You are on page 1of 1

PROPOSED EXTENSION OF MIXED-USE COMPLEX ALONG DESAI ROAD

SIDE ELEVATION, INTERIOR ELEVATION & SECTION NOTES:


GENERAL:
-ALL DIMENSIONS ARE IN MILLIMETRES UNLESS
OTHERWISE SPECIFIED.
-DRAWINGS ARE NOT TO BE SCALED. ONLY FIGURED
DIMENSIONS TO BE USED.
-DIMENSIONS MUST BE CHECKED AND VERIFIED ON
SITE AND ANY DISCREPANCIES TO BE REPORTED TO
THE ARCHITECT BEFORE COMMENCEMENT OF WORK.
-CONSTRUCTION TO COMPLY WITH THE LOCAL
AUTHORITY BY-LAWS AND REGULATIONS.

CONSTRUCTION:
-ALL SLABS AT GROUND LEVEL TO BE POURED OVER
1000 GAUGE POLYTHENE SHEET ON 50MM THICK
MURRAM BLINDING ON HARDCORE.
-ALL SOIL UNDER SLAB AROUND AND UNDER
FOUNDATION TO BE POISONED FOR PEST CONTROL.
-D.P.C. DENOTES ONE LAYER OF BITUMINOUS FELT TO
BE PROVIDED ON ALL WALLS 150MM ABOVE
M L K J I H G F GROUND LEVEL.

6 5 4 3 2 1 CIVIL:
-ALL SOIL ON CUT EMBANKMENTS TO BE STABILIZED.
THE SLOPE NOT TO EXCEED THE NATURAL ANGLE OF
REPOSE.
+8,100 +8,100 +8,100 +8,100 STRUCTURAL:
3 Story 3 Story 3 Story 3 Story -300MM DEPTH OF TOP SOIL TO BE REMOVED FROM
pv pv Stair notes: ALL BUILDINGS AND PAVED SURFACES.

750
pv pv pv pv pv pv pv pv pv pv
Plastered wall pv (Reinforced concrete) -FOR ALL R.C. WORK, REFER TO STRUCTURAL
ENGINEER'S DETAILS.
with glossy paint Height to 3rd Floor=
750 -DEPTH OF FOUNDATION TO BE DETERMINED ON SITE
finish 2700 TO STRUCTURAL ENGINEER'S APPROVAL.

1,650
18 risers X 150 -ALL WALLS TO BE REINFORCED WITH HOOP IRON AT
Tread=300 EVERY ALTERNATE COURSE.
+5,400 +5,400 +5,400 +5,400 -ALL ADJACENT R.C. WORK AND MASONRY WALLS TO
BE TIED WITH STRIP IRON AT EVERY ALTERNATE
2 Second Floor 2 Second Floor 2 Second Floor 2 Second Floor COURSE.
High speed roll- pv pv pv pv pv pv
150mm deep rc
MECHANICAL:
up door height - SVP DENOTES SOIL VENT PIPE TO BE PROVIDED AT
2400 beam HEADS OF DRAINAGE SYSTEM.
- DRAINS PASSING BENEATH BUILDINGS & DRIVEWAYS
1,000

TO BE ENCASED IN 150MM CONCRETE SURROUND &


SHOULD BE MINIMUM 450MM BELOW ESTABLISHED
+2,700 +2,700 +2,700 +2,700 GROUND LEVEL DATUM.
1 First Floor 1 First Floor 1 First Floor 1 First Floor - ALL INSPECTION CHAMBERS COVERS & FRAMING
SHALL BE MADE OF CAST IRON.
pv pv pv pv pv pv - MINIMUM SLOPE IN THE DRAINS PIPES TO BE 1:100
- ALL TESTING OF PIPES MUST BE COMPLETED BEFORE
PLASTERING.
- ALL MECHANICAL WORKS MUST BE CO-ORDINATED
WITH ELECTRICAL & ANY CONFLICT MUST BE CLARIFIED
BEFORE WORK BEGINS.
±0 ±0 ±0 ±0
0 Ground Floor 0 Ground Floor 0 Ground Floor 0 Ground Floor
ELECTRICAL:
-ALL CONDUITS MUST RUN ALONG STEEL SECTION
20,400 200mm thick COLUMNS AND BOUND USING BINDING WIRE.

3,900 3,200 2,700 2,500 2,700 2,700 2,700 masonry wall


depth 1000

M L K J I H G F
4,400 3,200 3,000 3,700 4,450
200mm thick rc REVISIONS :
footing on 50mm 18,550
concrete blinding Date: No. Revisions:
E02. SIDE ELEVATION (MWANGI RIIKA CRES) 6 5 4 3 2 1
1:100

S01. BUILDING SECTION


1:100

DRAWING DETAILS:
DRAWING NAME:
Interior Elevation, Building Section

DRAWING ID: SHEET SIZE:


E-02, S-01, E-03 A1
SHEET No.:
3

DRAWING SCALE:
1:100
DRAWN:

M L K J I H G F E D C B A

+8,100 +8,100
3 Story 3 Story
pv pv pv pv pv pv pv pv pv pv pv pv pv pv pv PM DESIGNS©
750

750
pv pv pv pv pv

PROJECT DETAILS:
1,650

1,650
PROJECT NAME:
+5,400 +5,400 PROPOSED EXTENSION OF MIXED-USE
2 Second Floor 2 Second Floor COMPLEX ALONG DESAI ROAD
pv pv pv pv pv pv pv pv pv pv pv
DESCRIPTION: LOCATION:
PLOT LR. 209/2489/44 OFF
STALLS & STUDIO MWANGI RIIKA CRES/
APARTMENTS DESAI ROAD
+2,700 +2,700
1 First Floor 1 First Floor
3,913 3,242 2,701 2,498 2,748 2,748 2,728 2,703 5,247 6,226 3,648 3,257
CLIENT:
pv pv pv pv pv pv pv pv RWATHIA HOUSE TRADING COMPANY
#Client Full Address

CLIENT DATE:
±0 ±0 SIGNATURE :
0 Ground Floor 0 Ground Floor February 2024

3,900 3,200 2,700 2,500 2,700 2,700 2,700 2,700 5,250 6,200 3,650 3,200
41,400

M L K J I H G F E D C B A

E03. INTERIOR ELEVATION


1:100

GSPublisherVersion 0.0.100.100