PLEASE NOTE: WE WILL NOT ATTEND SITE TO CARRY OUT THE INSTALLATION UNTIL YOU HAVE RETURNED THE
COMPLETED CHECKLISTS TO US CONFIRMING THAT ALL SERVICES ARE IN PLACE, INCLUDING PHOTOGRAPHS OF SERVICES.
Installation Requirements:
Yes No Comments
Power Supply: 230v AC, 50Hz,
16 Amps, Single Phase.
Power Supply: 110v AC. 60Hz
32Amp, Single Phase.
Air Supply: Dry and filtered, Oil
free compressed air at nominal
3-4 bar, to give flow of 60 l/min.
Has to be regulated with an
isolator valve. 8mm Push fit pipe
connection. The air must be
supplied via an approved
regulator.
Gas Supply: Commercial
propane with a purity of 99%,
capable of delivering 1 l/m at a
pressure of 1 bar. Has to be
regulated with an isolator valve.
Water Supply: Domestic supply
is usually adequate depending
on ambient temperatures at
location. 6mm push fit fitting, 0-
1 l/m flow rate required,
(required for ISO 5659-2 only)
Water Outlet: 6mm push-fit
fitting to drain. Recirculating
chiller also acceptable.
Access Requirements:
Access to the building/laboratory:
Yes No Comments
1. Do you have a forklift
truck for unloading and
moving the apparatus?
Comments:
Please add any information our technician may need to know prior to his installation visit below: