Operator: JAMES
HOLCOMB_MLD_OP
HOLCOMB_MLD_OP
1. Equipment setup, take down, and 4.00 HR 0.00 58.01 0.00 232.04
monitoring (hourly charge)
2. Add for personal protective 4.00 EA 0.00 39.81 15.13 174.37
equipment - Heavy duty
3. Add for HEPA filter (for negative 0.25 EA 0.00 207.37 4.56 56.40
air exhaust fan)
Crawlspace
4. Clean floor or roof joist system in 1,900.00 SF 0.00 2.43 3.61 4,620.61
confined space
5. HEPA Vacuuming - Detailed - 1,900.00 SF 0.00 0.89 0.00 1,691.00
(PER SF)
6. Seal the surface area with 1,900.00 SF 0.00 1.54 155.23 3,081.23
fungicidal/bacterial inhibitor - one coat
Attic
7. Contents - move out then reset - 1.00 EA 0.00 95.59 0.00 95.59
Large room
8. Tear out and bag wet insulation in 1,900.00 SF 2.13 0.00 10.83 4,057.83
confined space - Cat 3
9. Sheathing - plywood - 1/2" CDX 192.00 SF 0.00 1.84 18.79 372.07
Plywood is needed to make a temporary floor to safely be able to maneuver and clean and seal attic space.
10. Hazardous Waste/Mold Cleaning 8.00 HR 0.00 69.44 0.00 555.52
Technician - per hour
2 Remediation Technician/4 Hours to manipulate plywood throughout attic space.
11. HEPA Vacuuming - Detailed - 1,900.00 SF 0.00 0.89 0.00 1,691.00
(PER SF)
12. Clean floor or roof joist system in 1,900.00 SF 0.00 2.43 3.61 4,620.61
confined space
CONTINUED - Attic
13. Disinfect building - fog / spray - 1,900.00 SF 0.00 0.48 7.22 919.22
per SF
14. Seal the surface area with 1,900.00 SF 0.00 1.54 155.23 3,081.23
fungicidal/bacterial inhibitor - one coat
Summary
Line Item Total 24,874.51
Material Sales Tax 374.21
Recap of Taxes
Recap by Room
Recap by Category
Items Total %
CLEANING 9,234.00 36.57%
CONTENT MANIPULATION 95.59 0.38%
GENERAL DEMOLITION 4,047.00 16.03%
FRAMING & ROUGH CARPENTRY 353.28 1.40%
HAZARDOUS MATERIAL REMEDIATION 5,060.60 20.04%
PAINTING 5,852.00 23.18%
WATER EXTRACTION & REMEDIATION 232.04 0.92%
Subtotal 24,874.51 98.52%
Material Sales Tax 374.21 1.48%