Note : All prices are in Singapore Dollars and exclude GST. FINAL COSTING
REMINDER : The following works are not meant for construction, demolition of buildings/facilities and ADDTIONS/ALTERATION works which result in a CREATION of building
(e.g. Construction of a roof over existing walls), CHANGE in building GFA and earth filling works.
Short Description of works Replacement of Double Leaf Timber Door at Blk 216 #01-05
Item Service Number Item description Page Qty UOM Unit Rate ***Deduction for Percentage Total Cost
No Number labour, where Adjustment
applicable
(-10%)
c BI_WINDOW_DOOR055 Take down doors SR/BL/G/5 2.00 No $ 4.30 -18% $ 7.05
g BI_FLOORFINISH004 cement and sand plastered SR/BL/K/3 5.80 m2 $ 10.08 -18% $ 47.94
Average 3mm thick cement-based
h BI_WALLFINISH008 SR/BL/K/1 5.80 m2 $ 6.61 -18% $ 31.44
skim coat plaster to new walls
i BI_PAINTPLASTER003 undercoat paint to wall SR/BL/N/1 10.00 m2 $ 1.26 -18% $ 10.33
y BI_WINDOW_DOOR033 45mm thick solid Kapur timber panelled SR/BL/G/3 3.50 m2 $ 145.92 -18% $ 418.79
door
a BI_TIMBERFRAMES009 Kapur timber frame SR/BL/G/6 5.80 m $ 16.59 -18% $ 78.90
r BI_LININGS058 laminated plastic sheeting SR/BL/G/9 7.00 m2 $ 25.40 -18% $ 145.80
o BI_PAINT_WOOD012 enamel undercoat to door frame SR/BL/N/2 5.80 m $ 0.42 -18% $ 2.00
u BI_PAINT_WOOD018 enamel topcoat to door frame SR/BL/N/2 5.80 m $ 0.53 -18% $ 2.52
a BI_DOORCLOSERS001 Door closer with regular arm SR/BL/H/6 2.00 No $ 134.69 -18% $ 220.89
f BI_HINGES006 Hinges to timber door SR/BL/H/1 6.00 No $ 10.49 -18% $ 51.61
w BI_FLUSHBOLT001 Stainless steel lever action flush bolt SR/BL/H/6 1.00 No $ 7.87 -18% $ 6.45
200mm
x BI_FLUSHBOLT002 Stainless steel lever action flush bolt SR/BL/H/6 1.00 No $ 8.92 -18% $ 7.31
300mm
Door stops/holders complete with fixing
o BI_DOORSTOPS007 accessories in new or in replacement, SR/BL/H/6 1.00 No $ 7.87 -18% $ 6.45
including taking out existing
Signature
Prepared by Johnny Kindipan
Technical Officer
I declare that:**
a. The works quoted above do not involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of a roof over existing walls), CHANGE in building GFA
and earth filling works.
Signature
Confirmed by Ibrahim Adinan
Asst Operations Manager
*Not applicable to items related to systems, facilities and services contracted under PRMS/PMWS
** Delete where not applicable
*** For PMWS repair work where the FSR item includes supply and installation, 10% of the FSR item cost shall be deducted for labour
748625192.xls
Minor Works Estimates
Note : All prices are in Singapore Dollars and exclude GST.
REMINDER : The following works are not meant for construction, demolition of buildings/facilities and ADDTIONS/ALTERATION works which result in a CREATION of building (e.g.
Construction of a roof over existing walls), CHANGE in building GFA and earth filling works.
Item Service Number Item description Page Qty UOM Unit Rate ***Deduction for Percentage Total Cost
No Number labour, where Adjustment
applicable
(-10%)
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
SCADA, FMS and Security
a BI_NORMAL_HRS001 SR/BL/R/1 2 hr $ 7.46 NA -18% $ 12.23
Management Systems
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
b BI_NORMAL_HRS002 SR/BL/R/1 2 hr $ 13.64 NA -18% $ 22.37
SCADA, FMS and Security
Management Systems
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
a BI_NORMAL_HRS001 SCADA, FMS and Security SR/BL/R/1 2 hr $ 7.46 NA -18% $ 12.23
Management Systems
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
b BI_NORMAL_HRS002 SR/BL/R/1 2 hr $ 13.64 NA -18% $ 22.37
SCADA, FMS and Security
Management Systems
748625192.xls
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
a BI_NORMAL_HRS001 SCADA, FMS and Security SR/BL/R/1 4 hr $ 7.46 NA -18% $ 24.47
Management Systems
LABOUR RATES
Supply the following manpower and
services as and when instructed by the
S.O:
Note: Automation and Control System
Specialists include COLPRO, BAS,
b BI_NORMAL_HRS002 SR/BL/R/1 4 hr $ 13.64 NA -18% $ 44.74
SCADA, FMS and Security
Management Systems
Building Cost
Take down existing timber or
a BI_SUNDRIES017 demountable partitions, remove off site SR/BL/G/11 9.59 m2 $ 7.24 NA -18% $ 56.93
and make good to works disturbed
Timber Door/Casement/Window In
Repairs
c BI_WINDOW_DOOR055 Take down casement windows, shutters SR/BL/G/5 2.00 No $ 4.30 NA -18% $ 7.05
or doors, including ironmongery and
remove off site (Rate per leaf measured)
Take out existing cabinet, work-top and
d BI_FITMENTS001 SR/BL/G/15 6.00 m $ 9.56 NA -18% $ 47.04
the like and cart away off site
o BI_PAINT_WOOD012 enamel undercoat to timber frame SR/BL/N/2 5.00 m $ 0.42 NA -18% $ 1.72
u BI_PAINT_WOOD018 enamel topcoat to timber frame SR/BL/N/2 5.00 m $ 0.53 NA -18% $ 2.17
r BI_LININGS058 1mm thick laminated plastic sheeting SR/BL/G/9 3.28 m2 $ 25.40 NA -18% $ 68.32
Mortise locket
Polished or Satin finished stainless steel
entrance lockset with single key cylinder
r BI_LOCKSET001 SR/BL/H/1 1.00 No $ 137.42 NA -18% $ 112.68
(outside) and thumbturn (inside) (with
handle operated latch bolt, deadlocking
latch upon closing)
748625192.xls
102mm x 102mm x 3mm thick stainless
f BI_HINGES006 SR/BL/H/1 3.00 No $ 10.49 NA -18% $ 25.81
steel Grade 304 hinge
a BI_DOORCLOSERS001 Door closer with regular arm SR/BL/H/6 1.00 No $ 134.69 NA -18% $ 110.45
a BI_WALLFINISH001 Hack Existing Wall Tiles SR/BL/K/1 1.32 m2 $ 6.19 NA -18% $ 6.70
f BI_WALLTILING006 8mm thick glazed ceramic wall tiles SR/BL/K/2 1.32 m2 $ 47.24 NA -18% $ 51.13
j BI_WALLFINISH010 13mm thick cement and sand backing SR/BL/K/1 1.32 m2 $ 9.98 NA -18% $ 10.80
LABOUR RATES
Labour to Remove the Aluminium
h BI_NORMAL_DAYS001 SR/BL/R/2 2.00 Day $ 55.95 NA -18% $ 91.76
Hangers and Curtain Track (2 men x 1
day)
Signature
Prepared by Rue Ang / FOM
Name/ Appointment
I declare that:**
a. The works quoted above do not involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of a roof over existing walls), CHANGE in building GFA and
earth filling works.
b. The works quoted above involve construction, demolition of buildings/facilities and ADDTIONS / ALTERATION works which result in a CREATION of building (e.g. Construction of a roof over existing walls), CHANGE in building GFA and earth
filling works. Unit had been advised to submit the work request to DSTA FM for processing.
Signature
Confirmed by Rue Ang / FOM
Name of Manager
*Not applicable to items related to systems, facilities and services contracted under PRMS/PMWS
** Delete where not applicable
*** For PMWS repair work where the FSR item includes supply and installation, 10% of the FSR item cost shall be deducted for labour