Professional Documents
Culture Documents
Vision Corporation Construction Terms
Vision Corporation Construction Terms
Table of Contents
I. Definitions
(1) By the General Conditions, 4.15, which has been approved by the Owner, OR
(2) By the Invitation to Bidders, which has been approved by the Owner.
2. Architect
The Architect for the Project (as defined in Article 2 of the General Conditions) is [@ Architect Name @] whose
address is [@ Architect Address @].
1. Contract Sum
a. Provided that the Contractor shall strictly and completely perform all of its obligations under the Contract
Documents and subject only to additions and deductions by Change Order as provided in the General Conditions;
Owner shall pay to Contractor, at the times and in the installments hereinafter specified, the sum of $ [@ Contract
Sum @] (such sum being herein­after called the "Contract Sum"), to cover Contractor's profit, general
overhead and all costs and expenses of any nature whatsoever incurred by the Contractor in connection with the
performance of the Work, including, but not limited to, all overtime, shift work, weekend, and holiday work not
otherwise requested by Owner.
b. Payments will be made as provided hereafter with ten percent (10%) retainage being held from each payment,
which retainage may include an amount to insure payment of Contractor's Federal and State withholding tax
obligations. The retainage will be released within thirty (30) days after acceptance of the Work by the Owner and
submission to Owner of all forms and plans required by Contract Documents, subject to any right of setoff as
provided for elsewhere in the Contract Documents
c. Included in the Contract Sum is the amount of One Thousand Dollars ($1,000.00) in consideration for those
provisions contained in the Contract Documents which provide for indemnity, hold harmless and/or guarantee to
Owner, the Architect and affiliated companies of each, as well as the officers, agents and employees of each,
whereby any such person is granted indemnification from liability for damages to persons or property caused in
whole or in part by an act, omission or default of the Contractor or Contractor's subcontractors, material suppliers
or employees arising from the Contract or its performance. The said consideration for such indemnification is paid
to the Contractor by Owner on behalf of Owner, the Architect, related and affiliated companies of each of the
foregoing, and the officers, agents and employees of each of the foregoing, and is allocated to and shall be deemed
to have been paid out of the first installments of the Contract Sum payable hereunder.
d. Additional Work, unit prices: Any additions or deletions from the Contract Price shall be calculated on the cost
of the Work plus appropriate percentages; such sums shall not exceed the guaranteed maximum prices set forth,
which shall be good for the duration of the project. The unit prices set forth are fully burdened rates inclusive of
payroll taxes, insurance, overhead and profit.
e. Additional Work: The Contractor agrees that a single percentage for the overhead and profit of items not
defined by unit prices, shall be applied on additional and/or extra work required to be performed by:
(1) Contractor's own forces - 15% for overhead and profit
(2) Contractor's subcontractors - 10% for overhead and profit on subcontracted work. General Contractor -
10% for overhead & profit.
f. Omitted Work: The Contractor agrees that a single percentage for its overhead and profit of items not defined
by unit prices, shall be applied on omitted work originally required to be performed by:
(1) Contractor's own forces – In a percentage as determined from Contractor's actual Overhead & Profit as
established in the Contract Documents.
(2) Contractor's subcontractors - In the percentage as set forth in paragraph 'E' above.
g. Owner, at its sole option, may pay any amounts owing to Contractor under this Agreement by means of joint
checks drawn jointly in favor of Contractor and any person furnishing any labor, materials, equipment, tools,
machinery, supplies or transportation in connection with the Work. Any amounts so paid shall be deducted from
any amounts owing to Contractor under this Agreement.
h. To the extent not otherwise specifically identified in writing pursuant to the Notice provisions of the Contract
Documents, the acceptance by Contractor of any payment shall operate as, and shall be, a release of Owner from
all claim and liability to Contractor for anything done, or furnished for, or relating to, the Work, or for any act or
neglect of Owner relating to or affecting the Work hereunder through the date of acceptance of said payment.
i. Owner shall have the right to withhold an amount equal to two (2) times the estimated cost of all incomplete or
defective Work or disputed claims until such time as the incomplete or defective Work is corrected and accepted by
Owner or the claims are resolved to the Owner's satisfaction.
j. No payment by Owner shall be construed as performance by Contractor of this Agreement, either in whole or
in part, nor shall it be construed as an approval or acceptance of defective Work or Work failing to comply with this
Agreement, or of any items in any requisition made or bill rendered; further, no payment by Owner shall constitute
a waiver of any of Owner's rights under the terms of any applicable guarantees or with respect to unsettled liens.
k. The Contract Sum may be increased only by written change order signed by both parties hereto with the same
formality as the signatures below. The Contract Sum is intended to include all increases in cost, foreseen or
unforeseen, including, without limiting the generality of the foregoing, taxes, labor, materials, and transportation
costs, all of which are the sole responsibility of Contractor.
3. Payment
a. Based upon the Contractor's Application for Payment pursuant to the General Conditions, Owner shall make
progress payments to the Contractor on account of the Contract Sum, less ten percent (10%) retainage, except for
final application to which paragraph 'b' shall apply. Such payments shall be mailed on or before thirty (30) days
after receipt of Contractor's Application for Payment; provided, however, that Owner shall have no obligation to
make payment as aforesaid if Contractor does not submit to Owner, with its Application for Payment, a schedule
of values, partial release of liens (on owners form only) and such documents to substantiate the amount owed as
Owner may reasonably require.
b. Final payment, constituting the entire unpaid balance of the Contract Sum shall be paid by Owner to the
Contractor within thirty (30) days after acceptance of the completed Work by the Owner and submission to Owner
of all forms and plans required by the Contract Documents. "Completed Work" as used herein shall mean
completion of all Work including those items on the punch list.
c. Contract Sum Breakdown: For the purpose of progress payment, a schedule of values must be submitted to the
Owner within ten days (10) of receipt of Contract and approved by Owner, to include cost of materials, freight,
installation. The contract sum breakdown must be provided on the Owner's approved form.
Owner may, at its option, cause such corrective work to be done by others and charge the Contractor with the cost
thereof.
The warranties stated herein are in addition to all manufacturers' warranties received by Contractor and warranties
implied by law. No provision in the contract will be held to limit the scope or length of the warranties stated herein
or otherwise limit the Owner's right to seek remedies for warranty claims within applicable limitation of actions
periods.
4. Other Provisions
a. All Change Orders to the Contract Documents, including the Drawings and Specifications must be approved, in
writing, by the Owner's Project Manager.
b. The Owner has submitted building plans to necessary governmental agencies for review and approvals.
Contractor shall assist Owner to cause building permits to be issued in Contractor's name.
c. Contractor agrees it shall be responsible for recording a Notice of Commencement in the Public Records of the
County in which the project is located in those states requiring same. Owner shall prepare and forward to
Contractor the completed Notice of Commencement, together with any attachments required by law. In the event
the Contractor fails to properly and/or timely record the Notice of Commencement, Contractor shall indemnify
and hold harmless Owner, its parent company, its subsidiary, related and affiliated companies, and its officers,
agents and employees, from and against any and all claims, damages, losses and expenses whatsoever, including
attorney's fees at all trial and appellate levels and all arbitration and mediation proceedings arising directly or
indirectly out of or resulting from the Contractor's failure to fully perform its obligations herein.
d. Contractor does ( ) /does not (X) qualify as a minority contractor under Federal Law.
e. In the event Owner is leasing the real property or space where the Work is to be performed, any provisions of
the Owner's lease pertaining to or controlling the Work shall be included in the Specifications (Division 0), labeled
"Lease Provisions", and incorporated herein by reference. Contractor shall be responsible to abide by all
obligations of Tenant or Lessee (as the case may be) contained in the Lease Provisions which pertain to or control
the Work.
f. In the event the Contractor chooses not to utilize the schedule form outlined in the bid documents by the Owner
, two (2) copies of the approved construction schedule with an equivalent duration or less is to be provided by the
Contractor to the Owner along with the executed Contract. A Certificate of Insurance is also to be provided with the
Contract.
g. The Contractor will provide the Owner with a certified foundation location survey by no later than submission
of the second Application for Payment.
h. Any legal notices to owner shall be sent to the address on page one of this contract; ATTN.: Construction
Department with a copy to the same address, ATTN.: Law Department.
i. The Contractor agrees that he will not, without the prior written approval of the Owner, (a) publicize the fact
that the Owner has entered into this Agreement, or (b) disclose, confirm or deny any details of this Agreement. The
Contractor agrees that he will not use the Owner's name in connection with the Contractor's publicity with
respect to the Project without the prior review and written approval in each instance by the Owner. The Contractor
shall also insert the terms of this provision in all contracts and/or agreements executed in connection with the
services to be performed under this Agreement and shall pass such provision to his subcontractors under such
contracts and/or agreements.
j. Notwithstanding the fact that this Agreement is executed as of the date first set forth above, the parties recognize
that a portion of the Work may have been performed prior to such date, all of which Work shall be governed by the
terms and conditions of the Contract Documents and shall be deemed to be a part of the Work. Contractor shall not
be entitled to any compensation for such prior activities and services except as expressly provided herein. Without
limiting the foregoing, all of Contractor's liabilities and obligations to Owner hereunder shall apply to all work and
services provided by Contractor for the Project prior hereto, notwithstanding the fact that such work or services
may have been performed prior to the date hereof pursuant to prior negotiations, representations, agreements,
understandings or otherwise.
k. Each party hereto acknowledges that (1) each party hereto is of equal bargaining strength, (2) each such party
has actively participated in the drafting preparation and negotiation of this Agreement, (3) each such party has had
the opportunity to consult with such party's attorneys and advisors relative to entering into this Agreement, and (4)
any rule of construction to the effect that ambiguities are to be resolved against the drafting party shall not apply in
the interpretation in this Agreement, any portion hereof, any amendments hereto, or any exhibits attached hereto.
Signatures
Buyer Supplier
Name Name
(Title) (Title)
(Date) (Date)