SHE COMMITTEE MINUTES

DOC NO CLIENT EFFECTIVE DATE REV DATE REV APPROVED BY

PROC/SHECOMM/01 ESKOM 17/01/2024 17/01/2025 00 FRANKLIN NGOVE

PROJECT DESCRIPTION REFURBISHMENT OF 8MM HDPE EQUIPMENT DOSING LINE THROUGH


REMOVAL AND REPLACEMENT OF THE DEFECTIVE LINES
PROJECT LOCATION KUSILE POWER STATION
KEY OHS PERONNEL NAME CONTACT DETAILS SIGNATURE SIGNATURE DATE
SECTION 16(2)
SITE MANAGER
DOCUMENT ORIGINATOR ACE MABANDLA 076 041 7671 17/01/2024

Occupational Health and Safety Act No 85 of 1993 as Amended


SHE COMMITTEE MINUTES

1. MATTERS ARISING FROM PREVIOUS MINUTES Action Completion


by Date

2. HEALTH & SAFETY REPRESENTATIVES DEVIATION


REPORT

Page 1 of 2
Page 2 of 2