1.0 Scope
This method statement details the method of installation of Lighting Fixtures as per
Project Specification 16505.
Note
A separate Method Statement Ref. ETA/MS/E-40 shall be submitted for testing and
commissioning of the Lighting Fixtures.
2.0 Material
2.2 Sizes of the wires shall be as per approved shop drawings / system
manufacturers recommendation.
4.0 Method
4.1 Storage
4.1.1 All materials received at site shall be inspected and ensured against
approved material submittal.
Page 2 of 4
Burj Dubai – The Residences Nasa Multiplex
Client :- MEP Contractor
Emaar Properties (1804)
4.1.3 Material found not suitable for the project are to be removed from site
immediately.
4.2 Installation
4.2.1.2 Transfer the wire coils to the work place manually with the
help of proper man power.
4.2.1.3 Check the colour and size of the wire is as per approved
shop drawings.
Page 3 of 4
Burj Dubai – The Residences Nasa Multiplex
Client :- MEP Contractor
Emaar Properties (1804)
5.0 Records. :