JSA For Lifting of Equipments - Material
JSA For Lifting of Equipments - Material
HUB PROJECT
1|Page
Options For Concrete Pour At Raw Meal Silo Pile Cap
OPTION 1
LEAN
OPTION 2
• Concrete will be poured by dividing the pile cap into two sections.
• The sections will be of 2 meter and 1 meter as shown below.
• Each succeeding layer within each sectional pour will be restricted to time
span of 60 minutes to avoid the formation of cold joints .
• 2000 m3 (Approx.) and 1000 m3 (Approx) of concrete will be poured in
sections of 2m and 1m respectively.
1m
2m
LEAN
Pour Plan
• The concrete quantity of the pile cap structure is approximately 3200 m3
(Approx.)
• It will be done by three dedicated teams.
• Three stationary pumps will be deployed as mentioned
• Total 14 transit mixers will take part in the pouring activity
• 4 batching plants will be in operation and will supply concrete volume of
60-90 m3/h
• Two mobile pumps will be on stand-by mode and during the activity and
will be used as per requirement.