counter Weight 4.37 ton
GT-600EX
C:\Users\Gijo.Baby\QSGTL DATA\QSGTL LIFTING PLAN\GTL\CRANE SITING_FIN FAN MOTOR\DRAFT\QSGTL-CRANE SITING-000007_GTL-AB_BB_FIN FAN MOTOR_60 TON_R6.dwg
SWL:60 TON
Items to be unloaded
onto Pallet trolley Max. Work Radius. 12.0 m
and transferred to Boom Angle 68.5 °
10500 required locations.
Reeving No. (Min.) 1 -
1E-3143 Equipment Name / Tag No.
AS PER LOAD DATA
Removal & Installation
6250 6250 6250
required locations.
R80
CRANE DIMENSION
PLOT PLAN ELEVATION R3
700
APPLICABLE FOR AB / BB
6800
14775
MOBILE TELESCOPIC CRANE Crane Tadano
GT-600EX GT 600EX
5480
1000
SWL:60 TON (SWL:60 ton)
374
0
00
350
R7000 Digitally signed by
36275
Vimesh Madhavan
For L&H SME Date: 2023.10.04
11:35:45 +03'00'
Items to be unloaded
NEW EQUIPMENT ADDED
onto Pallet trolley 06 04-OCT-2023
ISSUED FOR APPROVAL
GIJO VM SJ
LIFT WEIGHT UPDATED
and transferred to 05 05-APR-2023
ISSUED FOR APPROVAL
GIJO VM SJ
REVALIDATED
required locations. 04 12-OCT-2022
ISSUE FOR APPROVAL
GIJO VM SJ
20500
MINER COMMENT
03 07-APR-2022 GIJO ZIN SJ
ISSUE FOR APPROVAL
NEW ITEM ADDED
02 07-APR-2022 GIJO ZIN SJ
ISSUE FOR APPROVAL
REVALIDATED
01 18-OCT-2021 SREEJITH ZIN RAZ
ISSUE FOR APPROVAL
00 21-APR-2021 ISSUE FOR APPROVAL NAFEES ZIN RAZ
Rev. DATE DESCRIPTION PRD. BY CHKD APPD
1E-6012 1E-6122
68
CALCULATION
2
4700
PREVAILING
WIND
APPLICABLE FOR AREA ITEMS
1E / 2E-3143 - A1 : K3
PERMISSIBLE WIND SPEED AC & BC 1E / 2E-3221 - A1 : A3
14775
C 9.0 m/s 1E / 2E-3202 - A1 : A3
(Refer wind speed note) 1E / 2E-3202 - A1 : A3
1E / 2E-3203 - A1 : A3
AA / BA 1E / 2E-3602 - A1 : A3
1824 KEY PLAN
MOTOR LIFTER, SPADE & SPOOL,
NRV, GRATE VALVE, CONTROL
C:\Users\Gijo.Baby\QSGTL DATA\QSGTL LIFTING PLAN\GTL\CRANE SITING_FIN FAN MOTOR\DRAFT\QSGTL-CRANE SITING-000007_GTL-AB_BB_FIN FAN MOTOR_60 TON_R6.dwg
VALVE, 184 / 284PCA-10007A
00
3000,09
350
6000 6250 6000 6000 6000
36275
Items to be unloaded 1E / 2E-6012 - A1 : A3
onto Pallet trolley 1E / 2E-6122 - A1 : A3
1000
and transferred to 1E / 2E-6143 - A1 : B3
required locations. 1E / 2E-3002 - A1 : A3
1E / 2E-3404 - A1 : D3
1E / 2E-3043 - A1 : M3
1E-6011 1E-1212 AB / BB 1E / 2E-3001 - A1 : D2
20500
1E / 2E-3421 - A1 : A2
000
1E / 2E-3402 - A1 : C3
MOTOR LIFTER, SPADE & SPOOL,
R12
NRV, GRATE VALVE, CONTROL
R1
00 VALVE, 184 / 284PCA-10007A
00
68
.5°
1E / 2E-6011 - A1 : A3
8058
1E / 2E-1212 - A1 : C3
1E / 2E-1222 - A1 : C3
1E / 2E-1214 - A1 : D3
1E / 2E-1211 - A1 : B3
12000 1E / 2E-1224 - A1 : D3
CRANE APRON 1E / 2E-1221 - A1 : B3
AC / BC 1E / 2E-1203 - A1 : C3
RIGGING ARRANGEMENT 1E / 2E-8401 - A1 : A3
1E / 2E-8402 - A1 : B3
1E / 2E-8406 - A1 : B3
MOTOR LIFTER, SPADE & SPOOL,
MOBILE TELESCOPIC CRANE NRV, GRATE VALVE, CONTROL
GT-600EX VALVE, 184 / 284PCA-10007A
SWL:60 TON
Webbing Slings - Wind speed is between 9 m/s & 12 m/s - reduce the
rated lifting capacity by 50%.
11:36:20 +03'00'
2# no. 2.0m X 2.0ton - Wind speed is between 12 m/s & 14 m/s, reduce the
rated lifting capacity by 70%
06 04-OCT-2023
NEW EQUIPMENT ADDED
ISSUED FOR APPROVAL
GIJO VM SJ
LIFT WEIGHT UPDATED
(Choker Hitch) - Stop operation when the wind speed exceeds 14 m/s.
05 05-APR-2023
04 12-OCT-2022
ISSUED FOR APPROVAL
REVALIDATED
ISSUE FOR APPROVAL
GIJO
GIJO
VM
VM
SJ
SJ
NOTES: MINER COMMENT
03 07-APR-2022 GIJO ZIN SJ
ISSUE FOR APPROVAL
· Area must be cleared & barricaded properly only by competent persons. 02 07-APR-2022
NEW ITEM ADDED
GIJO ZIN SJ
ISSUE FOR APPROVAL
· All lifting tackles must be inspected & have color code. 01 18-OCT-2021
REVALIDATED
SREEJITH ZIN RAZ
ISSUE FOR APPROVAL
· Integrity of the lifting point / eye bolt / thread to be verified before lifting. 00 21-APR-2021 ISSUE FOR APPROVAL NAFEES ZIN RAZ
· Crane outriggers aren't allowed on red & green concrete, manhole covers or gravels. Rev. DATE DESCRIPTION PRD. BY CHKD APPD
· Use steel plates under crane outriggers above red & green concrete.
· Single reeving maximum capacity 5.6 ton.
MOTOR · All dimensions are in meters. LIFTING ASSURANCE TEAM
· All weight are in metric ton (1 mt =1000 kg).
(Weight:0.5 ton) · Apply appropriate packing/softener material at potential sharp edges where sling is passing. PROJECT QATAR SHELL GTL LIMITED
· Approved lift plan to be available with crane operator at all times. AREA GTL - PHASE 1 & 2
· Blind lift controls to be followed. TITLE FIN FAN MOTORS
· Any lighter load/s within indicated radius can be lifted/shifted as far as rigging arrangement hand made DRG.NO. QSGTL-CRANE SITING-0007
sketch/es are prepared and attached with permit during execution by PIC. SCALE FIT TO PAPER SH. 2/2