You are on page 1of 9

EARTHWORKS 5) Soil poisoning:

a. Applying chemical treatments to the soil to


1) Excavation: eliminate or control pests, weeds, or pathogens.
a. Clearing the site of any obstacles or debris. b. Following safety protocols and guidelines for
b. Marking out the area to be excavated according to handling and applying soil poisons.
engineering plans. c. Ensuring proper coverage and penetration of the
c. Using heavy machinery such as excavators or soil poison to effectively treat the target areas.
bulldozers to dig and remove soil. d. Monitoring the treated soil to assess effectiveness
d. Ensuring proper safety measures are in place, and reapplying treatments as necessary.
such as shoring or trench boxes if required. e. Disposing of any leftover chemicals or containers
e. Regularly inspecting the excavation to check for in accordance with environmental regulations.
stability and potential hazards.
2) Backfill and compaction:
a. Bringing in suitable fill material to replace the STRUCTURAL WOKRS
excavated area.
b. Layering the fill material in accordance with Concreting and formworks:
engineering specifications. 1). Prepare formwork structural works:
c. Compact each layer of fill material using
compactors or rollers to achieve the desired a. Cutting and assembling formwork components such as
density. plywood sheets, timber planks, or steel panels
d. Ensuring proper compaction to prevent settling according to the structural drawings and specifications.
and maintain structural integrity. b. Ensuring that the formwork is adequately braced and
3) Grading and compaction: supported to withstand the pressure exerted by the
a. Using grading equipment such as graders or wet concrete.
bulldozers to shape the land to the desired c. Securing the formwork in place using clamps, nails, or
contours. screws to prevent shifting during concrete placement.
b. Ensuring proper drainage by grading the land
2). Install formwork supports and bracing:
away from structures or towards designated
drainage areas. a. Erecting temporary supports, such as props or
c. Compacting the graded surface using rollers or scaffolding, to hold the formwork in position at the
compactors to achieve the specified density. desired elevation.
d. Checking the finished grade against engineering b. Installing diagonal bracing or lateral supports to ensure
plans to ensure accuracy. stability and prevent the formwork from collapsing
4) Gravel bedding and compaction: under the weight of the concrete.
a. Spreading a layer of gravel or crushed stone to c. Checking and adjusting the supports and bracing as
provide a stable base for structures or utilities. necessary to maintain proper alignment and stability
b. Compacting the gravel layer to achieve the throughout the concreting process.
desired density and stability.
c. Ensuring proper thickness and uniformity of the
gravel layer according to project specifications.
d. Inspecting the finished gravel bedding for any
unevenness or defects.
3). Check formwork dimensions and alignments: b. Preparing the forms and reinforcement for the concrete
elements, such as footings, foundation walls, and slabs.
a. Verifying that the formwork dimensions match the c. Supervising the pouring of concrete to ensure proper
dimensions specified in the structural drawings, placement and consolidation.
including height, width, and thickness. d. Monitoring the concrete temperature and slump during
b. Using measuring tools such as tape measures or laser placement to ensure quality and workability.
levels to ensure accurate alignment and positioning of e. Using vibration equipment to consolidate the concrete and
the formwork. remove air voids, ensuring structural integrity.
c. Checking for any deviations or discrepancies in 3) Strike off and finish concrete surfaces:
formwork dimensions and making adjustments as a. After pouring, using screeds or straightedges to level and
needed to maintain structural integrity and dimensional smooth the surface of the freshly poured concrete.
accuracy. b. Performing any necessary finishing techniques, such as
4). Apply form release agent: troweling or brooming, to achieve the desired surface
texture.
a. Applying a form release agent to the interior surfaces c. Ensuring uniformity and consistency in the finish across the
of the formwork to prevent the concrete from sticking entire concrete surface.
and facilitate easy removal of the forms after curing. d. Checking for any defects or imperfections and addressing
b. Spraying or brushing the release agent onto the them promptly to achieve a high-quality finish.
formwork surfaces evenly and ensuring complete 4) Cure concrete using curing compounds or curing blankets:
coverage. a. Applying curing compounds or membranes to the surface of
c. Following manufacturer instructions regarding the the freshly poured concrete to retain moisture and promote
application and drying time of the release agent to proper curing.
ensure effective performance. b. Ensuring even coverage of the curing compound and
following manufacturer's recommendations for application
and curing time.
Cast-In-Place Concrete c. Alternatively, using curing blankets or wet curing methods to
protect the concrete from drying out too quickly and ensure
1) Set up concrete batching plant:
adequate strength development.
a. Selecting an appropriate location for the batching plant,
d. Monitoring the curing process and taking appropriate
considering access for concrete trucks and proximity to the
measures to maintain optimal curing conditions, such as
construction site.
shading the concrete from direct sunlight or protecting it from
b. Setting up the batching plant equipment, including concrete
rain.
mixers, aggregate bins, cement silos, and admixture storage
5) Saw contraction joints as required:
tanks.
a. Determining the appropriate locations for contraction joints
c. Calibrating the batching plant to ensure accurate proportions
based on the size and layout of the concrete elements and
of materials in the concrete mix.
the anticipated shrinkage of the concrete.
d. Conducting regular maintenance and inspections of the
b. Using concrete saws equipped with diamond blades to cut
batching plant to ensure smooth operation throughout the
contraction joints to the specified depth and spacing.
construction process.
c. Ensuring straight and clean cuts to control cracking and
2) Pour concrete for footings, foundation walls, slabs, etc.:
promote proper expansion and contraction of the concrete.
a. Coordinating with the concrete supplier to schedule
d. Removing any debris or residue from the saw cuts and
deliveries based on the construction timeline and
sealing the joints as necessary to prevent water infiltration.
requirements.
MASONRY WORKS
Masonry Reinforcements: Concrete Masonry Units (CMU):

1) Procure and Deliver Masonry Reinforcement: 1) Procure and Deliver Concrete Masonry Units:

a. Identify the required masonry reinforcement types and a. Identify the types, sizes, and quantities of concrete masonry
quantities from structural drawings. units (CMU) required for the project from architectural and
structural drawings.
b. Source masonry reinforcement materials from suppliers,
ensuring compliance with project specifications. b. Source CMU materials from suppliers, ensuring they meet
project specifications and quality standards.
c. Coordinate delivery schedules to ensure timely arrival of
reinforcement materials to the construction site. c. Coordinate delivery schedules to ensure timely arrival of
CMU materials to the construction site.
d. Verify the quality and quantity of masonry reinforcement
upon delivery, checking for any damage or discrepancies. d. Verify the quality and quantity of CMU upon delivery,
checking for any damage or discrepancies.
2) Fabricate Masonry Reinforcement Elements:
2) Lay Out CHB Walls According to Drawings:
a. Review structural drawings to determine the dimensions,
spacing, and types of reinforcement required. a. Review architectural and structural drawings to determine
the layout and dimensions of CHB walls.
b. Cut steel bars to the specified lengths using cutting tools
such as saws or torches. b. Mark wall locations and dimensions on the prepared footing
or foundation, following the drawings.
c. Bend steel bars into the required shapes and configurations
using bending equipment. c. Use string lines, chalk lines, or other layout tools to establish
precise wall positions and alignments.
d. Weld or tie reinforcement elements together according to
engineering and design specifications. 3) Lay First Course of CHBs on Prepared Footing/Foundation:

3) Install Masonry Reinforcement: a. Prepare the footing or foundation surface by cleaning and
leveling as necessary.
a. Prepare wall cavities and designated locations for the
installation of masonry reinforcement. b. Apply a bed of mortar on the prepared footing or foundation.

b. Position reinforcement elements within wall cavities, c. Place the first course of concrete masonry units (CMU) on
ensuring proper alignment and spacing. the mortar bed, ensuring proper alignment and level.

c. Secure reinforcement in place using wire ties, clips, or d. Use a level and mallet to adjust CMU as needed to achieve
mortar, as appropriate. straight and plumb walls.

d. Install additional reinforcement at critical locations such as


corners, openings, or areas prone to structural stresses.

e. Verify compliance with structural drawings and specifications


throughout the installation process.
4) Install Vertical and Horizontal Reinforcement: Masonry Assembles:

a. Insert vertical reinforcement bars into designated cores of 1. Apply Rough Plastering to Masonry Walls using Mortar Mix:
CMU as specified in the structural drawings.
 Prepare the mortar mix to the required consistency for
b. Install horizontal reinforcement (e.g., bond beams, lintels) at plastering.
specified locations within the wall.
 Apply a coat of mortar to the masonry walls using a trowel.
c. Secure reinforcement in place using mortar or grout,
ensuring proper embedment and alignment.  Roughly spread the mortar over the surface of the walls,
covering joints and irregularities.
5) Continue Layering CHBs:
 Ensure even distribution of mortar to achieve uniform
a. Apply mortar to the horizontal joints of the first course of coverage.
CMU.
2. Roughly Trowel Mortar onto CHB Surfaces to Cover Joints and
b. Place subsequent courses of CMU on top of the first course, Irregularities:
staggering joints for stability.
 Mix mortar to the appropriate consistency for troweling.
c. Ensure proper alignment and level of each course as the
wall is built upward.  Apply mortar to the surface of concrete masonry units (CMU)
using a trowel.
6) Fill CHB Cores with Grout or Mortar as Necessary:
 Roughly trowel the mortar to cover joints and irregularities in
a. Fill designated cores of CMU with grout or mortar to provide
the CMU surface.
additional reinforcement and stability.
 Work the mortar into the surface to ensure adequate
b. Use a grout pump or mortar bag to fill cores completely and
coverage and adhesion.
ensure proper consolidation.
3. Texture or Pattern the Plaster Surface as Required:
7) Install Bond Beams and Lintels as Specified:
 Use texturing tools or techniques to create desired patterns
a. Place bond beams and lintels at specified intervals or
or textures on the plaster surface.
locations within the CMU wall.

b. Ensure proper alignment and embedment of bond beams  Follow architectural plans or design specifications for the
and lintels within the mortar joints. desired finish.

c. Securely bond bond beams and lintels to adjacent CMU  Apply texturing evenly across the surface to maintain
units to provide structural support. consistency in appearance.
4. Allow Plaster to Cure and Set Before Further Finishing: b. Remove soil and debris from the excavation site, ensuring a
clean and stable work area.
 Monitor the curing process to ensure proper hydration of the
plaster. c. Shape the excavation to match the dimensions of the septic
tank and allow for proper installation.
 Protect the plastered surface from excessive moisture loss
or drying too quickly. 4) Fabrication of Steel Frame for Septic Tank:

 Allow sufficient time for the plaster to cure and set before a. Fabricate a steel frame or reinforcement structure for the
proceeding with further finishing. septic tank according to engineering specifications.

b. Cut and weld steel components to the required dimensions


and configuration.
Sewer and Drainage:
c. Ensure the frame provides sufficient support and
1) Installation of Pipes: reinforcement for the septic tank structure.
a. Determine the layout and route of sewer and drainage pipes 5) Steel Frame Installation:
based on the architectural and plumbing drawings.
a. Lower the fabricated steel frame into the excavated area for
b. Excavate trenches according to the planned pipe layout, the septic tank.
ensuring proper slope for drainage.
b. Position the frame securely in place, ensuring proper
c. Lay pipes in the trenches, joining them using appropriate alignment and level.
fittings and couplings.
c. Secure the frame to the surrounding soil or foundation using
d. Ensure proper alignment and grade of pipes for efficient anchors or braces.
drainage flow.
d. Verify the stability and integrity of the installed steel frame.
e. Secure pipes in place using supports or bedding materials
as necessary. 6) Concreting of Septic Tank:

2) Layout of Septic Tank: a. Construct the septic tank using reinforced concrete or
precast concrete components.
a. Determine the location and dimensions of the septic tank
based on regulatory requirements and site conditions. b. Pour concrete into the steel frame or formwork, ensuring
complete filling and consolidation.
b. Mark out the area for excavation and installation of the septic
tank, following architectural and engineering plans. c. Level and finish the concrete surface to the desired
specifications.
c. Ensure adequate clearance from buildings, property lines,
and water sources. d. Allow the concrete to cure and set according to the
recommended time frame before further handling or
3) Excavation of Septic Tank: backfilling.
a. Excavate the designated area for the septic tank to the
required depth and dimensions.

Water System:
1) Installation of Pipes: ELECTRICAL WORKS
a. Determine the layout and routing of water supply pipes 1. Installation of Conduits:
based on architectural and plumbing drawings.
 Determine the routing and placement of electrical conduits
b. Select appropriate piping materials such as PEX, copper, or based on electrical plans and building codes.
PVC based on local codes and project requirements.
 Select appropriate conduit types (e.g., PVC, metal) based on
c. Cut pipes to the required lengths using pipe cutters or saws, application and environmental conditions.
ensuring clean and square cuts.
 Cut conduits to the required lengths using conduit cutters or
d. Install pipe fittings such as elbows, tees, and couplings as saws, ensuring clean and straight cuts.
needed to connect pipes and navigate around obstacles.
 Secure conduits in place using straps, clamps, or hangers to
e. Secure pipes in place using straps, hangers, or supports to
maintain proper spacing and alignment.
prevent sagging or movement.
 Install conduit bends, elbows, and junction boxes as needed
f. Test the installed pipes for leaks and proper water flow,
to navigate around obstacles and change direction.
conducting pressure tests as necessary.
 Verify that conduit runs comply with electrical code
g. Insulate pipes located in unconditioned spaces to prevent
requirements for fill capacity and maximum bending radius.
freezing during cold weather.
2. Installation of Wires:
2) Installation of Plumbing Fixtures:

a. Procure plumbing fixtures including sinks, toilets, showers,  Pull electrical wires through installed conduits using fish
bathtubs, and faucets according to project specifications. tapes, cable pullers, or wire guides.

b. Prepare mounting locations for each fixture, ensuring proper  Ensure proper sizing and type of wires according to electrical
spacing and alignment with plumbing connections. load requirements and circuit designations.

c. Install mounting brackets or supports for each fixture  Strip insulation from wire ends and terminate them securely
securely to walls or floors. into electrical boxes, switches, outlets, or junctions.

d. Connect water supply lines to each fixture, ensuring proper  Connect wires to terminal screws, wire nuts, or splice
sizing and sealing of connections to prevent leaks. connectors following color-coding and wiring diagrams.

e. Install drain lines and traps for wastewater disposal,  Properly dress and bundle wires within conduits and junction
ensuring proper slope and venting to prevent blockages and boxes to minimize clutter and maintain organization.
odors.

f. Test each plumbing fixture for proper functionality, including


water flow, drainage, and flushing.

g. Make any necessary adjustments or repairs to ensure all


fixtures operate correctly and meet quality standards.

3. Installation of Switches and Outlets:


 Mount electrical boxes for switches and outlets at designated  Label the main electrical panel or switchgear with
locations based on electrical plans. appropriate markings and warnings for safety and
identification purposes.
 Secure boxes in place using screws or anchors, ensuring
they are level and flush with the wall surface. THERMAL AND MOISTURE PROTECTION
 Install switches, receptacles, and dimmers into electrical Fabrication of Roofing Materials:
boxes, making sure they are properly aligned and oriented.
 Procure roofing materials such as shingles, tiles, or metal
 Connect wires to switch terminals and outlet receptacles, panels according to project specifications.
ensuring proper polarity and grounding.
 Prepare roofing materials for installation by cutting, shaping,
 Test switches and outlets for proper operation and safety, or otherwise fabricating them to fit the roof layout.
verifying continuity and insulation resistance.
 Cut shingles or tiles to size using roofing knives, shears, or
4. Installation of Electrical Fixtures: saws, ensuring accurate dimensions and clean edges.
 Procure electrical fixtures such as lighting fixtures, ceiling  Shape metal panels or flashing using metal brakes, snips, or
fans, and appliances according to project specifications. bending tools to match roof contours and angles.
 Mount fixtures securely to ceilings, walls, or other surfaces  Apply protective coatings or treatments to roofing materials
using appropriate hardware and mounting brackets. as necessary to enhance durability and weather resistance.
 Connect fixture wires to electrical circuitry, ensuring proper 2. Installation of Roofing Materials:
wiring connections and grounding as required.
 Prepare the roof surface by removing old roofing materials,
 Test fixtures for proper functionality and safety, including repairing damaged areas, and ensuring a clean, smooth
illumination, operation of switches or controls, and electrical substrate.
insulation.
 Install underlayment and waterproofing membrane to provide
 Make any necessary adjustments or repairs to ensure all a moisture barrier and enhance roof protection.
fixtures are installed correctly and meet quality standards.
 Lay out roofing materials according to roof plans and
5. Installation of Main Power Line: specifications, starting from the eaves and working upward.
 Coordinate with utility providers to establish the main  Secure roofing materials to the roof deck using nails, screws,
electrical service to the building. adhesives, or other appropriate fasteners.
 Install the main electrical service panel or switchgear  Align and overlap successive rows of shingles, tiles, or
according to utility specifications and electrical codes. panels to ensure proper water shedding and
weatherproofing.
 Connect the main power line to the service panel or
switchgear, ensuring proper sizing and termination.  Install flashing and trim pieces around roof penetrations,
edges, and valleys to prevent water intrusion and ensure a
 Test the main power line for voltage, current, and continuity,
watertight seal.
verifying proper electrical supply to the building.
 Seal joints, seams, and penetrations with caulking or 2. Installation of Stair Railings:
sealants to provide additional protection against moisture
infiltration.  Determine the design and layout of stair railings based on
architectural drawings and building codes.
 Inspect the completed roofing installation for proper
alignment, fastening, and weatherproofing, making any  Procure stair railing materials such as balusters, handrails,
necessary adjustments or repairs to ensure a high-quality and newel posts according to design specifications.
finish.  Install newel posts at the top and bottom of stairs, securing
them to the floor or landing with screws or anchors.

NON-STRUCTURAL WORKS  Attach handrails to newel posts and walls using brackets or
rail fittings, ensuring a secure and sturdy connection.
1. Installation of Doors and Windows:
 Install balusters or spindles between the handrail and the
 Procure doors and windows according to architectural stair tread or stringer, spacing them evenly according to
specifications, ensuring they meet quality and size code requirements.
requirements.
 Secure balusters in place using screws or dowels, ensuring
 Prepare door and window openings by removing any they are properly aligned and parallel to each other.
obstructions and cleaning the surrounding surfaces.
 Test stair railings for stability and safety, applying pressure
 Install door frames and window frames securely into the to ensure they can support weight and withstand use.
rough openings, ensuring proper alignment and level.
 Make any necessary adjustments or repairs to ensure stair
 Shim frames as needed to ensure they are plumb and railings meet safety standards and provide a secure
square, using shims and a level to make adjustments. handhold for users.

 Attach door and window frames to the surrounding structure


using screws or nails, ensuring a tight fit.

 Install weatherstripping and insulation around the perimeter


of doors and windows to provide a tight seal against air and
water infiltration.

 Hang doors on hinges and install hardware such as handles,


locks, and hinges according to manufacturer instructions.

 Install window sashes and hardware, ensuring smooth


operation and proper sealing against the frame.

 Test doors and windows for proper operation, adjusting as


necessary to ensure smooth opening and closing.
 Allow the first coat of paint to dry completely before applying
additional coats as needed to achieve the desired color and
coverage.

 Sand between coats if necessary to smooth out any


FINISHES imperfections and ensure a professional finish.

1. Smooth Plastering: 3. Installation of Tiles:

 Prepare the surfaces on both the ground and second floors  Prepare the substrate on both the ground and second floors
by cleaning them thoroughly and removing any dust or by ensuring it is clean, level, and free of debris.
debris.  Lay out the tiles according to the desired pattern and
 Apply a bonding agent or primer to the surfaces to enhance spacing, using tile spacers to maintain even grout lines.
the adhesion of the plaster.  Apply thin-set mortar or tile adhesive to the substrate using a
 Mix the plaster according to manufacturer instructions to notched trowel, working in small sections.
achieve the desired consistency.  Press the tiles firmly into place, ensuring they are level and
 Apply the plaster evenly onto the walls and ceilings using a aligned correctly with neighboring tiles.
trowel or plastering tool, ensuring consistent coverage.  Use a tile cutter or wet saw to cut tiles as needed to fit
 Smooth out the plaster surface with a float or trowel, around obstacles or along edges.
removing any excess material and creating a uniform finish.  Allow the adhesive to cure for the recommended time before
 Allow the plaster to dry completely before sanding down any grouting the tiles.
imperfections and applying additional coats if necessary.  Apply grout to the joints between the tiles using a grout float,
 Sand the dried plaster to achieve a smooth and even surface pressing it firmly into the gaps and smoothing it out.
suitable for painting or tiling.  Wipe off excess grout from the surface of the tiles with a
2. Painting: damp sponge, being careful not to disturb the grout lines.

 Prepare the surfaces for painting by filling any cracks or  Allow the grout to dry completely before sealing the tiles to
holes with spackling compound and sanding them smooth. protect them from moisture and stains.

 Apply a coat of primer to the plastered surfaces to improve


paint adhesion and coverage.

 Select the desired paint color and type (e.g., latex, oil-based)
for both interior walls and ceilings.

 Stir the paint thoroughly before application to ensure uniform


color and consistency.

 Use brushes, rollers, or sprayers to apply the paint evenly


onto the surfaces, working from top to bottom.

You might also like