Professional Documents
Culture Documents
A Short Guide On NEC Contracts For Contractors
A Short Guide On NEC Contracts For Contractors
NEC Contracts
for Contractors:
A Short Guide
Contents
First time working with NEC4? 03
Communication in NEC4 09
2
First time working
with NEC4?
Here’s what you need
to know
The New Engineering Contracts (NEC)
have had a significant impact on how the
construction industry works.
https://www.trowers.com/insights/2017/october/nec4-contracts-evolution-not-revolution
1
3
N E C C O NTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
https://www.causeway.com/blog/how-an-ipt-ethos-supports-the-successful-delivery-of-nec-contracts
1
4
N E C C O NTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
Compensation Events
These are the only events that let
you increase the prices or delay
the contractual completion date.
In other contracts, these would be
called variations and extensions of
time and loss and expense.
Contract Data
This is broken into two parts. If
done incorrectly, it’s very difficult to
manage the contract:
Scope
Essential to understanding the scope of work and
describing the constraints in providing that work.
This was called Works Information under the NEC3
contracts.
Fee Percentages
There are several fee percentages that need to
be tendered in respect of assessing cost, and a
knowledge of their application is crucial when
formalising an NEC4 contract.
Activity Schedule
Under Option A, this is a series of lump sums with
payment only due if you complete the activity, such
as milestone payments.
6
N E C C O NTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
On one end of the scale, you have the more ‘traditional’ lump sum contracts, which give the client maximum
certainty of price, whereas Option F is a cost reimbursable contract – which gives the client the greatest risk:
7
N E C C ONTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
NEC4 puts a stronger emphasis on You need to show standard items It’s essential to note that the PM
programming compared to other like: could reject your programme,
contract types. Under most JCT under clause 31.3, for four reasons:
contracts, the contractor provides • Key dates
a programme. If they want to claim • The contractor’s plan shows it
• Method Statements for each
a time extension, they usually use operation to be impracticable
that programme to show where • It does not show the
delays occurred. • Order and timing of operations information the contract
requires
Under NEC4, you must submit You will also need to show items • Does not represent the
a detailed plan to the Project you wouldn’t normally under other contractor’s plan realistically
Manager (PM) inside the period of contracts, like: • It does not comply with the
reply that’s noted in the Contract Works Information (or Scope)
Data Part 1 – usually two weeks. • Float (how long something can
be delayed without delaying
Failing to provide a programme in The PM must accept the
the project)
that window means the PM can programme inside two weeks. If
deduct 25% from every payment • Risk allowances they withhold acceptance for a
until submitted in the right form. reason not stated in the contract, it
becomes a compensation event.
8
Communication in NEC4
In NEC4 contracts, all communication must be
documented – nothing verbal is permitted.
9
N E C C ONTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
https://www.neccontract.com/support/faqs/is-silence-deemed-acceptance
1
https://www.burges-salmon.com/news-and-insight/legal-updates/nec3-contract-notices-what-to-watch-out-for
1
10
Causeway
Commercial
Management
11
N E C C ONTR ACTS FOR CO NT RACTORS: A SH ORT GUIDE
12
To learn more about how Causeway
Commercial Management can support your
business with managing NEC contracts, talk
to us today!
13