You are on page 1of 1

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

NOTES

1) ALL DIMENSIONS ARE MILLIMETERS, ELEVATIONS & CO-ORDINATES ARE IN METERS.


2) MAIN PLANT DATUM ELEVATION IS THE HIGH POINT OF PAVING (H.P.P.) WHICH EQUALS TO 100.000 METERS.
A AND IT CORRESPONDS TO 7.55m BASED ON ROYAL COMMISSION DATUM THAT IS EQUAL TO MEAN SEA LEVEL.
A
3) ANY DISCREPANCY ON THIS DRAWING TO BE REPORTED TO ENGINEERING IMMEDIATELY FOR CLARIFICATION.
4) REBARS TAG TO CALLOUTS ARE SHOWN ON DRAWING USING THE FOLLOWING FORMAT:
MK2-98⌀ 25@100
BAR SPACING
MK4 MK4 NOMINAL REBAR DIAMETER
QUANTITY

3915
MK13-1Ø12(S/F) BAR MARK
100.300 TOC
MK3-1Ø12(S/F) 5) MATERIALS:
100.300 TOC 100.300 TOC STEEL REINFORCEMENT : ASTM A615/A615M, GRADE60 (fy = 415MPa) SHALL BE AS PER AES-C-0004
MK23-1Ø12(S/F)
MK12-14Ø16@200(T) REINFORCEMENT WITH FUSION BONDED EPOXY COATED REBARS.
B B
22 22 MK11-14Ø20@200(B) 24 24

MK1-12Ø20@200(B)
MK2-12Ø16@200(T)
MK3-1Ø12(S/F) MK3-1Ø12(S/F)

MK21-11Ø20@200(B)
26 26

MK22-11Ø16@200(T)
MK23-1Ø12(S/F) MK23-1Ø12(S/F)
- - - -

1815
1790
MK14 MK14 MK24 MK24
MK2
23 23
- -
MK2
21 21 MK12 25 25
- - MK12
- - MK22
MK22
- - MK3 MK3 MK13-1Ø12(S/F) MK13-1Ø12(S/F)
MK22-11Ø16@200(T)
MK13 MK13 MK23 MK23
MK2-12Ø16@200(T) 400 MK1 MK21-11Ø20@200(B)
MK1-12Ø20@200(B)
MK5-2Ø10 350 MK11 350 MK21
MK1 MK11-14Ø20@200(B) MK15-2Ø10 MK23-1Ø12(S/F)
C MK3-1Ø12(S/F) MK13-1Ø12(S/F)
MK25-2Ø10 C
MK12-14Ø16@200(T) MK11 MK21

R/F DETAIL OF RFJ001 SECTION 21 R/F DETAIL OF RFJ002 SECTION 23 R/F DETAIL OF RFJ003 SECTION 25 HOLDS
(SCALE: 1 : 50) (SCALE: 1 : 50) - (SCALE: 1 : 50) (SCALE: 1 : 50) - (SCALE: 1 : 50) (SCALE: 1 : 50) -
HOLD-1 FOUNDATION UNDER HOLD

D D
MK4-2Ø25

MK4-2Ø25

MK4-4Ø25 MK14-5Ø20

MK24-2Ø20
MK24-4Ø20

MK24-2Ø20
MK14-3Ø20
MK14-3Ø20
E E
MK4-4Ø25

MK14-5Ø20 MK24-4Ø20

SECTION 22 SECTION 24 SECTION 26


(SCALE: 1 : 25) - (SCALE: 1 : 25) - (SCALE: 1 : 25) -

F F

MK41-13Ø16@200(T)
MK41-13Ø16@200(B)
G G
32
29 29 30 30
MK32-5Ø12@200(T)
- - -
MK31-5Ø16@200(B) 28 28 - -
- - MK53-1Ø12(S/F)
955

955
MK33 MK33 MK52-12Ø16@200(T) MK51-12Ø20@200(B)
MK43 MK43
MK56 MK56
MK32 MK41
MK32
27 27

3915
MK42
MK52-12Ø16@200(T)
- - MK51-12Ø20@200(B)
100.300 TOC
H MK32-5Ø12@200(T) MK42-4Ø16@200(T) H
MK31-5Ø16@200(B)
31 31
MK42-4Ø16@200(B)
- - 33 33 34 34
250 MK41 MK53-1Ø12(S/F) MK53-1Ø12(S/F)
200 MK31
MK44 - - - MK57
-

965
MK34-2Ø10 MK52 MK52
MK31 MK42 MK52 MK52

MK53-1Ø12(S/F)
MK53 MK53 MK53 MK53

R/F DETAIL OF RFJ004 SECTION 27 29 29 400 300


- - 32 MK54-2Ø10 MK51 MK51 MK55-2Ø10
I (SCALE: 1 : 25) (SCALE: 1 : 25) - SECTION 29
- (TYP.) (TYP.) I
(SCALE: 1 : 25) - MK51 MK51
REFERENCE DOCUMENTS
DRAWING NO DESCRIPTION
R/F DETAIL OF RFJ006 SECTION 31 SECTION 32 4245-AA-DC-1362502001 (CV-136-0599-DLA)
CONCRETE FOUNDATION DRAWING FOR PIB BUILDING 1362-BL001A -
FOUNDATION LAYOUT
R/F DETAIL OF RFJ005 (SCALE: 1 : 50) (SCALE: 1 : 50) - (SCALE: 1 : 50) - 4245-AA-DC-1362502002 (CV-136-0600-DLA)
CONCRETE FOUNDATION DRAWING FOR PIB BUILDING 1362-BL001A -
FOUNDATION PLINTHS - FORMWORK
(SCALE: 1 : 25) CONCRETE FOUNDATION DRAWING FOR PIB BUILDING 1362-BL001A -
4245-AA-DC-1362502004 (CV-136-0602-DLA)
FOUNDATION PLINTHS - BBS

J MK33-3Ø16 J
MK43-3Ø16

MK56-2Ø25

MK56-2Ø25
MK56-4Ø25
MK57-1Ø16
MK33-1Ø16 MK33-1Ø16

MK57-3Ø16

MK57-3Ø16
MK43-1Ø16 MK43-1Ø16
MK33-3Ø16
MK43-3Ø16

MK57-1Ø16
MK56-4Ø25
SECTION 28 SECTION 30
K (SCALE: 1 : 25) - (SCALE: 1 : 25) - SECTION 33 SECTION 34
K

(SCALE: 1 : 25) - (SCALE: 1 : 25) -

35 39 HOLD-1
- 37 -
L - L

MK72-12Ø16@200(T) MK84-12Ø16@200(T)
MK63-1Ø12(S/F) MK73-1Ø12(S/F) MK71-12Ø20@200(B) MK85-1Ø12(S/F) MK83-12Ø20@200(B)

MK63-1Ø12(S/F)
MK65 MK65 100.300 TOC
MK84-12Ø16@200(T) APPROVED FOR CONSTRUCTION
MK83-12Ø20@200(B) MK82 MK82
3915

MK62-12Ø16@200(T)

3915
100.300 TOC
38 38 Date Initials Signature
MK61-12Ø20@200(B) MK75 MK75 100.300 TOC
- -
1790

MK73-1Ø12(S/F) MK73-1Ø12(S/F) 31-Mar-2022


MK85-1Ø12(S/F) MK85-1Ø12(S/F) S. Villari
MK72
M 36 36 MK72 M
40 40
- - MK72-12Ø16@200(T)
-
MK81
-
MK84

965
MK63-1Ø12(S/F) MK62 MK71-12Ø20@200(B)
MK62 MK73 MK73
MK84

MK63-1Ø12(S/F) MK62-12Ø16@200(T) MK73-1Ø12(S/F) 350 MK71


MK63 MK63 MK85-1Ø12(S/F) MK85 MK85
MK61-12Ø20@200(B) (TYP.) MK74-2Ø10

MK61 37 MK71 39 MK87 300 400 MK83


35
- MK61
MK64-2Ø10 - - MK86 00 31-Mar-2022 Issued For Construction M.Carbone M.Piatti A.Zoppellaro

MK83 B 24-Mar-2022 Issued For Design M.Carbone M.Piatti A.Zoppellaro

N A 02-Feb-2022 Issued For Preliminary M.Carbone M.Piatti A.Zoppellaro N


Rev Date Reason For Issue Prepared by Checked by Approved by
R/F DETAIL OF RFJ007 SECTION 35 R/F DETAIL OF RFJ008 SECTION 37 R/F DETAIL OF RFJ009 SECTION 39
CONFIDENTIALITY - This document and the information herein contained are the confidential proprietary information of APOC project. Any disclosure to third
(SCALE: 1 : 50) (SCALE: 1 : 50) - (SCALE: 1 : 50) (SCALE: 1 : 50) - (SCALE: 1 : 50) (SCALE: 1 : 50) - parties, use, or reproduction without proper authorization is strictly prohibited.

MK65-4Ø25
Advanced Polyolefins
MK65-2Ø25
MK65-2Ø25

MK75-3Ø20
MK82-2Ø25
MK81-1Ø16
O T O

MK82-4Ø25
MK81-3Ø16
MK75-5Ø20
MK75-5Ø20

MK82-4Ø25
MK81-3Ø16
APOC PP PLANT
MK65-4Ø25 MK81-1Ø16
JUBAIL INDUSTRIAL CITY, KINGDOM OF SAUDI ARABIA
MK82-2Ø25

MODEL NAME: 4245-AA3D-1362-BL001A


MK75-3Ø20 CONCRETE FOUNDATION
DRAWING FOR PIB BUILDING 1362-BL001A
SECTION 36 SECTION 38 SECTION 40 FOUNDATION PLINTHS - REINFORCEMENT
(SCALE: 1 : 25) - (SCALE: 1 : 25) - (SCALE: 1 : 25) - SCALE: 1:100 SHEET 1 OF 1
P P
CONTRACTOR REVISION FORMAT
Doc. Ref.
4245-AA-DC-1362502003

OWNER
CV-136-0601-DLA
00 A0
Doc. Ref.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

You might also like