JOB HAZARD ANALYSIS

Team composition: 04 / 11/ 2016


TASK: EXCAVATION AND LAYING OF CABLE FROM A8 TO A9 1) Uche Nwabueze (3) TIMIPRE-TOME OHORE
2) Alozie Sunday
Task step Hazard-Source Threats Top-Event Consequence Who/what Inher Barrier/ Control Recovery Action Party
May be ent Measure Measure
harmed Risk
1)-Visual H1 T1 C1.1-Adequate use R1.1-Apply
Inspection of Sharp-edges Inadequate use -Trip & fall -Injury to Personnel L of PPE- first-aid
site H2 of PPE personnel P1B C1.2-Make
Cable / Fuel line T2 - observation and R1.2-
H3 Inability to - report MEDIVAC
Poor Illumination make C1.3-Provide injured person
H4-Open observations lighting around
trenches C1.4-Do not over
stay inside
C1.5-Use of nose
mask

2)-Excavation H1- Use of Hand T1-Inadequate -Contact to sharp -Injury to Personnel C2.1-Ensure R2.1- Apply
tools use of PPE edges worker & adequate use of first-Aid
-Asset Damage Equipment PPE & Raise PTW
C2.2-No Horse- R3.2-
H2-Sharp-edges. T2-Horse-play -Loss of control play MEDIVAC

H3-Underground T3-Fatigue -Cut / Wound C2.3-Rest a while


facilities
T3.1-Poor -Skeletal- C2.3.1-Ensure
Supervision muscular proper supervision
disorder
T3.2-Tripping C2.3.2- Mind your
Hazard steps

T3.3- Poor C2.3.3-Do not


weather work under-rain
condition

3)-Laying of H1-Shape Edges T1-Inadequate -Contact to Injury to Personnel L C3.1- Use of PPE, R4.i Apply
Cable use of PPE sharp-edge personnel & P1.B C3.2-Avoid body First Aid.
Environment E1.B contact with
-Cut / Wound & sharp-edges. R1.iii
Environmental MEDEVAC
-Trip & Fall impact

H2-Weight of T2.0-Fatigue C3.2.0-Rest a


Cable while

T2.1-Poor
Supervision C3.2.1-Follow
procedures.
T2.2- Weather
condition C3.2.2-Do not
work under rain
T2.3-
Underground
facilities C3.2.3-Watch your
steps and work
carefully

4)-Back filling Personnel C4.1-Ensure R4.1- Apply


of Sand H1- Use of Hand T1-Inadequate -Contact to sharp Injury to & adequate use of First Aid.
tools use of PPE edges worker Environment PPE..
-Asset Damage C4.2-No Horse- R4.2.
play Medivac

H2-Sharp-edges. T2-Horse-play -Loss of control C4.2.0-No horse-


play.

H3-Underground T3-Fatigue -Cut / Wound C2.3-Rest a while


facilities
T3.1-Poor -Skeletal- C2.3.1-Ensure
Supervision muscular proper supervision
disorder
T3.2-Tripping C2.3.2- Mind your
Hazard steps

T3.3- Poor C2.3.3-Do not


weather work under-rain
condition
Prepared by ………………………………………………. Approved by ……………………………………… Approved ………………………………

WORK METHOD PROCEDURE / STATEMENT


INTRODUCTION: This document present the methodology involved in the ‘’EXCAVATION AND LAYING OF CABLE AT A.8 TO A.9

TASK: Excavation and Laying of Cable from A8 TO A.9

S/N TASK STEP STEPS DESCRIPTION REMARK


1 Raise Permit to Work (PTW) and Permit to work will enable the asset owners know about the job
other applicable attachment and put all control in place before execution of work.
2 Conduct Tool Box Meeting Toolbox meeting to be conducted to enable workers identify the
hazard and put control in place before commencing activities
3 Visual Inspection This involved the inspection of the work area where work is to be
carried out.
4 Do Excavation work Excavation work to be carried out with the use of insulated
excavation materials to enable laying of cable.
5 Laying of Cable Laying of cable from A8 TO A9
6 Back filling of Sand Back filling of sand will be carried out will be carried out after cable
have been laid.

Prepared by ……………………………………………… Approved by ……………………………………………