Pooja Mining & Marbles Pvt. Ltd.

Project - BPTP Terra Sector 37D Gurgaon Haryana.


Rate Analysis
Amendment-06
1 Analysis for Onex Cladding

Acrylic Plastic Sheet 52,920


Unsaturated Polyster Sheet 282624
Scaffolding Lumpsum Amount 5000
Labour Charge 150 720.283824 108042.57
448,586.57
Add: Water & Electricity 3% 13,457.60
Total with Overhead 462,044.17
Add: Contracor's Profit 20% 92,408.83
Grand Total Amount 554,453.00
Rate / Sqm 8285.81
Onex Cladding Rate Analysis

Acrylic Sheet ( For Framing) 790.84


Unsaturated Polyster Sheet 2970.864
Wastage 42% 1247.763
Scafolding 75.348
Labour ( Including L cleet, Screw, Adhesive & other consumable) 1614.6
6699.415
Electricity + Water 200.9824
Profit 20% 1339.883
8240.28
551189.3