1.1 Notes
Material Approval Records to include ISO certification and ✓ Sect.1 Part 7.11
2.1 Sect.6 Part 13.1.4
independent testing certificates
Sect.6 Part 13.2.15
As Built Drawings, to include ✓ ✓ Sect.1 Part 7.10.2
- Traffic Signal Layout and Phasing *If as built drawings not
2.2 - Cabling and Ducting Details available shop drawing will
- Location of Equipment submitted to ROMD
- Foundations, inspection chambers, detectors etc.
Inspection and Testing Records ✓ Sect.1 Part 8.7
- material inspection records Sect.6 Part 13.3
2.3 Sect.6 Part 13.4
- inspection requests
- Electrical and earth test results ✓
6b I PCC FCC PC
Material Approval Records, to include supplier/manufacturer ✓ Sect.1 Part 7.11
6b.1
approval for installation contractor Sect.6 Part 7.1.4
As Built Drawings, to include location, type, working width, *✓ ✓ Sect.1 Part 7.10.2
6b.2
post fixing and spacing, transitions *If as built drawings not
available Shop floor
drawings will be
submitted to Asset
Affairs(ROMD)
8a.2
Design Calculations ✓
8a.3 ✓
Design Drawings (to include architectural drawings if any) The
Index should include number of the drawing, revision, title,
filename and location ref. available in pdf & spreadsheet format.
8a.4
Design and Check Certificates
8a.5 ✓
Design Risk Assessments
8b.4
As Built Drawings
✓ ✓ ✓ Sect.1 Part 7.10.2
8b.7 Warranties, to include contact details of manufacturer and ✓ Sect.1 Part 21.1.2 (1a)
local agent, for Part 21.2.2
- Expansion joints Part 7.11.1
- Bearings Part 7.12.1 (2f)
- Parapets
- Waterproofing system
- MSE wall system
- Paint system / protective coating
8b.8 Spare Parts ✓ Sect.1 Part 9.1.10
- list of items taken down from site Part 21.1.2 (1)
- list of new items to be provided to Ashghal
- delivery receipts to Ashghal stores
8b.12 Art Works Sect 1 Part 21.4,
See 71, 7b1-11 in addition to essential requirements (to be Part 7.12.1 (2h)
accomplished by Artist, Contractor, Consultant and PMC (soft and
hard copy). Photos have to be submitted in High resolution (soft copy).
8c Maintenance Documents I PCC FCC
Maintenance Manuals ✓
- Expansion Joints
- Bearings
8c.1 - Parapets
- Waterproofing system
- MSE wall system
- Paint system / protective coating
- Details of any features incorporated to facilitate
maintenance including any recommended
procedures
9a Design Documents
9a.1 Feasibility Study and Investigation Report ✓ ✓
9a.2 Tunnel Operation Risk Assessment Report ✓ ✓
Approval in Principle (AIP) ✓ ✓ ✓
9a.3 - Civil works9
- MEP
9a.4 Detail Design Documents ✓ ✓
9a.5 Tunnel Operational Concept or Operators Guide ✓ ✓
9a.6 Stage 1 Design Certificate ✓ ✓
9b Construction Documents I PCC FCC
9b.1 Material Approval Records ✓ ✓ Sect.1 Part 7.11
9b.2 Shop Drawings ✓ ✓ ✓ Sect.1 Part 7.10.1
Layout drawing clearly indicating the location of the asset to
inspect as per the site condition.
9b.3 As Built Drawings, to include ✓* ✓ Sect.1 Part 7.10.2
- Tunnel Structure and approaches.
- Tunnel M&E systems.
- Tunnel Fire and Life Safety Systems.
- Tunnel ITS systems.
- Tunnel PLC and SCADA systems.
- Tunnel Services Buildings (TSB), Architectural and
Systems.
9b.4 Inspection and Testing Records ✓ ✓ Sect.1 Part 8.7
- material inspection records
- inspection requests
- FAT certificates (including test checklists)
- SAT certificates (including test checklists)
- SIT certificates (including test checklists)
9b.5 Most recent Consultant’s snag list ✓ ✓ ✓ N/A
9b.6 Warranties of all MEP, to include contact details of ✓ ✓ Sect.1 Part 21.2.2
manufacturer and local agent
9b.7 Spare Parts ✓ ✓ Sect.1 Part 9.1.10
- list of items taken down from site
- list of new items to be provided to Ashghal
- delivery receipts to Ashghal stores
9b.8 Construction Stage Photographs ✓ Sect.1 Part 21.7.9