Lift Planning & Risk Assessment Sheet
Page 67 of 110
Lift Categorization
Routine ☐ Non-Routine Simple ☒ Non-Routine Complex ☐
I confirm that the risks associated with this lift are as low as reasonably practicable
Date & Time:
Person In Charge Name: Signature
Date & Time:
Appointed person Name: Prasanthan N Signature 08.08.2023 03:00 AM
HANDOVER (In case of change of PERSON IN CHARGE)
Person In Charge Name: Signature Date:
Person In Charge Name: Signature Date:
REMOVAL OF EQUIPMENT:
. Verify the rated capacity, Validity of the load bearing & have a visual check before use.
. Secure the load with lifting tackles as per attached Rigging Tackle Arrangement (Refer the LPRA.)
. Ensure the load is completely free prior to lift from the position & check no loose
objects are with load.
. Drop the load on to the pallet or timber using chain block. (Secure the load).
. Verify the rated capacity, Validity of the load bearing & have a visual check before use.
. After mechanical teams’ necessary preparations done, attach the lifting tackles with the
load & load bearing scaffold as per the Rigging Tackle Arrangements.
. Lift and position the load using chain block, wait for the mechanical team to align & secure
the load in place.
. After installation/box up of the equipment Detach all the lifting tackles from the load.
. Demobilize the tools & tackles from the work location.
Lifting Supervisor
Name & Signature
Prasanthan N
08.08.2023
REMOVAL & REINSTALLATION OF ANGLE VALVE ( MUD DRUM VALVE)
USING LOAD BEARING SCAFFOLDS AT 2E-1112 A GTL T-2 BC AREA
Prasanthan N 1 m.
08.08.2023
QS-GTL-RTA-000033