METHOD OF STATEMENT FOR ERECTION WORKS

BACKGROUND INFORMATION
COMPANY DETAILS: No. 3A, Jalan KB2/15, COM Industrial Park 2, Kawasan Perindustrian
Kampung Baru Balakong, 43300 Seri Kembangan,
Selangor Darul Ehsan, Malaysia.
Tel: 603 – 9081 6965
Fax: 603 - 87276100
CLIENT: M Luna
OVERVIEW OF PROJECT/ACTIVITY: Installation CT coil and CT Meter at MSB room

IMPLEMENTATION AND CONTROL OF RISK

Bil Detail Description Of Activities Hazard & Potential Method Of Control PIC Remarks
Risk
1. Work permit application
- Wrongly fill up PTW. 1) Toolbox briefing. Competent
2) Ensure work permit person at site
has been applied and
approved.
3) Comply with instruction
given / inform by
Operation.

2. Loading & unloading the equipment


and tools to site.

- Inspect and ensure the accessible the - Unclear boundary of 1) Use a proper PPE Competent
loading area. working. 2) Use proper equipment person at site
- Ergonomic or tools
Bil Detail Description Of Activities Hazard & Potential Method Of Control PIC Remarks
Risk
3. Isolation AC Mains Supply

- Switch OFF the MSB mains AC - Unclear boundary of 1) Use a proper PPE Electrical
Breaker working. 2) Use correct and proper Contractor
- Ensure no AC supply to SSB - Risk of Electrical equipment and tools
panel shock 3) Use LOTO system
- Dismantle MSB output cable (to 4) Establishing that all
SSB input cable) equipment, plant, tools and
- Install CT coil and CT Meter substance used are
- Laid CT Secondary connection suitable for the task and
wires and terminate the CT kept good working
Secondary wires to CT Meter. condition.

4. Installation new CT coil and CT Meter

- Dismantle MSB output cable (to - Unclear boundary of 1) Use a proper PPE Swicpower
SSB input cable) working. 2) Use correct and proper technical
- Install CT coil and CT Meter - Risk of Electrical equipment and tools personnel
- Laid CT Secondary connection shock 3) Use LOTO system
wires and terminate the CT 4) Establishing that all
Secondary wires to CT Meter. equipment, plant, tools and
substance used are
suitable for the task and
kept good working
condition.

5. After completed installation works.


Switch ON AC Mains Supply

- Switch ON AC Mains supply - Unclear boundary of 1) Barricade and sign the Electrical
Breaker working. location of works. Contractor
- Measure on the AC output supply, - Risk of Electrical 2) Used proper PPE and
ensure the voltage and current is shock. Isolated Equipments.
normal. 3) Establishing that all
equipment, plant, tools and
substance used are
suitable for the task and
kept good working
condition.
Bil Detail Description Of Activities Hazard & Potential Method Of Control PIC Remarks
Risk
6. After completed installation works.

- After switch ON AC mains supply. - Unclear boundary of 1) Use a proper PPE Competent
- Measure on the AC Incoming working. 2) Use correct and proper person at site
supply, ensure the voltage and - Risk of Electrical equipment and tools
current is normal. shock. 3) Use LOTO system
- Check and test on the CT meter, 4) Establishing that all
ensure the meter working equipment, plant, tools and
properly. substance used are
suitable for the task and
kept good working
condition.

7. House keeping
- Site access 1) All unwanted materials Competent
blocked must be removed from time person at site
to time
2) Ensure emergency is clear
from materials and debris

Prepared by: Approved by:

……………… ………………….. ……………… ………………………


(Name) (Name)

(Signature)
(Signature)