Professional Documents
Culture Documents
Jha For Excavation Work 2016
Jha For Excavation Work 2016
2)-Excavation H1- Use of Hand T1-Inadequate -Contact to sharp -Injury to Personnel C2.1-Ensure R2.1- Apply
tools use of PPE edges worker & adequate use of first-Aid
-Asset Damage Equipment PPE & Raise PTW
C2.2-No Horse- R3.2-
H2-Sharp-edges. T2-Horse-play -Loss of control play MEDIVAC
3)-Laying of H1-Shape Edges T1-Inadequate -Contact to Injury to Personnel L C3.1- Use of PPE, R4.i Apply
Cable use of PPE sharp-edge personnel & P1.B C3.2-Avoid body First Aid.
Environment E1.B contact with
-Cut / Wound & sharp-edges. R1.iii
Environmental MEDEVAC
-Trip & Fall impact
T2.1-Poor
Supervision C3.2.1-Follow
procedures.
T2.2- Weather
condition C3.2.2-Do not
work under rain
T2.3-
Underground
facilities C3.2.3-Watch your
steps and work
carefully