Minor Works Estimates

Note : All prices are in Singapore Dollars and exclude GST. FINAL COSTING

Date of Work Request 1-Apr-14 Type "X" if urgent charges applied


Date of Release2 17-Apr-14
Reference SMM/2014/04/006/V2
Contract Number 8011100253 Type "X" if offshore charges applied
Unit PLC / 11C4I Note to MINDEF/SAF:
Contractor Name Fonda Global Engineering Pte Ltd 1. Please use "95161426" as Commodity Code when
Contact No raising non-catalogue requisitions in ePS
Percentage Adjustment Building (-18%) 2. Cost estimate where the value is up to $7,000 is
Offshore Rates Adjustment NA valid for 3 months from the date of release.

REMINDER : The following works are not meant for construction, demolition of buildings/facilities and ADDTIONS/ALTERATION works
which result in a CREATION of building (e.g. Construction of a roof over existing walls), CHANGE in building GFA and earth filling works.

Short Description of works Minor Building Works for 11C4I

Item Service Number Item description Page Qty UOM Unit Rate ***Deduction for Percentage Total
No Number labour, where Adjustment Cost
applicable
(-10%)
Replace Window Handle and
Pull Handle at Blk 260

Stainless Steel Pull Handle


Stainless steel pull handle
complete with fixing accessories,
SR/BL/
l BI_HANDLE003 suitable for timber and metal doors 2 No 12.18 -18% $ 19.98
H/2
(Rate per number of handle)
19mm diameter x 300mm height
stainless steel pull handle

Accessories for Aluminum


Windows
Aluminum handle to casement/top
hung window complete with
SR/BL/I/
f BI_ALUMACCESS006 stainless steel screws including 7 No 2.93 -18% $ 16.82
29
taking out existing handle and
make goods to works disturbed
Natural, bronze or black anodized
aluminum window handle

Ease and Adjust Door, Repair


Door Lock at Blk 260
Timber Door/Casement/Window In
Repairs
Ease and adjust doors and SR/BL/
i BI_WINDOW_DOOR061 2 No 12.07 -18% $ 19.79
windows and re-hang (any type G/5
and size) including taking down
and re-hanging as necessary
SUNDRIES - LOCKSETS
SR/BL/
k BI_LOCKSET022 Opening up lock, re-condition and 2 No 20.79 -18% $ 34.10
H/4
re-fix it
Replace Cubicle Locks at Blk
260 #03-13 Male Toilet
TOILET PARTITIONS
Replace nylon/stainless steel
SR/BL/
r BI_TOILETPTN004 lockset with knob for toilet cubicle 3 No 31.49 -18% $ 77.47
G/10
door with new including taking out
existing
Ease and Adjust Window at Blk
235
Timber Door/Casement/Window In
Repairs
Ease and adjust doors and SR/BL/
i BI_WINDOW_DOOR061 1 No 12.07 -18% $ 9.90
windows and re-hang (any type G/5
and size) including taking down
and re-hanging as necessary
Accessories for Aluminum
Windows
Aluminum handle to casement/top
hung window complete with
SR/BL/I/
f BI_ALUMACCESS006 stainless steel screws including 7 No 2.93 -18% $ 16.82
29
taking out existing handle and
make goods to works disturbed
Natural, bronze or black anodized
aluminum window handle
Replace of Glass Lourvre Panel
at Blk 260 Bunks
Cutting Openings in Glass
Take out existing glass louvres
(any size from doors, windows, SR/BL/
s BI_SUNDRIESGL007 6.24 m 2.15 -18% $ 11.00
vents, louvre frames, and stack M/3
aside or cart away as directed or
set aside for re-use

STANDARD GLASS IN LOUVRES


SR/BL/
r BI_LOUVRESGL011 150mm wide x 5mm thick tinted 6.24 m 6.09 -18% $ 31.16
M/2
float glass louvres
Subtotal (A+B) 237.03
Add Offshore Charges*
Note to MINDEF/SAF: When raising non-catalogue requisition in ePS, Less Cost Cap
please use the Short Description of Works as Item Description and Add Urgent Charges(for emergency
The unit price shall be the same as the "Total (excluding GST)"
works order only)
quantity as "1 Lot" on the right. Total (excluding GST) 237.03

Signature
Prepared by Simon Ang
Technical Officer
I declare that:**

a. The works quoted above do not involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of
a roof over existing walls), CHANGE in building GFA and earth filling works.

b. The works quoted above involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of a roof
over existing walls), CHANGE in building GFA and earth filling works. Unit had been advised to submit the work request to DSTA FM for processing.
Signature
Confirmed by S.Poobalan
Asst Operations Manager
*Not applicable to items related to systems, facilities and services contracted under PRMS/PMWS
** Delete where not applicable
*** For PMWS repair work where the FSR item includes supply and installation, 10% of the FSR item cost shall be deducted for labour
Minor Works Estimates
Note : All prices are in Singapore Dollars and exclude GST.

Date of Work Request 1-Apr-14 Type "X" if urgent charges applied


Date of Release2 17-Apr-14
Reference SMM/2014/04/005/V2
Contract Number 8011100253 Type "X" if offshore charges applied
Unit PLC / 11C4I Note to MINDEF/SAF:
Contractor Name Fonda Global Engineering Pte Ltd 1. Please use "95161426" as Commodity Code when
Contact No raising non-catalogue requisitions in ePS
Percentage Adjustment Building (-18%) 2. Cost estimate where the value is up to $7,000 is
Offshore Rates Adjustment NA valid for 3 months from the date of release.

REMINDER : The following works are not meant for construction, demolition of buildings/facilities and ADDTIONS/ALTERATION works
which result in a CREATION of building (e.g. Construction of a roof over existing walls), CHANGE in building GFA and earth filling works.

Short Description of works Minor Plumbing Works for 11C4I

Item Service Number Item description Page Qty UOM Unit Rate ***Deduction for Percentage Total
No Number labour, where Adjustment Cost
applicable
(-10%)
Blk 235 Level 1 Male Toilet -
3789

SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR006 following items: 1 No $ 21.73 -18% $ 17.82
L/31/Q
Clearing
choke/blockage/obstruction in
water closet pan or squat pan

Blk 235 #02-20 Male Toilet -


3790
SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR005 following items: 1 No $ 20.63 -18% $ 16.92
L/31/P
Clearing
choke/blockage/obstruction in
urinal bowl/range/trap
Blk 235 #03-23, #03-26 -
3801

Floor Trap / Floor Waste Gratings


Floor trap/floor waste gratings set
in cement mortar in new or in
SR/BL/
18 BI_FLOORTRAP009 replacement including taking out 2 No $ 3.36 -18% $ 5.51
L/16/E
existing
75mm diameter UPVC floor waste
grating

Blk 235 #04-06 Male Toilet -


3853

SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR006 following items: 1 No $ 21.73 -18% $ 17.82
L/31/Q
Clearing
choke/blockage/obstruction in
water closet pan or squat pan

Blk 235 #02-31 Male Toilet -


3952
SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR006 following items: 1 No $ 21.73 -18% $ 17.82
L/31/Q
Clearing
choke/blockage/obstruction in
water closet pan or squat pan
Blk 235 #04-22 Male Toilet -
4018

SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR005 following items: 1 No $ 20.63 -18% $ 16.92
L/31/P
Clearing
choke/blockage/obstruction in
urinal bowl/range/trap
Blk 235 #03-26 Male Toilet -
4017
SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR005 following items: 1 No $ 20.63 -18% $ 16.92
L/31/P
Clearing
choke/blockage/obstruction in
urinal bowl/range/trap
Blk 235 #03-17 Male Toilet -
4016

Wall Hung Bowl Urinal


Approved vitreous china wall hung
urinal with back inlet including
integral strainer waste and SR/BL/
18 BI_URINAL006 1 No $ 83.14 -18% $ 68.17
brackets to walls (cistern or flush L/26/M
valve measured separately)
Labour only in fixing single bowl
urinal (any type)

Blk 260 #05-13, #06-13 Male


Toilet - 4028
SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR006 following items: 2 No $ 21.73 -18% $ 35.64
L/31/Q
Clearing
choke/blockage/obstruction in
water closet pan or squat pan
Blk 235 #01-16 Male Toilet -
4044

SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR005 following items: 2 No $ 20.63 -18% $ 33.83
L/31/P
Clearing
choke/blockage/obstruction in
urinal bowl/range/trap

Blk 235 #03-17 Male Toilet -


3975
SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
SR/BL/
18 BI_PLUMBINGLBR006 following items: 1 No $ 21.73 -18% $ 17.82
L/31/Q
Clearing
choke/blockage/obstruction in
water closet pan or squat pan

SUNDRIES
Supply labours, equipment and
tools for clearing blockage for the
following items: SR/BL/
18 BI_PLUMBINGLBR004 1 No $ 19.52 -18% $ 16.01
Clearing L/31/O
choke/blockage/obstruction in
floor trap or floor waste on upper
floor

Blk 235 Level 1 Female Toilet -


3788
WASTE FITTINGS
32mm diameter chromium plated SR/BL/
18 BI_WASTEFITTING001 1 No $ 3.15 -18% $ 2.58
waste fitting including all L/30/P
connections
WASTE FITTINGS
Disconnect and take out existing SR/BL/
18 BI_WASTEFITTING005 1 No $ 0.73 -18% $ 0.60
waste fitting, remove off site and L/30/T
prepare to receive new

WASTE TRAP
UPVC bottle trap in new or
replacement including all SR/BL/
18 BI_WASTETRAP003 1 No $ 12.12 -18% $ 9.94
connections and adjustment to L/31/I
pip
32mm diameter UPVC bottle trap
Blk 235 Level 2 Male Toilet -
3849
WASTE FITTINGS
32mm diameter chromium plated SR/BL/
18 BI_WASTEFITTING001 1 No $ 3.15 -18% $ 2.58
waste fitting including all L/30/P
connections
WASTE FITTINGS
Disconnect and take out existing SR/BL/
18 BI_WASTEFITTING005 1 No $ 0.73 -18% $ 0.60
waste fitting, remove off site and L/30/T
prepare to receive new
WASTE TRAP
UPVC bottle trap in new or
replacement including all SR/BL/
18 BI_WASTETRAP003 1 No $ 12.12 -18% $ 9.94
connections and adjustment to L/31/I
pip
32mm diameter UPVC bottle trap
Blk 235 #03-17 Male Toilet -
3976
WASTE FITTINGS
32mm diameter chromium plated SR/BL/
18 BI_WASTEFITTING001 1 No $ 3.15 -18% $ 2.58
waste fitting including all L/30/P
connections
WASTE FITTINGS
Disconnect and take out existing SR/BL/
18 BI_WASTEFITTING005 1 No $ 0.73 -18% $ 0.60
waste fitting, remove off site and L/30/T
prepare to receive new

WASTE TRAP
UPVC bottle trap in new or
replacement including all SR/BL/
18 BI_WASTETRAP003 1 No $ 12.12 -18% $ 9.94
connections and adjustment to L/31/I
pip
32mm diameter UPVC bottle trap
Subtotal (A+B) 320.55
Add Offshore Charges*
Note to MINDEF/SAF: When raising non-catalogue requisition in ePS, Less Cost Cap
please use the Short Description of Works as Item Description and Add Urgent Charges(for emergency
The unit price shall be the same as the "Total (excluding GST)"
works order only)
quantity as "1 Lot" on the right. Total (excluding GST) 320.55

Signature
Prepared by Simon Ang
Technical Officer
I declare that:**

a. The works quoted above do not involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction
of a roof over existing walls), CHANGE in building GFA and earth filling works.

b. The works quoted above involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of a
roof over existing walls), CHANGE in building GFA and earth filling works. Unit had been advised to submit the work request to DSTA FM for processing.
Signature
Confirmed by Steven Lim
Asst Operations Manager
*Not applicable to items related to systems, facilities and services contracted under PRMS/PMWS
** Delete where not applicable
*** For PMWS repair work where the FSR item includes supply and installation, 10% of the FSR item cost shall be deducted for labour