PERHITUNGAN VOLUME PEKERJAAN

BACK UP ESTIMATION

PEKERJAAN JALAN RABAT BETON RUAS A-B = P= 152 M L= 5 M

Lebar/T
ebal Sat
URAIAN PEKERJAAN Pjg Tgg/ Tbl Bnyk Vol
No. rata- Volume
rata
(M) (M) (M) (X)
PEKERJAAN PERSIAPAN
1 Uitzet 1 Ls
2 Pembersihan Lapangan 1 Ls
3 Papan Nama Kegiatan 1 Ls
PEKERJAAN JALAN RABAT BETON RUAS A-B = P= 152 M L= 5 M
I PEKERJAAN TANAH
1 Pekerjaan Leveling Sirtu 5,00 152,00 0,10 1,00 76,00
76,00 m3
II PEKERJAAN JALAN BETON RUAS A-B = P= 152 M L= 5 M
1 Pemasangan Plastik Plythene 5,00 152,00 760,00
760,00 m2
2 Sewa Begesthink Plat besi 152,00 2,00 304,00
304,00 m
3 Pekerjaan Rabat Beton K-300 5,00 152,00 0,15 1,00 114,00
114,00 m3
Pekerjaan Grooving 5,00 152,00 760,00
760,00 m
4 Concrete cutting 152,00 1,1 166,21
166,21 m
5 Join Sealant 152,00 0,42 63,84
63,84 Ltr