OTIS-FOD CHINA Gen2 and Gen3 Dwg : HAA25DR4

FIELD ENGINEERING Date : 28/06/2020


CHINA
630 - 2000 KG Page : 38/42

004 - INSTALL CAR FRAME, ROPE CLIMBER AND REMOVE TOP FLOOR
FIM WORKING PLATFORM
Remove top floor working
4.7
platform

1. Remove top floor working platform


After completing the installation of rope climber and safety test for the running platform, remove the
top floor working platform.

Safety warning!
Platforms, disassembled either outside or inside of hoistway must incorporate the use of Life Lines as a
fall arrest system, refer to WWJSSS 4.3.D.

1.1 Remove the kick plates and guardrails of upper deck

1.2 Remove the footboards and ladder of upper deck

GEN2MRL_HZ_FIM_EN Unpublished Work Copyright © OTIS Elevator Company 38


OTIS-FOD CHINA Gen2 and Gen3 Dwg : HAA25DR4
FIELD ENGINEERING Date : 28/06/2020
CHINA
630 - 2000 KG Page : 39/42

004 - INSTALL CAR FRAME, ROPE CLIMBER AND REMOVE TOP FLOOR
FIM WORKING PLATFORM
Remove top floor working
4.7
platform

1.3 Remove the platform beams and support brackets of upper deck

1.4 Remove the middle support brackets of upper deck

GEN2MRL_HZ_FIM_EN Unpublished Work Copyright © OTIS Elevator Company 39


OTIS-FOD CHINA Gen2 and Gen3 Dwg : HAA25DR4
FIELD ENGINEERING Date : 28/06/2020
CHINA
630 - 2000 KG Page : 40/42

004 - INSTALL CAR FRAME, ROPE CLIMBER AND REMOVE TOP FLOOR
FIM WORKING PLATFORM
Remove top floor working
4.7
platform

1.5 Remove the steel channel (Or angle iron) at the front end of lower deck

Structure 1 Structure 2

1.6 Loosen but don’t remove the bolts of the lower deck braces

GEN2MRL_HZ_FIM_EN Unpublished Work Copyright © OTIS Elevator Company 40


OTIS-FOD CHINA Gen2 and Gen3 Dwg : HAA25DR4
FIELD ENGINEERING Date : 28/06/2020
CHINA
630 - 2000 KG Page : 41/42

004 - INSTALL CAR FRAME, ROPE CLIMBER AND REMOVE TOP FLOOR
FIM WORKING PLATFORM
Remove top floor working
4.7
platform

1.7 Remove the footboards in turns from the front end to the first angle iron, then remove the first
angle iron and the other footboards

1.8 Remove the“L” bracket.

GEN2MRL_HZ_FIM_EN Unpublished Work Copyright © OTIS Elevator Company 41


OTIS-FOD CHINA Gen2 and Gen3 Dwg : HAA25DR4
FIELD ENGINEERING Date : 28/06/2020
CHINA
630 - 2000 KG Page : 42/42

004 - INSTALL CAR FRAME, ROPE CLIMBER AND REMOVE TOP FLOOR
FIM WORKING PLATFORM
Remove top floor working
4.7
platform

1.9 Remove the connection bolts of lower deck plank and support beams, and then pull the plank out
from hoistway. Remove the second angle iron and support beams finally.

1.10 Recover the entrance protection of top floor

GEN2MRL_HZ_FIM_EN Unpublished Work Copyright © OTIS Elevator Company 42