Four Laning of Harda to Teamagaon section (Harda - Betul Pkg-1) NH-47(Old NH-59A) from Design Ch. 0.

000 To Design
Ch. 30.000 (Length - 30.00 Km) under Bharatmala Pariyojana Phase - 1 (Economic Corridor) in the state of Madhya
Pradesh on HAM Mode
Client : National Highway Authority of India
Independent Engineer : Lion Engineering Consultant Private Limited
Concessionaire : Harda Pathways Private Limited
EPC Contractor : Prakash Asphaltings & Toll Highways India Limited

Calibration Of WMM Plant (Kadola)


Date of Calibration 12.07.2023 Due Date :- 11.01.2024
Make : Material per m. length : 42.2/1.315= 32.09 kg.
No. of Feeders: 4 (Four) Length of gathering belt 26.3 M.
Speed of gathering belt : 1.315 m/sec. (1 st to 4th Feeder )
Rated Capacity of the Plant : 200TPH. Required discharge of the beltb : 42.2KG/sec.
Present Plant Capacity : 152 TPH

Constituent Weight : 40mm (35%)= 11.23 Kg., 20 mm (20%) = 6.418 Kg. ,10mm (12%) = 3.85 Kg., Dust (33%) = 10.58 Kg. , Water
(6.05%) = 9.196 Kg.

Feeder No.1
14000
40mm 40 mm
Feed Weight 12000
Rate in gm
30 6850 10000
35 8750
40 10450 8000
45 11600
6000
50 13100
4000

2000

0
25 30 35 40 45 50 55

Feed Rate Per Minute

Feeder No.2
20 mm 20 mm
Feed Weight 7000
Rate in gm
12 3400 6000
14 4700
16 5600 5000

18 6550
4000
20 7150
3000

2000

1000

0
11 12 13 14 15 16 17 18 19 20 21

Feed Rate Per Minute

For Contractors Rep. For ConcessionaireRep. For Independent Engineer Rep.


Four Laning of Harda to Teamagaon section (Harda - Betul Pkg-1) NH-47(Old NH-59A) from Design Ch. 0.000 To Design
Ch. 30.000 (Length - 30.00 Km) under Bharatmala Pariyojana Phase - 1 (Economic Corridor) in the state of Madhya
Pradesh on HAM Mode
Client : National Highway Authority of India
Independent Engineer : Lion Engineering Consultant Private Limited
Concessionaire : Harda Pathways Private Limited
EPC Contractor : Prakash Asphaltings & Toll Highways India Limited

Calibration Of WMM Plant (Kadola)


Date of Calibration 12.07.2023 Due Date :- 11.01.2024
Make : Material per m. length : 42.2/1.315= 32.09 kg.
No. of Feeders: 4 (Four) Length of gathering belt 26.3 M.
Speed of gathering belt : 1.315 m/sec. (1 st to 4th Feeder )
Rated Capacity of the Plant : 200TPH. Required discharge of the beltb : 42.2KG/sec.
Present Plant Capacity : 152 TPH

Constituent Weight : 40mm (35%)= 11.23 Kg., 20 mm (20%) = 6.418 Kg. ,10mm (12%) = 3.85 Kg., Dust (33%) = 10.58 Kg. , Water
(6.05%) = 9.196 Kg.

Feeder No.3
10 mm
Feed Weight 5000
10mm
Rate in gm
4500
6 2050
4000
12 2350
18 3450 3500
24 3900 3000
30 4700
2500

2000

1500

1000

500

0
0 5 10 15 20 25 30 35

Feed Rate Per Minute

Feeder No.4
Stone Dust Stone Dust
Feed Weight 14000
Rate in gm
15 4200 12000
20 6900
10000
25 9100
30 10700 8000
35 12900
6000

4000

2000

0
10 15 20 25 30 35 40

Feed Rate Per Minute

For Contractors Rep. For ConcessionaireRep. For Independent Engineer Rep.


Four Laning of Harda to Teamagaon section (Harda - Betul Pkg-1) NH-47(Old NH-59A) from Design Ch. 0.000 To Design
Ch. 30.000 (Length - 30.00 Km) under Bharatmala Pariyojana Phase - 1 (Economic Corridor) in the state of Madhya
Pradesh on HAM Mode
Client : National Highway Authority of India
Independent Engineer : Lion Engineering Consultant Private Limited
Concessionaire : Harda Pathways Private Limited
EPC Contractor : Prakash Asphaltings & Toll Highways India Limited

Calibration Of WMM Plant (Kadola)


Date of Calibration 12.07.2023 Due Date :- 11.01.2024
Make : Material per m. length : 42.2/1.315= 32.09 kg.
No. of Feeders: 4 (Four) Length of gathering belt 26.3 M.
Speed of gathering belt : 1.315 m/sec. (1 st to 4th Feeder )
Rated Capacity of the Plant : 200TPH. Required discharge of the beltb : 42.2KG/sec.
Present Plant Capacity : 152 TPH

Constituent Weight : 40mm (35%)= 11.23 Kg., 20 mm (20%) = 6.418 Kg. ,10mm (12%) = 3.85 Kg., Dust (33%) = 10.58 Kg. , Water
(6.05%) = 9.196 Kg.

Water

Feed Weight 12000 Water


Rate in gm
11000
4 5850 10000
6 6950 9000
8000
8 8300
7000
10 9400 6000
12 10550 5000
4000
3000
2000
1000
0
3 4 5 6 7 8 9 10 11 12 13
Feed Rate Per Minute

For Contractors Rep. For ConcessionaireRep. For Independent Engineer Rep.


Four Laning of Harda to Teamagaon section (Harda - Betul Pkg-1) NH-47(Old NH-59A) from Design Ch. 0.000 To Design
Ch. 30.000 (Length - 30.00 Km) under Bharatmala Pariyojana Phase - 1 (Economic Corridor) in the state of Madhya
Pradesh on HAM Mode
Client : National Highway Authority of India
Independent Engineer : Lion Engineering Consultant Private Limited
Concessionaire : Harda Pathways Private Limited
EPC Contractor : Prakash Asphaltings & Toll Highways India Limited

Calibration Of WMM Plant (Kadola)


Date of Calibration 12.07.2023 Due Date :- 11.01.2024
Make : Material per m. length : 42.2/1.315= 32.09 kg.
No. of Feeders: 4 (Four) Length of gathering belt 26.3 M.
Speed of gathering belt : 1.315 m/sec. (1 st to 4th Feeder )
Rated Capacity of the Plant : 200TPH. Required discharge of the beltb : 42.2KG/sec.
Present Plant Capacity : 152 TPH

Constituent Weight : 40mm (35%)= 11.23 Kg., 20 mm (20%) = 6.418 Kg. ,10mm (12%) = 3.85 Kg., Dust (33%) = 10.58 Kg. , Water
(6.05%) = 9.196 Kg.

Required
Design Aggregate Feed Rate Per
Type of Material Material Weight
Blending (%) Minute
in (gm)

40mm 35 11230 43

20mm 20 6418 17.8

10mm 12 3850 24

Stone Dust 33 10580 29.1

Water 6.05 9196 10

For Contractors Rep. For ConcessionaireRep. For Independent Engineer Rep.