DG KHAN CEMENT COMPANY LIMITED

HUB PROJECT

IZHAR CONSTRUCTION PVT LTD

Proposal For Concrete Pour At Raw Meal Silo


(341) Pile Cap

Doc. No Rev Description Pages Date Prepared By Checked By Approved Status


By
RMS-Pour 0 Proposal For 8 2-6-2016 Aneel Faisal For
Plan-01. Concrete Pour Kumar Laeeq Approval
At Raw Meal
Silo (341) Pile
Cap

1|Page
Options For Concrete Pour At Raw Meal Silo Pile Cap

OPTION 1

• Concrete will be poured by dividing the pile cap in three sections of 1m


each
• Each section will be of 1000 m3 (Approx.) concrete in layers.
• Each succeeding layer within each sectional pour will be restricted to time
span of 60 minutes to avoid the formation of cold joints.
1m
1m
1m

LEAN
OPTION 2
• Concrete will be poured by dividing the pile cap into two sections.
• The sections will be of 2 meter and 1 meter as shown below.
• Each succeeding layer within each sectional pour will be restricted to time
span of 60 minutes to avoid the formation of cold joints .
• 2000 m3 (Approx.) and 1000 m3 (Approx) of concrete will be poured in
sections of 2m and 1m respectively.
1m
2m

LEAN
Pour Plan
• The concrete quantity of the pile cap structure is approximately 3200 m3
(Approx.)
• It will be done by three dedicated teams.
• Three stationary pumps will be deployed as mentioned
• Total 14 transit mixers will take part in the pouring activity
• 4 batching plants will be in operation and will supply concrete volume of
60-90 m3/h
• Two mobile pumps will be on stand-by mode and during the activity and
will be used as per requirement.