You are on page 1of 3

SABGS SCHOOLS PHASE III

CONTRACT No. (6601000200)


BI No. (23-10883)
Construction Daily Report
Project Location ABQAIQ GIRLS ELEMENTARY SCHOOL 01
Report No. #110 Date: 14 April 2024
Day Sunday Climate Clear Sunny Cloudy Rainy TEMPERATURE : 27.00°C

SN Division Activity Description Status Start Finish Previous Today Cummulative Remarks

1 Construction Concrete Curing for footing foundation Ongoing 05/04/2024

2 Construction Surface Prepration for footing foundation Ongoing 14/04/2024

4 Construction House-keeping Ongoing 11/01/2024

PLANNED ACTIVITIES FOR TOMORROW


SN Division Activity Description Status Start Finish Remarks

1 Construction Concrete Curing for footing foundation Ongoing 28/02/2024

2 Construction Surface Prepration for footing foundation Ongoing

3 Construction House-keeping Ongoing 11/01/2024


SABGS SCHOOLS PHASE III
CONTRACT No. (6601000200)
BI No. (23-10883)
Construction Daily Report
Project Location ABQAIQ GIRLS ELEMENTARY SCHOOL 01
Report No. #110 Date: 14 April 2024
Day Sunday Climate Clear Sunny Cloudy Rainy TEMPERATURE : 27.00°C
ISSUES & CONCERNS
SN Division Issue & Concerns Issued by Proactive Remarks

10
SABGS SCHOOLS PHASE III
CONTRACT No. (6601000200)
BI No. (23-10883)
Construction Daily Report
Project Location ABQAIQ GIRLS ELEMENTARY SCHOOL 01
Report No. #110 Date: 14 April 2024
Day Sunday Climate Clear Sunny Cloudy Rainy TEMPERATURE : 27.00°C
SITE PHOTOS

Main Building Footings Curing Main Building Footings Surface prepration

Main Building Footings Surface prepration Main Building Footings Surface Chipping