Professional Documents
Culture Documents
1. Project HSE Plan C-21007 (Rev. 0)
1. Project HSE Plan C-21007 (Rev. 0)
PROJECT MANAGER
REVIEWED BY,
SITE MANAGER
PREPARED BY,
TABLE OF CONTENT
NO DESCRIPTION PAGE
COVER 1
TABLE OF CONTENT 2
1 INTRODUCTIONS 3
2 PURPOSE 3
3 SCOPE 3
4 DEFINITION 3
5 REFERENCES 6
6 LEADERSHIP AND COMMITMENT 6
7 RISK MANAGEMENT 13
8 MANAGEMENT OF CHANGE 14
9 PREMOBILIZATION MANAGEMENT 14
10 SUBCONTRACTOR MANAGEMENT 15
11 TRANSPORTATION MANAGEMENT 18
12 HEALTH MANAGEMENT 19
13 ENVIRONMENTAL MANAGEMENT 22
14 OPERATING PROCEDURE AND SAFETY STANDARD 24
15 TRAINING AND COMPETENCY 45
16 COMMUNICATION 46
17 STOP WORK AUTHORITY 47
18 EMERGENCY RESPONSE PLAN 47
19 INCIDENT INVESTIGATION 49
20 HSE INCENTIVES AND CONSEQUENCES 51
21 PERFORMANCE EVALUATION 52
1. INTRODUCTION
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 3 OF 54 0
This HSE Management Plan for reference Project information containing the information
as the following:
The scope of work for this project and further detail shall refer to the contract and
client’s technical specification.
Any specific scope of work or additional job is included in another section.
HSE details of scope of work shall accompany this HSE management plan for reference.
2. PURPOSE
2.1 To provide the guidance to project management team in preparing project HSE
plan (PHSEP) as a general overview of project HSE preparation and planning
which shall be applied and implemented at the project, to determine and ensure
that all of HSE activities are in accordance with and under controlled of internal
company needs and complying client HSE requirements.
2.2 The importance and essence of this PHSEP is for guidance, monitoring and
controlling of HSE in construction preparation stage and operation stage, in
accordance with appearing high performance and teamwork coordination internally
within project management and corporate management.
2.3 The PHSEP is containing of Health, Environment and Safety work planning
correlated with scope of work and typical of the project and client requirements.
3. SCOPE
This Project HSE Plan (PHSEP) shall be implemented by PT. Koin Konstruksi.
5. REFERENCE
5.1 HSE Management System PT. Koin Konstruksi No. P-HSE-001
5.2 Guidelines for Established Project HSE Plan No. P-HSE-011
5.3 Safety Handbook PT. Koin Konstruksi
RESPONSIBLE
LEADING INDICATOR TARGET REMARKS
PERSON
RESPONSIBLE
LAGGING INDICATOR TARGET
PERSON
Fatality 0 (zero fatality) HSE
Incident Frequency Rate Max 10 per 1 million manhours HSE
Incident Severity Rate Max 10 per 1 million manhours HSE
Nearmiss Frequency Rate Max 5 per 1 million manhours HSE
Environment 0 (zero spill) HSE
3. Site HSE Manager in carrying out his duties at the site is assisted by HSE
Coordinator, Environment Officer, HSE Inspector and HSE Supervisor.
4. HSE Organization Chart
PROJECT
SITE
MANAGER
SITE HSE
MANAGER
HSE HSE
SUPERVISOR SUPERVISOR
SAFETYMAN SAFETYMAN
9. Serves as liaison for PT. Koin Konstruksi with governing agencies and
other groups in related to HSE requirements.
10. Participates with the Engineer in making a pre-job HSE hazard
analysis prior to the commencement of the job, this involves regular
visits to the project.
11. Checks on the use of all types of personal protective equipment,
evaluated their effectiveness, and suggest improvements where
indicated.
12. Conducts independent audits to observe conformance with established
HSE program and determines the effectiveness of individual elements
of the program.
13. Establish good relation and coordination of incident prevention
activities with client and subcontractors.
14. Review all investigative reports, providing instructions and guidance
as needed to maintain flow of accurate, complete and prompt
reporting of all types of incidents.
15. It is primarily the duty of the Site HSE Manager to see that the best
possible medical arrangements are made at the start of each job and
to ensure all governmental insurance are prepared, distributed, and
maintained in a proper manner.
16. Establish written HSE emergency procedures for the project.
7. RISK MANAGEMENT
7.1 HIRADC
1. To describe the measures to be implemented within PT. Koin Konstruksi
project for identification of hazards, and for the assessment and control of
HSE risks.
2. Methodology of identification HSE aspect and risk assessment should be
made by consider scope of work, government regulation, standards and
contract agreement.
3. Engineer, supervisor and subcontractors should make Hazard identification,
risk assessment and determining control (HIRADC) for all job (routine/non
routine).
4. Site HSE Manager and Site Manager at Project together with HSE Manager at
Head Office are responsible to ensure the conformity of HIRADC with all
project activities prior to project starting.
5. Site HSE Manager shall monitor and evaluate the implementation of risk
control operation as follow:
a. Taking improvement action whenever required or when any
deviation/incident are detected;
b. Prepare the determining control implementation report and
submitted to Project Manager as an input to Management Review Meeting
at Project.
2. JSA will be required for all jobs performed On or Off site. Construction
Engineer/Superintendent or Supervisor shall be responsible to provide JSA
and understood by all the work team member. HSE are responsible to review
the JSA. Normally during daily Tool Box Meeting (TBM). Employee shall sign
the JSA Attendance list and involving in any review of activity change. New
hazard identified in JSA shall be add on HIRADC register.
3. As minimum JSA shall described breakdown steps for the task and hazards
identified for each step including control measures
8. MANAGEMENT OF CHANGE
8.1 MOC is required to provide a documented process for managing change in order to
achieve an acceptable level of risk. Change can be imposed from external and/or
internal drivers and can occur quickly or over a long period of time. Whatever form
change takes, it must be properly managed at the appropriate level so that
unwanted risks do not evolve.
8.2 Change can be broadly defined as an alteration or modification, replacement,
addition, revision or deletion to any aspect of Contractor’s operations, systems or
business. However, change as it applies to this plan is limited to impacts on
personal health & safety, environmental harm, and regulatory compliance
8.3 Once a change or a need for future change is identified, it is necessary for that
change to be managed by the appropriate person which will be guided by the
associated risk assessment as to whether the proposed change(s) represents an
acceptable level of risk.
10.2 HSE plan shall show in the structure of time schedule, clear and understandable,
the following items are mandatory;
1. HSE and Security Induction/orientation program for all employees.
2. Group Toolbox Meeting.
3. Line Supervisor Safety Meeting
4. HSE Inspection
5. Emergency Procedure
6. Reward & Punishment
7. HSE Training
8. HSE / Accident Investigation and Reporting
9. Safety Campaign
10. Construction Equipment, Tools & Machinery Inspection
10.3 PT. Koin Konstruksi held authority to develop changes in the subcontractors HSE
plan.
2. System shall involve all staff and employee to enable continues improvements
to the subcontractor employee capability to have an overlook to any
substandard condition and or practices.
3. Whenever it is necessary, PT. Koin Konstruksi is entitle to issue suggestions
based on the subcontractor needs and direct /actual findings.
10.11 Project Manager, Procurement Manager and Construction Manager shall ensure
that all bidders for subcontracting passed PT. Koin Konstruksi & Client CSMS
(Contractor Safety Management System).
10.12 Site Management or Client may sometimes conduct an audit to Subcontractors
by prior appointment arrangement. This audit will be carried out at least 7 days
prior notice, and can be done at Subcontractors Home Office or Project Office
agreed. The results of this audit will be determined as a reference for
Subcontractors CSMS score validity.
10.13 Subcontractor shall provide their employees with proper equipment and skill
certification from relevant authorized government institution, provide adequate
work tools and provide all required personal protective equipment as required in
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 19 OF 54 0
the government rules regulations and applicable industrial standard both national
and international.
10.14 All Subcontractors and outsource parties that contribute directly with
Contractor is obliged to provide health/safety and employment insurance facility
to workers, both individually and in groups.
when it is safe to use, safely park the vehicle, and then use their mobile
telephone.
11.12 Drivers will not operate project vehicles at any time if they are under the
influence of drugs and/or alcohol.
11.13 In cases where driving ability may be impaired due to taking medication, driver
will not be allowed to operate vehicles. (Where possible, reasonable
accommodations shall be provided).
11.14 Personnel will not drive their private cars around the construction area.
11.15 Scheduled maintenance (by dealers, project mechanics or other certified
facilities) shall cover critical parts and equipment such as brakes, steering
systems, windshield wipers, brake lights, headlights, tires, etc.
11.16 Seat belts shall be utilized on all project vehicles as designated by vehicle safety
equipment requirements
11.17 Seat belts must be worn at all times by both the driver and all passengers when
the vehicle is in motion. Driver must not proceed until all passengers have
fastened their seat belts.
11.18 Employees should not set out on any journey in adverse weather conditions
unless absolutely necessary and then only after the appropriate approval has
been granted
11.19 The multiple transports of employees shall be carefully considered due to the
potential for catastrophic loss of project personnel in the event of an accident. A
project specific risk assessment shall be undertaken and used to develop a set of
guidelines for the drivers regarding all possible risk scenarios and associated
areas of mitigation and control.
All workplace environments must be hygienic and safe for employees and
visitors. This applies to all, not just the workplace involved in handling
personal food and products.
A solid workplace hygiene policy is the best way to ensure that employees
maintain a clean workplace.
Basic hygiene in the workplace can be put down to four different things:
personal hygiene; work area cleanliness; clean restroom facilities; and a clean
kitchen.
2. Fatique Management
Fatigue control strategies should be prepared by supervisors to minimize risks
associated with fatigue in the workplace
Enforcing procedures if performing moderate to very high risk work during
periods of high fatigue
Considering job rotation and scheduling (including time of day), for repetitive
or monotonous work, or work that involves heavy physical exertion
12.6 Housekeeping
1. Housekeeping practices and clean-up of all project facilities will be
maintained by construction team
2. The work area shall be maintained to a high standard of cleanliness, and
supervisors will be expected to review and rectify their respective work areas
as required on a daily basis.
3. Waste material shall not be burned in site and shall be segregated when
disposed of in the bins.
• Reactive
• Toxic
• Infectious
• Corrosive
• Poisonous
PT. Koin will ensure following requirements are implemented to manage waste of
hazardous chemical:
• Symbol and label shall be affixed on the hazardous chemical waste containers.
• The condition of the hazardous waste container/drum shall be inspected on a
daily basis.
• Containers intended for hazardous waste disposal should not be used for other
purpose.
• The waste should be kept at a proper temporary hazardous waste storage not
more than 90 days.
• The hazardous waste temporary storage should be provided with
license/permit from authorized body.
• PT. Koin will provide third-party (who have license) to handle hazardous waste.
• Transfer of all hazardous wastes to a third-party should be accompanied by
manifest/document hazardous waste. Copies of document hazardous waste
should be maintained.
• Hazardous waste temporary storage shall comply with applied regulation and
shall be equipped with Fire extinguisher, PPE and spill kit equipment.
• Basic waste management training periodically will conduct and must be followed
by personal who involved with waste of hazardous chemicals.
• Waste such as empty containers or drums with residue of flammable liquid
should be stacked in isolated area away from building and installation. Have
notice displayed forbidding smoking or naked lights. These containers should be
thoroughly steam- cleaned or washed before use.
2. Non Hazardous Waste: Includes untreated lumber, garbage, solid sewage waste,
scrap metals, and other waste not designated as hazardous by AMDAL, RKL
standards.
Non hazardous waste shall be moved to the designated waste collection area, where
it shall be segregated
3. Waste Segregation.
Given the complex nature of the waste expected on the project, waste segregation
shall be implemented involving sorting and separating waste on the basis of its
characteristics.
Waste materials shall be segregated at source by providing marked (with universal
symbols and writing in English/Bahasa Indonesia) bins for storing the waste as
follows:
a. Hazardous wastes.
b. Organic.
c. Non organic.
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 24 OF 54 0
Bins shall be labeled with labels, which clearly describe in English, Indonesian, and
International symbols, the types of waste and the precautions when handling the
waste.
Bins shall be placed in offices, constructions project, mess centers, and clinics. No
waste collection bin shall be allowed to overflow before it is emptied, and waste
storage receptacles shall be replaced promptly, in the event damage.
A sufficient number of bins shall be placed for each type of waste at waste collection
points, depending on the variety and quantity of the wastes expected from the
location.
HSE bins shall be placed and emptied in an effective and timely manner in the
various the waste disposal areas.
Waste
Explosive, Flammable,
Reactive, Poison,
Listed on Infection, Corrosive,
table Toxicology
Yes
No
B3 Waste
Non B3 Waste
Collection, Temporary Storage
Documentation, Symbol / Label /
Inventory Non B3
Waste
Transportation
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 25 OF 54 0
B3 Waste Transportation
(Third Party)
Dispose off at
Dispose off at B3 Waste Treatment Facilities waste landfill
(Third Party)
Table 1
13. When a crane is parked and left unattended overnight, the crane
will be secured in a manner that prevents unauthorized startup,
operation, or movement of the machine.
14.2.2 Storage.
1. Cylinders must be stored on a upright (standing) position and tied or
otherwise made secure.
2. Cylinders should not be stored near highly flammable substances.
3. Do not store cylinders near aisles, or in locations where moving
objects may strike or fall on them.
4. Cylinders containing acetylene should always be stored in a separate
group, never with store together with oxygen cylinders.
14.2.3 Usage.
1. Never mix gases in a cylinder.
2. Never attempt repairs to valves or gauges, return them to the
Maintenance Department.
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 31 OF 54 0
3. All confined spaces activities must be risk assessed. The identified control
measures by the JSA have to be reviewed and fully implemented on the
field prior to work commencing.
4. The following signage “CONFINED SPACE – PTW REQUIRED FOR
ENTRY”shall have posted at all site confined spaces entrance
5. Prior entering a confined space, gas testing must be conducted. The gas
testing equipment shall have a valid certificate of calibration and checking
by a certified third party for the parameters oxygen, carbon monoxide,
flammable gases and toxic gas
6. The gas testing shall be undertaken at least once per shift and/or at the
frequency specified in the PTW form
7. All basic PPE applicable on site and all specific PPE identified during the
JSA shall be provided before work is started
8. Ventilation (by either natural or mechanical means) is necessary and has to
be installed prior to work commencing. There are some particular places
(e.g. excavations, big diameters open tanks, etc.) which forced ventilation
is not necessary. The JSA will establish more precisely if ventilation is
required or not and it will be mentioned on the PTW
9. A minimum one stand-by man has to be designated for one confined space
activities
10. This person can be a part of the working team, but his duties must not take
him away from the vicinity of the entry of the confined space to control the
entrance workers in a confined space
11 Prior to work commencing, during the JSA, all the required means access
must identify.
12. The access will have to consider that all have to be suitable for emergency
evacuation. All platforms have to be dimensioned to accept a stretcher or a
winch and the people around these rescue means
13. Electrical earthling in the confined space will be done to prevent
electrocution by a faulty electrical tools or wire and by a discharge of
electrostatic charge resulting from the functioning of forced ventilation or
grit/sand blasting operations.
14. All possible ignition sources will bel be removed from the immediate area
where the installation or application of flammable or combustible
substances is required within the confined space.
15. Adequate fire protection means suitable to the risk(s) involved will be
provided for all confined spaces work locations.
16. During any hot works activities (e.g. welding, cutting, grinding, etc.) there
will be sufficient artificial air movement installed at entrance/exit points to
ensure fumes, etc. are forced out of the confined space and breathing air is
continuously replenished. In some cases, local exhaust may be required to
directly remove fumes.
3. All lamps shall be of industrial type and shall only be used for their intended
purpose (e.g. lamps to be mounting on walls/sealing shall not be used as
ground floor lamps). All lamps shall be suitably installed.
4. Lamps to be installed at Flammable Chemical Storage area shall have
explosion protection.
5. Extension Cables shall be of industrial type complying with IEC. For
application in hazardous area, appropriate equipment shall be used (e.g.
explosion protection).
6. Cable Management (Cables shall be buried where practicable or laid in such
a way that they do not create slip/trip hazards)
7. All electrical equipment and cables should be protected from the risk of
damage from mechanical shock
8. The generating set shall be equipped with an output circuit breaker,
overcurrent, overload, earth fault protection and Residual Current Device /
GFCI (having a rated residual operating current not exceeding 30 mA).
9. The generator and associated equipment shall conform with Applicable
Laws and standards relating to electrical installations and electrical safety.
10. All electrical connections to the generator shall be affected and certified by
a qualified electrician.
11. Grounding for Generator set, Welding Transformer etc.
12. Temporary lighting will be install when work site activities are scheduled to
take place during darkness
13. Temporary lighting brightness shall be sufficient to allow for safe working
conditions at the work site and at access routes and passageways.
7. Damaged or defects tools should not be used and removed from site.
Reinspection should be done for these tools after repair.
8. Daily checks shall be done by tools user to ensure that tools is in good
condition and safe.
9. Always use appropriate tools for every job. Do not use improvised or
modified tools
10. Non-spark, explosion proof or intrinsically safe tools are mandatory to be
used at several hazardous or flammable area.
11. Impact surfaces of tools including, but not limited to, hammers, wrenches,
drift pins, chisels must be kept free of mushroomed heads.
Before turning off the power, the Authorized Employee shall notify Affected
Employees in the work area that power will be shut off, the reason for the
shutdown, and that the equipment will be locked/tagged out.
4. Shutdown Equipment
The equipment/machine shall be shut down by the normal stopping
procedure. When appropriate, a “DO NOT OPERATE” tag shall be affixed to
the power switch.
5. Isolate Equipment
The equipment/machine shall be de-energized, secured and isolated form
hazardous energy sources. An orderly shutdown must be utilized to avoid any
increase of additional hazards to employees.
6. Lockout/Tag out
The Authorized Employee shall place locks and/or tags in the appropriate
energy isolating locations.
7. Release Stored Energy
After lockout devices have been placed on the equipment, all stored
electrical, gravitational, mechanical, and/or thermal energy must be
disconnected and drained to a zero-energy or otherwise made safe by
blocking or repositioning of equipment. This can be accomplished by:
a. Releasing pressure lines such as hydraulic, air, steam. gas, and water;
b. Release spring-loaded equipment;
c. Blocking mechanical equipment with moving, rotating, or elevated parts.
8. Verify Isolation
Before performing maintenance on the machine, the Authorized Employee
verifies the system is isolated. This is generally accomplished by first
establishing that no personnel are exposed and then turning the machine
switch to the ON position using normal operating controls. Verification of
isolation must be continued if there is a chance of the re-accumulation of
stored energy during the service/maintenance activity.
9. Perform the Service/maintenance Activity
Service or maintenance activities can be perform after verification of isolation
2.
When additional equipment is necessary for the safe performance of
assigned work, it shall be requested when not available in stock or issued
from the warehouse on the request of Supervisor’s and HSE Officer
authorized signature.
3. The Supervisors/Superintendent with assistance of Project HSE Officer shall
determine the type[s] of personal protective equipment required for the
job.
4. Description of minimum requirement of Personal Protective Equipment
(PPE);
Refer to the UU No. 1-1970 regulated regulations and corporate policy, type
and specification of Basic Personnel Protective Equipment, as follows:
a. Hard hat
b. Safety Glasses
c. Safety shoes/rubber boots with toe cap
5. Additional Personal Protective Equipment will be considered depend on
work activity.
6. Recording of PPE Distribution:
a. All PPE released from warehouse should be acknowledged and
approved by concerned Line Supervisor and Project HSE Officer.
b. Project HSE Officer should be recorded and documented the request in
order to keep correctly update PPE distribution data to monitor loss
control. This responsibility and authority shall be regulated in form of
field work instruction.
b. Project HSE administrator shall develop written instruction subject to
monitor the PPE requisition, ordering, receiving, storage, and
distribution. This shall be done in coordination with project Warehouse
Section.
c. Those PPE is mandatory and shall be worn at all times at project.
Mandatory signs to remind all personnel shall be placed at assigned
locations where PPE is mandatory to avoid any injury to person.
d. Additional equipment and similar safety items may be required
depending on the nature of the work and the work area involved.
e. When the possibility of loose particles or flying projectiles exists, proper
safety protection devices shall be worn.
14.14 Pneumatic Tools
1. Pneumatic tools include Chippers, Drills, Hammers, and Sanders. Pneumatic
power tools shall be secured by proper clamps and whip checks.
2. In addition to mandatory PPE, eye protection (goggles) or a face shield (with
safety glasses or goggles), and hearing protection are required for working
with pneumatic tools.
3. Pneumatic tools may be used only by employees who are properly
instructed and familiar with these tools.
4. Employees must follow safe practices for operating pneumatic tools, including
the following:
1. Before assembling the system, check all hoses for cuts, breaks, and loose
connections.
2. Blow out all hoses before hooking up the equipment. If the connector has
a rubber seal.
Remove it before (and replace it after) blowing.
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 42 OF 54 0
3. When possible, run air lines through areas with little traffic. If possible,
avoid laying lines across roads. Protect air lines or hoses against trucks
and pedestrians either by building runways over the hose or suspending
the hose overhead with the lowest part of the hose at least 7 feet (2
meters) above the ground.
4. Tighten hammer-joint connections with a hammer. Do not tighten them
by hand. Hoses equipped with special connections require special
tightening techniques or equipment. One example is hammer-union
connections, which must be tightened with a hammer. Another example
is spanner-wrench connections, who must be tightened with a spanner
wrench. Do not tighten these connections by hand.
5. Do not turn on air valves until the hose connections are secure.
6. Do not point an open-air hose at anyone.
7. Compressed air shall not be used for cleaning purposes except where
reduced to less than 30 psi, and then only with effective chip guarding
and proper personal protective equipment.
8. Unless the equipment has quick change connectors (with internal check
valves), shut off the air at the air supply valve ahead of the hose before
breaking the connection.
8. Scaffolding and work platforms shall require toe boards around the edge.
9. Tools and equipment will be stored in appropriate containers/boxes to
prevent dropped objects.
10. Hot Work will not be performed overhead in areas where the potential for
hot slags, sparks or molten metal to contact employees working below
without covering by fire blanket or other similar protections.
11. Tools, materials, will never be placed or stored on beams, pipes, valves
unless they are secured.
12. Proper tool holsters shall be used when working at height/elevated area.
1. All such facilities shall contain adequate number of suitable fire extinguisher.
Contractors must conduct periodical inspection to ensure fire extinguisher
and others emergency equipment maintained in good condition.
2. Each facility shall have evacuation procedure posted at regular interval
throughout. Shall ensure that the facility evacuation procedures remain in
clear view to all.
3. All facility occupants shall be made aware of the evacuation procedures and
the relevant assembly/muster points for that facility.
4. Lightning protection shall be provided to all such facilities. The electrical
installation of such facilities shall be approved standard and comply with
regulation electrical installation.
5. All emergency exits, shall be clearly marked by an A4 sized poster/notice. All
emergency exits shall remain free from obstruction at all time. Any
obstruction found shall be removed immediately.
6. At no time will rubbish, refuse and combustible materials be permitted to
accumulate within any facility. All rubbish, refuse and combustible shall be
removed from yard to a designated tipping area. Open burning of rubbish,
refuse and combustible material generated by such facilities will not be
permitted at any location within project boundary.
7. All facilities must be kept clean and tidy at all time. Any spillage shall be
cleaned immediately.
14.19 Scaffolding
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 44 OF 54 0
1. Scaffold material and structures shall conform to Applicable Laws, local and
standards
2. Only tubular and coupling scaffolding material allowed for erection of
scaffolding. A / H-Frame scaffolding is restricted to 6 m in height / 3 tier
high.
3. Scaffolds shall only be assembled, dismantled and modified by competent
persons from the scaffold company with appropriate training and
certification.
4. The work area must be clearly identified by signs and barriers during the
assembly and dismantling of scaffolds.
5. Signs marked with "DO NOT USE SCAFFOLD" shall be clearly displayed at
all potential access points to avoid unauthorized use of the scaffold during
its construction, disassembly, and modification and before it has been
approved for use.
6. Scaffold inspections shall only be performed by competent persons certified
by an appropriate level of training and formally authorized by their
employer to perform scaffold inspections.
14.20 SIMOPS
1. SIMOPS is define as execution of 2 or more operations with potential
interaction that could lead to an increase of risk or introduction of new
hazards to each other’s.
2. SIMOPS procedure should be established as a guideline to identify and
manage simultaneous activities. Construction will provide the SIMOPS
procedure with the participation of HSE and other required discipline.
or splices with insulating quality equal to that of the cable are provided.
Exposed metal parts must be insulated.
6. Ground return cables must have current carrying capacity equal to or
exceeding the total maximum output capacities of the welding unit. Do not
use electrical conduits or structures or pipelines containing gas or flammable
liquids as part of the grounding circuit system.
7. Arc welding rames must be grounded, either through a third wire in the cable
containing the circuit conductor or through a separate wire at the source of
the current. Grounding circuit resistance must be low enough to permit
sufficient current to flow to cause the fuse or circuit breaker to interrupt the
current.
8. When machines are not in use, the power supply switch shall be shut off and
the electrodes removed and the holders placed to prevent employee injury.
9. Always wear safety glasses, face shield, protective gloves, suitable
protective clothing, hard hat, steel toe boots and hearing protection and
dust mask if necessary. Keep other employees away while operating power
tool
10. Always use proper guard with grinding wheel, it protects operator from
broken wheel fragments. Turn the wheel guard so that the closed area is
towards the operator.
11. Ensure that sparks produced during work do not constitute a risk to the
user or other personnel and are not able to ignite inflammable substances.
Endangered areas must be protected with flame-resistant covers. Make
sure that fire-risk areas are always provided with suitable fire extinguishers.
12. Never use cutting discs for grinding purposes. Cutting discs must not be
subjected to any lateral pressure
13. Disconnect the plug form the power source before making any adjustments,
changing accessories, or storing the tool. Such preventive safety measures
reduce the risk of starting the tool accidentally.
14. Jewelry, long hair or loose clothes can be caught in moving parts. Keep
them away
15. Avoid accidental starting. Be sure switch is off before plugging in. Carrying
tools with your finger on the switch or plugging in tools that have the
switch on invites accidents.
16. Ensure that the accessories used always fulfill the following minimum
requirements. Respect the maximum grinding-disc diameter. The diameter
of the central hole in the grinding disc (3) must fit the inner flange (10)
without any play. Do not use any adapters or reducers.
14.23 Welfare
1. Site management will provide service and maintain reasonable Site facilities
according to the number of its personnel, Applicable Laws and general
standards of health and hygiene and responsible for maintaining its
facilities.
2. Site management shall install and maintain hygiene and sanitary facilities
fully adequate in size, number and configuration
3. Site management shall be responsible for providing fresh drinking water for
its personnel
4. Rest shelters must be provided to protect the workers from severe weather
conditions
16. COMMUNICATION
16.1 Tool Box Meeting
Tool Box Meeting shall be conducted daily. Supervisor shall instruct their
personnel to work safely on the projects, during tool box meetings and as
otherwise needed.
Tool Box Meetings:
1.Continues HSE education at the project performs through an effective “Tool
Box Meeting”. To accomplish this objective company decided the use of
“TBM”.
2.The “TBM” is a two-way directions communication pattern, which shall
inform each employee of any additional or new HSE messages not
delivered during his period of indoctrination; briefings shall determine
task, hazards/ risk at task be performed; tool and equipment which will
be used, readiness of personnel, both physically and mentally; Details
shall be recorded by an assigned personnel in each group; Supervisor in-
charge shall monitor and keep documentation of his group.
3.Information from the HSE Section, information about other general aspects,
and any new subject shall be transmitted to the supervisor, who in turn
instructs his subordinates. In case of any HSE information or questions,
which the workers have, shall be transmitted to their supervisor, for direct
follow up or in turn pass it along to Superintendent.
4.The “TBM” shall be considered means of two-way communication. To
have an effective and efficient TBM, all Line Supervisor’s shall
prepare:
5.Cover topics related to HSE aspects in his task and prevention to avoid
injury /damages:
a. HSE of workers (physical & mental) on the job.
b. Critical steps, Hazards on the job and hazard prevention (JSA).
c. Tools and equipment condition.
d. Understanding of the workers how to perform safely – aware and
seriousness.
e. Spirit announcement – theme shall be in accordance with the
existing HSE campaign launched.
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 48 OF 54 0
f. Time during Tool Box meeting shall not be used for general
grouping or social conversation, but used for the constructive
transmission of valuable information.
6. TBM lead by the HSE and Supervisor
a. The Supervisor conducts the meetings for his personnel, assign person
to record notes and obtains a signed attendance list of all
participants for each meeting.
b. The record and attendance list shall be given every day to HSE Section
administrator.
2. Superintendent/Engineer
1. Responsible as the executor of the investigation for the case of accident
over first aid. Superintendent / Engineer shall obtain correct information
from employees involved in the event, for the completeness of the
investigation and follow-up on the improvements to be suggested.
2. Responsible for possible incident impact on work / personnel in other
work areas
3. Compulsory to know the calculation of the cost of losses arising as a
result of an incident
4. The Superintendent acts as a member of the investigation team.
3. HSE Manager/Officer.
1. Responsible as an HSE expert staff, always assisting the investigation
team and always provide directions, suggestions and inputs related to
rules, procedures, instructions, standards, codes of ethics etc.
2. Acting as vice chairman of the investigation team.
4. Project/Site Manager
1. Acting as Chairman of the investigation team
2. Responsible for monitoring investigation process and reviewing the
results of the investigation (incident review)
DOCUMENT NUMBER:
PROJECT HEALTH SAFETY AND C.21007 PHSE-011
ENVIRONMENT PLAN
DATE OF ISSUED :
10 MAY 2021
UNIT ISSUING : APPROVED BY: PAGE : REV
HSE PROJECT MANAGER 51 OF 54 0
2. Investigation Report
If potential is found to lead to a greater risk of loss (LTI & Fatal), an
incident investigation report should be made