Standard Operating Procedure Document KEC/IMS/GEN/Q/SOP/1007

No.
Issue. No. 02 Revision. No. 01

QUALITY GATE -T&D SITES Issue. Date. 08-12-2018 Revision. Date. 08-10-2019

Sheet No 1 of 4

QUALITY GATES - T&D SITES

Prepared By Ankit Nimbalkar Reviewed By- Nishant Umare Approved By Arvind Srivastav
Signature Signature Signature
Date 01/06/2022 Date 02/06/2022 Date 03/06/2022
Standard Operating Procedure Document KEC/IMS/GEN/Q/SOP/1007
No.
Issue. No. 02 Revision. No. 01

QUALITY GATE -T&D SITES Issue. Date. 08-12-2018 Revision. Date. 08-10-2019

Sheet No 2 of 4

CONTENT

SL NO. DESCRIPTION PAGE NO.

I COVER SHEET 1

II CONTENT 2

1 PURPOSE 3

2 SCOPE 3

3 RESPONSIBILITY 3

4 PROCESS 3-4

5 RECORDS 4
Standard Operating Procedure Document KEC/IMS/GEN/Q/SOP/1007
No.
Issue. No. 02 Revision. No. 01

QUALITY GATE -T&D SITES Issue. Date. 08-12-2018 Revision. Date. 08-10-2019

Sheet No 3 of 4

1 PURPOSE:
This procedure is to ensure that each succeeding work activity is carried out after internal checks and
compliance through Quality gates at T&D sites.

2 SCOPE:
This process is applicable for T&D (TL & Sub Station) across KEC International Limited for all project sites.

3 RESPONSIBILITY:
1. PRIMARY: Quality Manager/ Project Manager
2. SECONDARY: Quality Engineer/ Project Engineer/Surveyor

4 PROCESS:
The following diagram shows the applicability and criteria for Quality stage gate.
Standard Operating Procedure Document KEC/IMS/GEN/Q/SOP/1007
No.
Issue. No. 02 Revision. No. 01

QUALITY GATE -T&D SITES Issue. Date. 08-12-2018 Revision. Date. 08-10-2019

Sheet No 4 of 4

Points to be Ensured:
➢ The above Quality stage gates shall not be bypassed in any condition.
➢ Approval for commencing next activity must only be given after ensuring that all the observations
mentioned in gate checklist are fully complied.

5 Records:
The following Quality gate clearance are to be used for respective activity.
a) KEC/IMS/Q/SOP-1007/F/001 – Survey
b) KEC/IMS/Q/SOP-1007/F/002 – Excavation
c) KEC/IMS/Q/SOP-1007/F/003 – Stub Setting
d) KEC/IMS/Q/SOP-1007/F/004 – Foundation
e) KEC/IMS/Q/SOP-1007/F/005 – Erection
f) KEC/IMS/Q/SOP-1007/F/006 – Stringing