PROJECT ; FLOOR / SLAB NO. 2 , DRYING ROOM-2 / 'S5' LOCATION below platform' WHO-20D'
CLIENT ; BUILDING NAME; Production building , FIT-1

Clear Short Dimension (m) 1.575


Clear Long Dimension (m) 7.100

Slab Thickness (cm) 27.5


m = S/ L 0.22
Covering of concrete (cm) 7
ONE WAY SLAB (YES/NO) YES

CONSTANT
fy ksc 4000
fc' ksc 280
β= ksc 0.85

k = β 6120/(6120 + fy) 0.51


m = fy / 0.85 fc' 16.81
ρ max = 0.75 k / m 0.023 SHORT LONG
ρ = 0.5 ρb 0.015 External(-Mdisc) Middle(+M) Continious(-Mcont)External(-Mdisc) Middle(+M) Continious (-Mcont)
Bending Moment Mu (kg.m/m) 2495.0 1294.0 2495.0
Effec Deep (actual) (cm) 20
Effe Depth of Slab. (Req) (cm) 7.213 5.194 7.213
Check depth of Slab (O.K / No) O.K O.K O.K
Ru = Mu / Φbd² ,b = 1 m, Φ = 0.9 ksc / m 6.931 3.594 6.931

ρ require = (1- √(1-2xRu/ 0.85 fc' ) )/m 1/m 0.002 0.001 0.002
Require As = ρbd cm²/m 3.517 1.811 3.517

Provide As cm²/m 3.93 3.93 3.93 3.93 3.93 3.93


Provide Dia of Re-Bar ( RB / DB) DB 10 10 10 10 10 10

Spacing Of Re-bar m 0.2 0.2 0.2 0.2 0.2 0.2

Check Shear Strength


Shear =(Wu)x0.5xs = Vu(kg/m) 2381.40 <-- b = 1.0 m. ** Remark For the amount of requirement for top rebar in short span = 1.693 >1.51 anyway
opening area ( cm2) 228.00 <-- 15.2x15 cm. actually the opening posititon is not located at the edge of span ( M-max = 771.3 kg*m/m.) but
ΦVc = Φ 0.53(bd - opening area) √fc'; Φ = 0.85 (kg) 13357.88 next to the edge of span .,so bending moment is less than maximum , 1.51 is amount of reamining re
Φ Vc >= Vu (Ok/ No) O.K after cored can accept.

The existing re-bar


more than amount
of re-bar required,
Satisfactory!