You are on page 1of 1

Working procedure for Charging Station Foundation Construction:

1. Layout of foundation to be done as per drawings.


Title 2. Reinforcement cutting, bending, placing & binding as per approved BBS
& Drawing.
1 Charging station Foundation details on Well compacted floor (or) Concrete floor 3. Shuttering/Formwork for foundation as per drawing.
4. Concrete casting up to 192 mm from FGL. Tamp the concrete while
2800 concreting to avoid formation of honeycombs or air voids.
233 233
5. Base plate fixing ,alignment of Anchor bolts and Placing of Ø 50 mm
258 150 150
258
PVC Conduit to be placed as per drawing measurements.
6. Concrete casting up to 300 mm from FGL.
150 1700 150
7. De-shuttering of foundation after 24 Hrs.
A A' 8. Curing for minimum of 7 Days ( If curing is not possible for minimum of
7 days then use curing admixtures like Sika Antisol or as availability )
1000
695
1045 50 mm Dia PVC Notes :
450 535
Conduit Pipe
450
1. All levels and Dimensions are mentioned in mm. Unless otherwise
specified and the drawing is not to scale.
2. The clear cover for reinforcement shall be 50 mm for foundation.
3. Use M20 (1:1.5:3) Grade of concrete for R.C.C.
BOTTOM BARS: 4. All reinforcement steel shall be TMT Bars of Grade Fe 500 confirming to
TOP BARS:
8mm Dia @ 300 mm C/C IS:1786 - 2008
Bothways
8mm Dia @ 300 mm C/C 5. Lap length shall be 50 times to Dia of the bar.
Bothways
6. All Hooks, Bends and splices shall be provided as per IS 456:2000.
7. If foundation bolts are fouling with stirrups, then it may suitably adjust at
14 mm Anchor bolts 14 mm Anchor bolts site.
8mm Thick MS Plate 8mm Thick MS Plate 8. Foundation bolts shall be placed in position before concreting. Incase of
2800
unavailability of foundation bolts before concreting suitable bolt pockets
150 1700 150 shall be provided on site, later pockets need to be filled with GP2 grout.
100 9. All finished edges shall be smooth and free from sharpness and burrs.
300
192
300 10. Foundation shall not be laid on loose sandy soil.
FGL
Hard Strata or Concrete floor or Well Compacted earth
Check Points :
1. Ensure to maintain covering on all sides of the reinforcement.
Section - AA' 2. Verify the Foundation dimensions as per approved drawing before casting
Y
and after casting.
3. Ensure to Use M20 (1:1.5:3) Grade of concrete for R.C.C. and TMT Bars
of Grade Fe 500.
X 8mm Thick MS Plate Details 4. Ensure the position of anchor bolts and PVC Conduit as per detailed
drawing.
83 117 117 83
Abbrevations: Project Name and Location :
FGL - Finished Ground Level 108
Single Charging Station Deployment on hard strata
PVC - Poly Vinyl Chloride
c/c - Center to Center Distance 94
MS Plate - Mild Steel Plate 400 Client :
Ø - Diameter 90
R.C.C. - Reinforced Cement Concrete
108
S.No. Bar Shape a (mm) b (mm) c (mm) Dia (mm) Spacing (c/c) in mm Cutting length No.s Total Length (mm)
1 Bottom reinforcement 400
X-Dir a b c 200 2700 200 8 300 3100 4 12400 6 Holes Ø 16mm
Issued for : Construction
Y-Dir a b c 200 900 200 8 300 1300 10 13000
Form work 2.58 Sq.m.
2 Top reinforcement Date : 04 April 2023
X-Dir a b c 100 2700 100 8 300 2900 4 11600 Excavation 0.00 Cum.
b
Drawn by : Vedavyas Dande
Y-Dir a c 100 900 100 8 300 1100 10 11000
R.C.C. - M20 Concrete 0.84 Cum.
Total length in Meter 48 Constructionsvedika9 LLP,
Cement 268.80 Kgs Approved by :
# 12-1-17, Ganesh Nagar,
Unit Weight per Meter 0.395 kg/m Siddipet, Telangana 502103
Aggregate 0.72 Cum.
Total weight of www.constructionsvedika.com
18.96 Kgs Sand 0.36 Cum.
Reinforcement +91 905 2254911

You might also like