(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
Task details
Company: PT KOIN KONSTRUKSI Area : BOILER AREA
Drill Date: Sept 6, 2020 (Plan)
Description of task:
Oil Spill from heavy equipment on ground Boiler
Type of rescue
Confined Space Rescue Working At Height Rescue
Deep Excavation Rescue Working near or above water (Fall Into Water Rescue)
Restricted Work Area Rescue Diving Rescue
Cleaning oil spill
Communications: Methods to be employed between the worker and supervisor / rescue team
Direct voice communication Mobile phone Megaphone Hand flare
Whistle Two-way radios chanel No....... Air horn Other................
IRTA 0813-2502-5575
Fire Warden, Attendant/ Standby personnel
HANAFI 0822-6150-8080
Other Support Personell WANTURI ‘081313230701
i.e Crane operator and rigger
If the site rescue team is unable to affect a rescue within 5min, Emergency Services are to be called on HDEC incident
comander or deputy.
Note: The supervisor shall be prepared to provide the following information to emergency services as a minimum:
Location and Injured person condition
Page 1 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
Are operators trained competent & in date in use of rescue equipment? Yes No
Are rescue training records in date? Yes No
Are there a sufficient number of rescuers and other personel available? Yes No
Are all emergency personeell aware about emergency instruction and procedure? Yes No
Is rescue equipment selected appropriate for nature of work? Yes No
Have assessments been made of anchor points, and are they in date for test? Yes No
What obstructions are in the way of reaching the Injured person, suspended person? (Detail below – sketch location of emergency
equipment, access, pick up
Page 2 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
Safety of rescuers: Tick as appropriate
Page 3 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
Safety of rescuers: Tick as appropriate
Page 4 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
Safety of rescuers: Tick as appropriate
Has consideration been made to method of attaching the Injured person? (Detail below emergecy instruction)
In case of one heavy equipment (Crane 220T) was get oil leakage on hydraulic part when lifting activity on
BOILER area happened, report to Supervisor, Safety personnel or ERT in charge, do not panic
Stop related activity
Give detail report information about Crane 220T condition including part of hydraulic that was damage
Make sure material already release on below elevation when operator know that the hydraulic was leakage
KOIN safety personnel report to ERT KOIN commander
ERT KOIN commander will forward this information to first aider and evacuate team, wheatear any victim from
workers, ERT KOIN Commander also ask to foreman cleaning bring equipment and tools to directly toward to
scene and bring the cleaning team
First aider and evacuate team observer arrived at the scene, soon they do observer to Crane 220T and around
environment at boiler ground, after confirm that no victim in this accident, first aider report to ERT KOIN
Commander.
Directly by radio, KOIN ERT commander makes sure to foreman cleaning that already stand by on scene. KOIN
ERT commander by radio inform to evacuate team to install hard barricade around 220T and standby to monitor
the spill. Cleaning team give a sand around the leakage area the purpose is to absorb the oil with the sand after
that cleaning team preparing sack, team cleaning load the sand to sack and preparing light vehicle to transfer
sack to B3 storage.
After all finish team cleaning continue to clean leakage with spray with water and made clean leakage area.
After all finish evacuate team report to ERT Commander that oil spill already handle with safe, hard barricade
can be open again, lifting activity can continue again.
Page 5 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
How will rescuers get to casualty? Tick as appropriate
Rescue ladder system ☐ Rescue haul system ☐
Entry rescue ☐ Forcible entry ☐
Pull casualty in through scaffold ☐ Pull casualty up through floor/slab/roof ☐
Climb / abseil down building / structure ☐ Suspended access equipment ☐
Aerial equipment from ground ☐ Crane man basket ☐
AED Crane
Signature:
Date
EQUIPMENT USED :
1. BROOM 6. BUCKET
Page 6 of 7
EMERGENCY RESCUE PLAN
(Critical Activities)
Cirebon 2, 1 X 1000 MW Coal Fired Power Plant Project
2. WISTLE
3. HARD BARRICADE
5. A SAND